Mid Argyll, Kintyre & the Islands Area Committee agreed this item on Wednesday 3 June 2015. Below is the council's own wording, with the papers it was decided on.
Decision Members agreed:- 1. To note the contents of the report; 2. To note the proposed opening date of 27 June 2015; and 3. To Congratulate the team on their hard work and commitment to service. (Ref; Report by Executive Director of Development and Infrastructure Services, dated 3 June 2015, submitted.)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Mid Argyll, Kintyre & the Islands Area Committee
Executive summary
This report outlines progress to date in the delivery of the CHORD Campbeltown Berthing Facility Project with specific information on the operator tender and the critical timeline for completing the project.
As outlined in the previous update of 8 April 2015, the primary risks concerned the sourcing of an appropriate operator and the completion of the piling. The risks concerned with the piling have been addressed and have been secured within the budget and project timeline. An operator was appointed on the 11th May 2015.
It is anticipated that the berthing facility will be fully operational and open for business in May 2015 in time for the start of the sailing season.
It is proposed to have an official opening on the 27th June 2015.
It is recommended that members:
• Note the contents of the paper • Note the proposal to have an official opening on the 27th June 2015
2.1The purpose of this report is to update members on the progress to date in the delivery of the Campbeltown Berthing Facility, both in terms of the works and the subsequent operation of the facility.
Recommendations
It is recommended that members:
3.1Note the contents of the paper
3.2Note the proposed opening date on 27th June 2015
4.0DETAILS
4.1Since the last report on 8 April 2015, GSS have completed the manufacture, supply, and installation of the Transit Berthing Facility in Campbeltown. Several small items are still in the process of being connected but the project is currently on target to complete on the 28th May 2015 as per the contract.
4.2An operator was appointed on the 11th of May 2015
4.3The seabed license from CLBC to Argyll and Bute Council is expected to be concluded by the end of May 2015.
4.4As at April 2015, the project has spent £955,415 and is on track to be delivered within budget.
5.0CONCLUSION
5.1The pontoons, bridge and shower block works are due for completion by the 28 May 2015. The total project contract completion date is the 28 May 2015.
6.0IMPLICATIONS
6.1Policy The delivery of this project fits with the Council’s Corporate Plan, Single Outcome Agreement and
2 approved Development Plan key actions and policy for safeguarding our built heritage and town centre regeneration. The economic outcomes from this project will contribute to the Council’s Economic Development Action Plan at a strategic and area based level.
6.2Financial No financial implications to date.
6.3Legal No legal issues to date.
6.4HR Personnel commitment across relevant departments for duration of project
6.5Equalities No equal opportunities implications
6.6Risk The main risk is slippage of the project programme due to unforeseen issues with the piling affecting a timeous handover of the operating contract prior the sailing season start. This has now been mitigated
6.7Customer Services There are no customer service implications
Pippa Milne, Executive Director of Development and Infrastructure Policy Lead, Ellen Morton 8 April 2015
For further information contact: Kirsteen Macdonald (Regeneration) [email protected] 01546 604 271
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Mid Argyll, Kintyre & the Islands Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Supporting communities fund 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee agreed that the 21 applications, marked as ‘Award’ an...
Roads and infrastructure services updateDecision The Mid Argyll, Kintyre and the Islands Area Committee noted the contents of the report. (Reference: Report ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.