Decision The Committee:- i. Noted the progress of the Roads Reconstruction Programme for 2012-13 and the proposals for 2013-14 within the £21M works; and ii. Agreed that the proposals for use of the additional capital funding which will be available to OLI following the Council decision of 21 st March would come to the Business Day on 8 th May. (Ref: Report by Head of Roads and Amenity Services dated 28 th March 2013, submitted).
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1This report advises Members of the progress being made with regard to the delivery of the overall Roads Reconstruction Programme 2012 - 15. This report reviews the works carried out in Year 1, 2012-13 and the proposed programme for year 2, 2013-14.
1.2In 2011, the Council decided to increase investment in upgrading its road network following successive poor winters, and subsequently delivered a £7M programme of works which made an immediate and positive impact on the Council’s roads network. In February 2012, the Council approved a further £21M investment in roads reconstruction for 2012-15.
Recommendation
2.1That Committee notes the progress of the Roads Reconstruction Programme for 2012-13 and the proposals for 2013-14 within the £21M works
3 DETAIL
3.1The focus of the roads reconstruction programme has been to recover the network through the delivery of a mix of carriageway resurfacing schemes, patching/surface dressing and insitu road surface recycling, which follow the principles set out within the proposed Roads Asset Management and Maintenance Strategy.
3.2The summary table below highlights the positive and visible impact of the works undertaken to date. By March 2013 the Council had upgraded over a quarter of its “A” class roads and almost 300km of roads in total, within the last 24 months, as indicated below.
Table 3.2 Road Treatment % Treatment % Total Treatment Total Treatment category 2011/12 2012/13 Length as a % of network length 2011-13 A 55.76 km = 10% 93.37 km = 17% 149.13 km 27% B 26.846 km = 4% 58.912 km = 10% 87.76 km 14% C 12.374 km = 3% 4.008km = 1% 16.38 km 4% U 18.860 km = 3% 17.553 km = 2% 36.41 km 5% 289.68km
3.3The current 3 year capital investment programme will allow the Council to upgrade over 50% of its class A roads and 30% of its class B roads by 2015, which will make a significant and positive impact upon the local economy, connectivity and the quality of life of our communities.
1 3.4 The Roads Reconstruction Programme has been delivered by a mixed economy model with the Council’s in house team delivering carriageway resurfacing and patching works across the Council area. In Mull, Islay, Jura and Kintyre resurfacing and patching works have been delivered by the Council’s contractual partner Breedon and their locally based sub-contractors. Unit cost for surfacing carried out by the Councils in-house teams compare favourably with unit costs from Breedon’s. Surfacing dressing has been delivered by Kiely Brothers who were awarded the contract for the Council wide area.
3.5The Capital budget was accelerated in Year 1 of the £21M budget to achieve an early benefit to road condition and partly as preparation for future year’s operations. A record of the impact on the Capital budget, scheme by scheme in the OLI Area for Year 1 is attached in Appendix 1a&b
3.6The above service delivery model will be used in the Year 2 programme for the Council network as indicated in the Schemes List for the OLI Area as detailed in Appendix 2. At present the Budget allocation is based on the re-profiled sum remaining in the £21M programme, distributed approximately equally over the remaining year 2 and 3.
3.7Recently announced additional funding from the Scottish Executive which the Council has allocated to additional Roads schemes are at present being assessed. A future paper will detail these schemes and how they may affect the sequence of operations. Where operational efficiency dictates, the present sequence of schemes will be adjusted, which may result in some sites commencing at earlier or later dates.
4 CONCLUSION
4.1This report updates Members on the progress being made to upgrade the Council’s road network through the delivery of the Roads Reconstruction Programme 2012-15.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Oban Lorn & The Isles Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Roads and infrastructure updateDecision The Oban, Lorn and the Isles Area Committee noted the contents of the report. (Reference: Report by Executiv...
Oban PVA Flood Risk Management UpdateDecision The Oban, Lorn and the Isles Area Committee:- 1) considered the contents of this report; and 2) noted the co...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.