Decision The Committee:- i. Noted the contents of the report; ii. Agreed to invite the new CHORD Project Officer to the next Area Committee when they are in post; and iii. Agreed to bring a report to the Area Committee after every CHORD Project Board, so that all Members not on the CHORD project Board can be updated. (Ref: Report by CHORD Project Manager dated 2 nd April 2013, submitted).
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
ARGYLL AND BUTE COUNCIL OBAN, LORN & ISLES AREA COMMITTEE
Development and Infrastructure Services 10TH APRIL 2013
CHORD PROGRAMME AND CHORD OBAN UPDATE
1.0SUMMARY 1.1 The purpose of this paper is to update Oban, Lorn and the Isles Area Committee on the delivery timescales for the CHORD projects, in particular Oban CHORD, and on the new three year CHORD Consultancy Framework.
2.0RECOMMENDATIONS 2.1 That the Oban, Lorn and the Isles Area Committee note the contents of this paper.
3.0DETAIL
3.1Details of the projected delivery timescales for all CHORD projects are outlined in Table 1 below.
Campbeltown THI n/a Apr ‘09 Sep ‘09 Sep ‘14 Berthing June ‘09 May ‘13 Jun ‘13 Apr’ 14 Facility Kinloch Road June ‘09 Apr ‘10 Nov ‘10 May ‘13 Regeneration Helensburgh Town Centre June ‘09 Sep ‘11 April ‘13 June ‘14 and West Bay Oban Bay / April ‘11 *Oban IBC Oct ‘13 Apr ‘15 Harbour completed Jan’12 FBCs being developed.
Rothesay THI June ‘09 May ‘10 Apr ‘11 Apr ‘16 *Pavilion June ‘09 Mar ‘11 July ‘15 Dec ‘16 Dunoon Queens Halls June ‘10 Apr ‘12 March ‘14 Jun ‘15 Phase 1
Footnotes: * Timespan between Rothesay Pavilion FBC and Implementation date is due to progressing HLF application: securing HLF Stage 1, progressing to Stage 2 (decision July 14) and securing funding from Creative Scotland etc. 3.2 Oban CHORD has a funding allocation of £6.9 million. An Interim Business Case for the release of £1.84 million was approved by the CHORD Programme Board and Council in early 2012. In addition, £195,000 was approved for additional revenue funding.
3.3At the Oban CHORD Project Board meeting on the 27 March 2013, the Board instructed officers to progress discrete business cases in order that the drawdown of the remaining Oban CHORD monies, £4.865 million, can be approved by the CHORD Programme Board and Council.
3.4Table 2 below outlines the proposed utilisation of the Oban CHORD Capital budget allocation of £6.9m.
Table 2 - Proposed breakdown of the £6.9m Oban Bay North Lighting South Project Allocated Total Public Pier Strategy Pier Manager to Realm Quarter Revenue £2.6m £3.5m £0.1m £0.36m £0.145m £0.195m £6.9m
3.5The intention is to deliver the above four projects by the following dates:
Oban Bay Public Realm November 2014 North Pier Quarter April 2015 Oban Bay Lighting November 2013 South Pier EFF To be advised, following decision on funding application.
3.6The procurement of the new three year CHORD Consultancy Framework, anticipated potential value of £1.8m, has now been completed. The top three tenders were Parsons Brinckerhoff, Amey and Capita. The purpose of this Framework is to augment the capabilities and expertise of the CHORD Programme Office and the various project teams already established, in order to deliver the works contained in the Business Cases. It will also allow the Programme Office to cope with increases and peaks in workload, and retain flexibility of resources. Having the Framework in place gives the Programme Office the opportunity to effective and efficiently drawdown professional services where the Council does not have the skills or capacity in house. The Council has given no guarantee as to the nature or value of work to be awarded to the appointed Consultants under the Consultancy Framework Agreement. The CHORD Programme Board has been kept informed of this process and the outcome.
3.7The Consultancy Framework Agreement shall encompass a wide range of multi- disciplinary functions and activities and includes: Project Management; Architectural and Surveying services; Civil and Structural Engineering; CDM-C (Construction Design and Management).
In terms of specific project requirements, this will include design team services for the Queens Hall project in Dunoon and the Oban Bay Public Realm projects. 4.0 IMPLICATIONS
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Oban Lorn & The Isles Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Roads and infrastructure updateDecision The Oban, Lorn and the Isles Area Committee noted the contents of the report. (Reference: Report by Executiv...
Oban PVA Flood Risk Management UpdateDecision The Oban, Lorn and the Isles Area Committee:- 1) considered the contents of this report; and 2) noted the co...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.