CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Argyll and Bute Council
Oban Lorn & The Isles Area Committee, Wednesday 15 April 2015 at 10.30am

LORN ARC QUARTERLY UPDATE REPORT

Noted Committee 2 papers

Oban Lorn & The Isles Area Committee noted this item on Wednesday 15 April 2015. Below is the council's own wording, with the papers it was decided on.

Item11

Resolved

Decision The Committee: 1. Unanimously noted the current progress with the Lorn Arc Programme; and 2. Noted the progress reports will be presented to the Area Committees on a quarterly basis. (Ref: Report by Oban Regeneration Project Manager dated 27 th March 2015, submitted).
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Oban Lorn & The Isles Area Committee

Executive summary

1.1The purpose of this report is to update the OLI Area Committee on progress in delivering the Lorn Arc Tax Incremental Financing Programme and its 9 capital infrastructure investment projects led by Development and Infrastructure Services. The attached Highlight Report (Appendix A) outlines the current position of the projects as at the 23 March 2015.

1.2This report sets out the envisaged timeline for start dates for each of the nine projects within the Lorn Arc programme and provides a brief synopsis of the current position relating to each of the 9 projects.

1.3Of particular note, the Lorn Arc programme requires the first material investment in one of the sub-projects to be made before the end of September 2015. It has been determined that this first material investment should be the construction of an access road to facilitate the development of a new business park on Council owned land adjacent to Oban Airport (Project 9). Start up costs were approved for this project by Policy and Resources committee on 5th February 2015. A planning application is expected to be submitted for the proposed access road and related outline masterplan at the time of writing this report, and is expected to be determined within 4 to 6 weeks. Meanwhile, work is continuing on the production of an Economic Impact Assessment and Full Business Case (FBC) to assess the merits on implementing this project. This FBC is expected to be presented initially to a special Oban, Lorn and the Isles Area Committee on 1st May, 2015 for their views and then on to Policy and Resources Committee for determination on 14th May 2015. In addition, work is also continuing on the finalised design of the road so that the project can be tendered immediately following Committee, assuming an approval of the FBC, and importantly so that work can begin on site prior to the end of September deadline.

1.4Budget: Two of the projects have start up cost capital budgets approved and the projects are both operating within these budgets at the present time. Summary details are contained within Appendix A.

Total capital budget of £18.9m 2015 – 2020 approved borrowing Income received to date None Total capital funds committed £333,650 Total capital project spend to £13,051 date Balance of committed funds £320,599

1.6It is recommended that the OLI Area Committee:-

• Note the current progress with the Lorn Arc Programme; and • Note that progress reports will be presented to OLI Area Committees on a quarterly basis. ARGYLL AND BUTE COUNCIL Oban,Lorn and the Isles (OLI) Area Committee

DEVELOPMENT & INFRASTRUCTURE SERVICES 15th April, 2015

LORN ARC – UPDATE REPORT AS AT 23 MARCH 2015

2. INTRODUCTION

2.1This report provides an update to the OLI Area Committee on progress in delivering the Lorn Arc Tax Incremental Financing Programme and its 9 capital infrastructure investment projects led by Development and Infrastructure Services. The attached Highlight Report (Appendix A) along with a Programme Plan (Appendix B) outlines the current position of the projects as at the 23 March 2015.

Recommendation

3.1It is recommended that the OLI Area Committee:-

• Note the current progress with the Lorn Arc Programme; and

• Note that progress reports will be presented to OLI Area Committees on a quarterly basis.

4. DETAILS

4.1The envisaged timeline for start dates for each of the nine projects within the Lorn Arc programme are set out in Table 1 below.

Table 1 : Capital investment start dates

TIF Asset project Construction start date (financial yearly quarter – Q1-4)

15/16 16/17 17/18

1 - Lorn Rd / Kirk Rd Q4 Improvements, Dunbeg

2 - Gateway Features / Q4 Traffic Calming, Dunbeg

3 - Halfwayhouse Q4 Roundabout / Dunbeg Development Road, Dunbeg

4 - South Oban Q4 Development Zone

5 - North Pier Extension, Q3 Oban

6 - North Pier Q4 Streetscape, Oban

7 - Access Q2 Improvements, Barcaldine

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
FINAL Appendix AAppendix 70 KB Download
PDF
LORN ARC QUARTERLY UPDATE REPORTReport 114 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 14 attended
DC
Donald CampbellPublic, expected
MD
Councillor Mary-Jean DevonMember, present
DF
Danielle FinlaySecretary, expected
GF
Graeme ForresterClerk, expected
SL
Sally LoudonOfficer, expected
IM
Councillor Iain MacDonaldMember, present
AM
Councillor Alistair MacDougallMember, present
DM
Councillor Duncan MacIntyreMember, apologies
NM
Councillor Neil MacIntyreMember, present
IM
Councillor Iain MacLeanMember, present
SM
Shirley MacLeodOfficer, expected
RM
Councillor Roderick McCuishChair, present

All 14 on the meeting page

On this subject at Argyll and Bute

Search all
  1. LORN ARC QUARTERLY UPDATE REPORTThis decision
  2. Lorn arc tif programme dunbeg corridor updateNoted
  3. Lorn arc tax incremental finance (tif) updateNoted
  4. Lorn arc tax incremental finance programme - oban airport business park - updateNoted
  5. Lorn arc tax incremental finance programme - update reportNoted
  6. Lorn arc programme updateNoted

More from Argyll and Bute Oban Lorn & The Isles Area Committee

All decisions
MeetingDecisionOutcome
9 Sep 2026 Public question time part 1It was agreed therefore that the responses would not be read out but included in the minute and also emailed to the A... Agreed Open
9 Sep 2026 CHARTS (Argyll and Isles)Decision The Oban, Lorn and the Isles Area Committee considered and noted the information provided in the presentatio... Noted Open
9 Sep 2026 Roads and infrastructure updateDecision The Oban, Lorn and the Isles Area Committee noted the contents of the report. (Reference: Report by Executiv... Noted Open
9 Sep 2026 Oban PVA Flood Risk Management UpdateDecision The Oban, Lorn and the Isles Area Committee:- 1) considered the contents of this report; and 2) noted the co... Noted Open
9 Sep 2026 Argyll Square Project: Consolidated Financial Report and Delivery UpdateDecision The motion was carried by 4 votes to 2 and the Committee resolved accordingly. (Reference: A report by Secti... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies