CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Argyll and Bute Council
Policy and Resources Committee, Thursday 12 May 2016 at 11.00am

CAMPBELTOWN CHORD POSITION STATEMENT

Agreed Committee 2 papers

Policy and Resources Committee agreed this item on Thursday 12 May 2016. Below is the council's own wording, with the papers it was decided on.

Item10

Resolved

Decision The Committee agreed that up to £15,000 is allocated from the remaining £197,625 of Campbeltown CHORD Funds to allow the purchase of a suitable mechanical sweeper for use in Campbeltown Town Centre to ensure that the improved appearance of the town is maintained due to the start of the summer months. (Reference: Recommendation from the Mid Argyll, Kintyre and Islands Area Committee held on 6 April 2016 and report by Executive Director – Development and Infrastructure Services dated 3 May 2016, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Policy and Resources Committee

Executive summary

1.1At the meeting of the Mid Argyll, Kintyre and the Islands Area Committee held on 6 April 2016, the Committee considered a report on the Campbeltown CHORD position statement which set out the remaining balance of funds at £197,625. It was noted that the Council has still to determine how unallocated CHORD funds are to be treated and that this will be the subject of a future report however in the interim the MAKI Committee agreed to recommend to the Policy and Resources Committee the purchase of a Mechanical Street Sweeping Machine for use in Campbeltown and consequently the Policy and Resources Committee is asked to consider that additional recommendation.

The Policy and Resources Committee is asked to agree:-

That up to £15,000 is allocated from the remaining Campbeltown CHORD funds to allow the purchase of a suitable mechanical sweeper for use in Campbeltown Town Centre to ensure that the improved appearance of the town is maintained. Argyll and Bute Council Policy and Resources Committee

Development and Infrastructure 12 May 2016 Services

RECOMMENDATION FROM MAKI AREA COMMITTEE – CHORD POSITION STATEMENT

2.0INTRODUCTION

2.1At the meeting of the Mid Argyll, Kintyre and the Islands Area Committee held on 6 April 2016, the Committee considered a report on the Campbeltown CHORD position statement which set out the remaining balance of funds at £197,625. It was noted that the Council has still to determine how unallocated CHORD funds are to be treated and that this will be the subject of a future report however in the interim the MAKI Committee agreed to recommend to the Policy and Resources Committee the purchase of a Mechanical Street Sweeping Machine for use in Campbeltown and consequently the Policy and Resources Committee is asked to consider that additional recommendation.

Recommendation

3.1Policy and Resources Committee is asked to agree:-

That up to £15,000 is allocated from the remaining £197,625 of Campbeltown CHORD funds to allow the purchase of a suitable mechanical sweeper for use in Campbeltown Town Centre to ensure that the improved appearance of the town is maintained as we enter the summer months.

4.0DETAIL

4.1At the meeting of the Mid Argyll, Kintyre and the Islands Area Committee held on 6 April 2016, the Committee considered a report on the CHORD position statement. During the course of the discussion, Councillor Colville asked the Members to agree to an additional recommendation in relation to the purchase of a suitable mechanical sweeper for use in Campbeltown.

4.2The decision of the Area Committee was:-

The Committee agreed the recommendations contained at Section 3 of the report, but with the additional recommendation to recommend to Policy and Resources Committee that up to £15,000 is allocated from the remaining CHORD funds to allow the purchase of a suitable mechanical sweeper for use in Campbeltown Town Centre to ensure that the improved appearance of the town is maintained.

3.3The recommendations at Section 3 of the report highlighted to Members that any decision in relation to the allocation of CHORD funds, which was outwith the original business case of the CHORD project would require to be referred to Policy and Resources Committee for approval. The additional recommendation in relation to the mechanical sweeper is outwith the original business case and is therefore being referred for final approval.

4.0CONCLUSION

4.1Policy and Resources Committee is being asked to consider the recommendation from the MAKI Area Committee in relation to the purchase of a suitable mechanical sweeper using some of the unallocated CHORD funds.

5.0IMPLICATIONS

5.1Policy None

5.2Financial Up to £15,000 will be allocated from the remaining balance within the Campbeltown CHORD funds.

5.3Legal None

5.4HR None

5.5Equalities None

5.6Risk None

5.7Customer Service None

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CAMPBELTOWN CHORD POSITION STATEMENTReport 71 KB DownloadRead as text
PDF
MAKI AC to P&R 12 May 2016Report 47 KB Download

At this meeting

Whole meeting

Who was there

11 of 18 attended
DW
Councillor Dick WalshChair, present
RC
Councillor Rory ColvilleMember, present
RC
Councillor Robin CurrieMember, present
MC
Councillor Maurice CorryMember, apologies
MD
Councillor Mary-Jean DevonMember, present
RM
Councillor Roderick McCuishMember, present
IM
Councillor Iain MacLeanMember, absent
AM
Councillor Alistair MacDougallMember, apologies
NM
Councillor Neil MacIntyreMember, apologies
AM
Councillor Aileen MortonMember, present
EM
Councillor Ellen MortonVice-Chair, present
GM
Councillor Gary MulvaneyMember, apologies

All 18 on the meeting page

On this subject at Argyll and Bute

Search all
  1. CAMPBELTOWN CHORD POSITION STATEMENTThis decision
  2. Campbeltown chord surplus fundsApproved
  3. Campbeltown CHORD Position StatementAgreed
  4. CHORD Campbeltown Berthing Facility Project UpdateAgreed
  5. Chord campbeltown berthing facility project updateAgreed
  6. Campbeltown chord - kinloch road regeneration project - acha fundingApproved

More from Argyll and Bute Policy and Resources Committee

All decisions
MeetingDecisionOutcome
20 Aug 2026 Financial monitoring overview – 30 june 2026Decision The Policy and Resources Committee – 1. agreed to recommend that Council approve the budget changes in Secti... Agreed Open
20 Aug 2026 Budget outlook 2027-28 to 2031-32Decision The Policy and Resources Committee noted the current Budget Outlook position for the period 2027-28 to 2031-... Noted Open
20 Aug 2026 Potential impact of iran conflict - updateDecision The Policy and Resources Committee noted the content of the submitted report. (Reference: Report by Section ... Noted Open
20 Aug 2026 Funding request from local organisationsDecision The Policy and Resources Committee – 1. agreed to award a one-off grant of £36,000, to be paid from the Prio... Agreed Open
20 Aug 2026 Scottish languages act 2025 - areas of linguistic significanceDecision The Policy and Resources Committee – 1. noted the progress being made to ensure that the Council meets its s... Noted Open