Decision The Committee noted the contents of the report. (Ref: Report by Marine Operations Manager dated 15 th April 2015, submitted).
Oban Lorn & The Isles Area Committee noted this item on Wednesday 15 April 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision The Committee noted the contents of the report. (Ref: Report by Marine Operations Manager dated 15 th April 2015, submitted).
The main purpose of this report is to outline the situation on the state of repairs to Iona slipway.
The Council has identified the requirement to refurbish Iona slipway as a priority prior to the commencement of the 2015 summer season. George Leslie Ltd has been awarded the contract to carry out the refurbishment.
The lower (seaward) end of Iona slipway has become seriously degraded and in danger of separating from the upper end of the slipway. The Contractor is utilising concrete repairs to the lower end using pre-cast concrete beams to connect both sections. The repairs are estimated to have a life of between twenty to thirty years.
Construction started on 8 March and will continue until the 22 May, the work being undertaken in 3 phases, in advance of the summer influx of visitors to Iona.
The contract for the Iona slipway repairs has been awarded and is valued at a total of £1,248,356. In order to fund these works there is a requirement to utilise all available marine budgets both capital and revenue.
The Contractor, George Leslie Ltd, has identified several risks associated with the possibility of adverse weather and is looking at scheduling a fourth phase of work, to be completed before 22 May.
2.0INTRODUCTION
2.1The slipway at Iona has been degrading over time and this year the Council identified the requirement to refurbish the slipway as a priority prior to the commencement of the 2015 summer season. George Leslie Ltd has been awarded the contract to carry out the refurbishment.
3.1That the Area Committee notes the report. 1 4.0 DETAIL
4.1The lower (seaward) end of Iona slipway has become seriously degraded and in danger of separating from the upper end of the slipway. The Contractor proposed to utilise concrete repairs to the lower end using pre-cast concrete beams to connect both sections. These repairs are estimated to have a life of between twenty to thirty years.
4.2Work commenced on the 8 March and is scheduled to complete by 22 May with the period of 9-22 May being a demobilisation period for the contractors. Due to the state of the tides during the period of refurbishment, the actual work is split into 3 phases. Phase 1 of the refurbishment from 17-26 March is now complete and had the Contractor working on the upper half of the repair area from mid tide to low tide. The second phase will start on 15 April and is scheduled to run until the 23 April and the Contractor will work on the lower half of the repair area. A third period is scheduled from 2-8 May when the Contractor will complete the work required on the lower part of the repair area.
4.3In the event of inclement weather, the Contractor may be forced to schedule a fourth phase of work to complete the repairs but should have completed all repairs by 22 May. The first phase of work was not hampered by the weather although it is considered prudent to plan for a fourth phase.
4.4The Iona ferry continues to operate throughout this period, although a relief passenger service timetable is required during a window of 3 hours before, to three hours after, Low Water in order that the Contractor may carry out the repairs. The local community have been fully engaged with CALMAC on the revised passenger ferry service and to date no complaints have been received.
4.5The contract for the Iona slipway repairs is valued at a total of £1,248,356. The works required to repair the ferry slip on Iona have been tendered through an open competitive process and the innovative tender has been evaluated at £1,148,356 with an additional requirement of £100,000 to fund the relief passenger service from Fionnphort to Iona. In order to fund these works there is a requirement to utilise all available marine budgets both capital and revenue.
5.0CONCLUSION
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
IONA PIERReport | 70 KB | DownloadRead as text |
Follow Oban Lorn & The Isles Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Sep 2026 | Public question time part 1It was agreed therefore that the responses would not be read out but included in the minute and also emailed to the A... | Agreed | Open |
| 9 Sep 2026 | CHARTS (Argyll and Isles)Decision The Oban, Lorn and the Isles Area Committee considered and noted the information provided in the presentatio... | Noted | Open |
| 9 Sep 2026 | Roads and infrastructure updateDecision The Oban, Lorn and the Isles Area Committee noted the contents of the report. (Reference: Report by Executiv... | Noted | Open |
| 9 Sep 2026 | Oban PVA Flood Risk Management UpdateDecision The Oban, Lorn and the Isles Area Committee:- 1) considered the contents of this report; and 2) noted the co... | Noted | Open |
| 9 Sep 2026 | Argyll Square Project: Consolidated Financial Report and Delivery UpdateDecision The motion was carried by 4 votes to 2 and the Committee resolved accordingly. (Reference: A report by Secti... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.