Decision The Policy and Resources Committee – 1. Approved the request from Campbeltown Community Business (CCB) for a contribution of £40,000 towards the capital costs of the restoration of Campbeltown Picture House; 2. In respect of Kintyre Sea Sports (KSP), agreed the recommendations set out at 3.1 1) i ) and ii); 3. Noted that Kintyre Sea Sports (KSP) had indicated it had no plans to make any approach to the Council for further funding if the Full Business Case proves positive. (Reference: Report by Executive Director – Development and Infrastructure Services dated 29 May 2017, submitted; and Notice of Motion by Councillor Aileen Morton, seconded by Councillor Gary Mulvaney, tabled)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1This report assesses two external funding requests to be allocated from surplus CHORD funds following approval by the Policy and Resources Committee:
1) from Kintyre Seasports for £20,000 of funding to go towards the preparation of a Full Business Case for the Kintyre Seasports Project (KSP) which has a total cost of circa £80,000. The balance of the required amount is to come from private investors, the Sailing Club and KSP partners. 2) from Campbeltown Community Business for £40,000 to support the capital costs of the Restoration of The Picture House. If approved, the £40,000 will be used to help meet the cost of; the fit out of the foyer and catering facilities and the additional costs incurred as a result of extensive damp and dry rot rectification works.
1.2Kintyre Seasports is a new partnership comprising 14 partners from the Kintyre area (see Appendix 1) aiming to be a hub for water sports activities in Campbeltown. Kintyre Seasports will be based in new premises at Dalintober close to the site of the existing yacht club on reclaimed land, owned by Campbeltown Sailing Club. The centre will facilitate all water sports activities within the Campbeltown Loch area, with other non-water based activities also to be supported.
1.3Campbeltown Community Business (CCB) is at an advanced stage of restoring the `A’ Listed Picture House as an `atmospheric cinema’ with new facilities improving the cinema going experience and ensuring viability of the community based business. On completion the Picture House will offer:- a 193 seat restored historic cinema auditorium also capable of use for live music and drama; a new 52 seat auditorium, a new foyer and café area; an exhibition area; a meeting/committee room; and up to date low energy infrastructure.
1.4CCB is already in receipt of grant funding of £190,000 from the Council for the cinema project. This includes £40,000 CHORD funding that was approved in May 2015. To date £153,134.89 has been paid to CCB against total expenditure of over £2million. RECOMMENDATIONS
1.6That members note the content of this report and consider:
1) The request from Kintyre Seasports for £20,000 to assist with the preparation of a Full Business Case for the Kintyre Seasports Project. If the grant is approved it will be subject to the following conditions:
i) Kintyre Seasports providing evidence that the remainder of the funding is in place to complete the Full Business Case. ii) Evidence that Kintyre Seasports has carried out a competitive tendering process to appoint the external consultants who will be preparing the Full Business Case.
2) The request from Campbeltown Community Business for an additional contribution of £40,000 towards the capital costs of the Restoration of The Picture House. ARGYLL AND BUTE COUNCIL POLICY AND RESOURCES COMMITTEE
DEVELOPMENT AND 29 June 2017 INFRASTRUCTURE SERVICES
CAMPBELTOWN CHORD SURPLUS FUNDS
2.0INTRODUCTION
2.1This report has been produced to assess two external funding requests for surplus Campbeltown CHORD funds. The Kintyre Seasports partnership has requested £20,000 to assist with the preparation of a Full Business Case for the Kintyre Seasports Project (KSP). Campbeltown Community Business (CCB) has requested £40,000 towards the capital costs of the Restoration of The Picture House
2.2On the 16th March 2017 the Policy and Resources Committee agreed that the Development and Infrastructure Services Department should undertake further work to assess both requests, as set out in paragraphs 4.5.5 to 4.5.8 of the report considered at the Mid Argyll, Kintyre and the Islands Area Committee on the 1st February 2017. It was also agreed that the outcome of both assessments should be reported back to a future meeting of the P&R Committee for further consideration.
2.3Both assessments have now been undertaken.
Recommendations
3.1That members note the content of this report and consider:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Budget outlook 2027-28 to 2031-32Decision The Policy and Resources Committee noted the current Budget Outlook position for the period 2027-28 to 2031-...
Funding request from local organisationsDecision The Policy and Resources Committee – 1. agreed to award a one-off grant of £36,000, to be paid from the Prio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.