CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Argyll and Bute Council
Mid Argyll, Kintyre & the Islands Area Committee, Wednesday 8 April 2015 at 10.00am

CHORD CAMPBELTOWN BERTHING FACILITY PROJECT UPDATE

Agreed Committee 1 paper

Mid Argyll, Kintyre & the Islands Area Committee agreed this item on Wednesday 8 April 2015. Below is the council's own wording, with the papers it was decided on.

Item15

Resolved

Decision 1. Members agreed to note the contents of the report; and 2. noted that officers would continue to procure a sustainable operator whilst managing an interim temporary solution to accommodate incoming enquiries and bookings from March until the operator is appointed at the start of May 2015. (Ref: Report by Executive Director of Development and Infrastructure Services, dated 8 April 2015, submitted.) Councillor MacMillan left the meeting at 1.35pm.
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Mid Argyll, Kintyre & the Islands Area Committee

Executive summary

This report outlines progress to date in the delivery of the CHORD Campbeltown Berthing Facility Project with specific information on the operator tender and the critical timeline for completing the project.

As outlined in the previous update of 5 November 2014, the primary risks concerned the cost submissions from the tender returns for the works and ensuring that an appropriate operator is in place.

The risks concerned with the cost submissions for the works have been addressed and a contractor was appointed in December 2014. As instructed by members a funding contribution was sought and secured from HIE (£120,000) and a reduction in costs, £25,000 was negotiated with the contractor.

It is anticipated that the berthing facility will be fully operational and open for business in May 2015 in time for the start of the sailing season provided the piling goes according to plan.

The original tender for an operator was sent out in December 2014, two submissions were received but as the returns did not meet the required quality standards, a new tender was issued on Friday 6th March 2015, to be returned by the 27th March 2015. It is anticipated that the award will be made on the 6 May 2015.

It is recommended that members:

1.1Note the contents of the paper; and

1.2Instruct officers to continue to procure a sustainable operator whilst managing an interim temporary solution to accommodate incoming enquiries and bookings from March until the operator is appointed at the start of May 2015

1 ARGYLL AND BUTE COUNCIL MAKI AREA COMMITTEE

DEVELOPMENT AND INFRASTRUCTURE SERVICES 8 APRIL 2015

CHORD CAMPBELTOWN BERTHING FACILITY PROJECT UPDATE

2.0INTRODUCTION

2.1The purpose of this report is to update members on the progress to date in the delivery of the Campbeltown Berthing Facility, both in terms of the works and the subsequent operation of the facility.

Recommendations

It is recommended that members:

3.1Note the contents of the paper; and

3.2Instruct officers to continue to procure a sustainable operator whilst managing an interim temporary solution to accommodate incoming enquiries and bookings from March until the operator is appointed at the start of May 2015

4.0DETAILS

4.1Since the last report on 5 November 2014, GSS was appointed in December to undertake the works, to date the contractor is on track to complete the pontoon construction works by the end of March/ beginning of April, provided there are no issues with the piling works, which are due to commence on the 9th March 2015.

4.2The contract was awarded with the two component parts, the pontoons and the shower block. The latter is contractually due for completion by the 28 May 2015, thus the overall contract completion date is the 28 May 2015.

4.3Transfer of the Assets from Campbeltown Berthing Company (CLBC) to Argyll and Bute Council was concluded in November 2014.

4.4The original tender for an Operator was sent out in December 2014, two submissions were received but as the returns did not meet the required quality standards, a new tender was issued on Friday 6th March 2015, to be returned by the 27th March 2015. It is anticipated the successful operator will be appointed at the 2 beginning of May 2015

4.5In the event that a satisfactory operator cannot be found, the proposed safe guard position could be that the Council runs the facility under its existing Harbour Authority with additional human resources funded through the income received from the new facility. Members will be consulted if this situation arises.

4.6In the interim period between now and when an operator is appointed, incoming bookings and enquiries are being accommodated by the Harbour Master in Campbeltown and will continue to do so until a successful operator is appointed. CLBC have agreed to leave a voice mail message on the berthing facility phone re- directing callers to the Harbourmaster so that no potential business is lost.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CHORD CAMPBELTOWN BERTHING FACILITY PROJECT UPDATEReport 75 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 13 attended
JA
Councillor John ArmourMember, present
AB
Antonia BairdOfficer, expected
RC
Councillor Rory ColvilleChair, present
RC
Councillor Robin CurrieMember, present
AH
Councillor Anne HornMember, present
LI
Lynsey InnisSecretary, expected
DK
Councillor Donald KellyMember, present
SL
Sally LoudonOfficer, expected
DM
Councillor Donald MacMillanVice-Chair, present
JM
Councillor John McAlpineMember, apologies
AM
Councillor Aileen MortonMember, expected
DP
Councillor Douglas PhilandMember, present

All 13 on the meeting page

On this subject at Argyll and Bute

Search all
  1. CHORD CAMPBELTOWN BERTHING FACILITY PROJECT UPDATEThis decision
  2. Campbeltown chord surplus fundsApproved
  3. Campbeltown chord position statementAgreed
  4. Campbeltown CHORD Position StatementAgreed
  5. CHORD Campbeltown Berthing Facility Project UpdateAgreed
  6. Campbeltown chord - kinloch road regeneration project - acha fundingApproved

More from Argyll and Bute Mid Argyll, Kintyre & the Islands Area Committee

All decisions
MeetingDecisionOutcome
2 Sep 2026 Charts (argyll and the isles)Decision The Mid Argyll, Kintyre and the Islands Area Committee noted the information provided. (Reference: Presentat... Noted Open
2 Sep 2026 Supporting communities fund 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee agreed that the 21 applications, marked as ‘Award’ an... Agreed Open
2 Sep 2026 Roads and infrastructure services updateDecision The Mid Argyll, Kintyre and the Islands Area Committee noted the contents of the report. (Reference: Report ... Noted Open
2 Sep 2026 Lochgilphead conservation area regeneration scheme (cars) - final project reportDecision The Mid Argyll, Kintyre and the Islands Area Committee noted: 1. the content of the report and noted that Lo... Noted Open
2 Sep 2026 Area committee quarterly performance reports – fq1 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee noted the performance and supporting commentary as pr... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies