Mid Argyll, Kintyre & the Islands Area Committee, Wednesday 6 April 2016 at 10.00am

Schools Redevelopment Projects

Agreed Committee 1 paper

Mid Argyll, Kintyre & the Islands Area Committee agreed this item on Wednesday 6 April 2016. Below is the council's own wording, with the papers it was decided on.

Item5

Resolved

Decision Members thanked the Schools Development Project Manager and all those involved in bringing this project forward and developing a good news story for Campbeltown and agreed to note:- 1. the project milestone of reaching Financial Close for the Campbeltown Grammar School and Oban High School redevelopment project; and 2. the key construction dates for Campbeltown Grammar School as set out in Paragraph 4.6 of the report. (Ref: Report by Executive Director of Community Services, dated 6 April 2016, submitted.)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Mid Argyll, Kintyre & the Islands Area Committee

Executive summary

1.1This report provides Members with progress on the new schools redevelopment project in partnership with hubNorth Scotland Ltd (hubNorth) to build the new Campbeltown Grammar School.

1.2The Stage 2 Submission for the Campbeltown/Oban Design Build Finance and Maintain (DBFM) was received from hubNorth in December 2015. The Submission has been reviewed by the schools redevelopment project team with support from the Council’s external Financial, Legal and Technical advisors.

1.3At its meeting on 17 March 2016, the Policy and Resources Committee agreed:  the Stage 2 Submission for the Campbeltown/Oban schools project; and  that the project could proceed to a Financial Close within the financial envelope agreed by the Council in its Capital Plan and Revenue Outlook at the budget meeting of 11 February 2016.

1.4The Scottish Futures Trust (SFT) has carried out its Key Stage Review (KSR) of the Stage 2 Submission and the SFT’s approval was received on Wednesday 23 March 2016.

1.5Financial Close on the Campbeltown/Oban schools redevelopment project was reached on Thursday 24 March 2016.

1.6The key programme construction dates for the new Campbeltown Grammar School are set out in Paragraph 4.6 hereof.

Recommendations

It is recommended that Members note: 1 The project milestone of reaching Financial Close for the Campbeltown Grammar School/Oban High School redevelopment project; and

2 The key construction dates for Campbeltown Grammar School are as set out in Paragraph 4.6 hereof.

1 ARGYLL AND BUTE COUNCIL MAKI AREA COMMITTEE

COMMUNITY SERVICES 6 APRIL 2016

NEW SCHOOLS REDEVELOPMENT PROJECT

2.0INTRODUCTION

2.1This report provides Members with progress on the Council’s new schools redevelopment project in partnership with hubNorth Scotland Ltd (hubNorth) to build a new secondary school in Campbeltown. The new school to be delivered through the Scottish Government’s Schools for the Future Programme.

2.2The Project will deliver in Campbeltown the construction of a new secondary school for pupils aged between 12 to 18, with a capacity for 500 pupils, to replace the existing Campbeltown Grammar School on the current school site, and will include the demolition of the existing school buildings, provision of an enlarged car park, landscaping and a 3G artificial turf pitch.

3.0RECOMMENDATIONS It is recommended that Members note:

3.1The project milestone of reaching Financial Close for the Campbeltown Grammar School and Oban High School redevelopment project; and

3.2The key construction dates for Campbeltown Grammar School as set out in Paragraph 4.6 hereof.

4.0DETAIL

4.1The Stage 2 Submission for the Campbeltown/Oban Design Build Finance and Maintain (DBFM) project was received from hubNorth in December 2015 and was reviewed by the schools redevelopment project team with support from the Council’s external Financial, Legal and Technical advisors. 4.2 Prior to the conclusion of the SFT’s Key Stage Review (KSR) of the Stage 2 Submission, the Council was required to discuss the progress and proposals of the project with the Scottish Government (SG) and the SFT. The discussions took the form of a presentation and workshop held on Wednesday 2 March 2016, at the SFT’s offices in Edinburgh.

The Council’s project team demonstrated through its presentation, how it has responded to achieving Scotland’s Schools for the Future 2 Programme goals within the project.

Namely:  Efficient & Effective Procurement;  Cost Efficiency;  Delivery of Schools by the Council’s Target Date of March 2018; and  Delivery of the Schools Estate Strategy Principles.

The outcome for the workshop has been a clear understanding between the parties (SG, SFT, and the Council) that the school projects are on track to achieving the four key programme goals.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Schools Redevelopment ProjectsReport 106 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 10 attended
JA
Councillor John ArmourMember, present
RC
Councillor Rory ColvilleChair, present
RC
Councillor Robin CurrieMember, present
AH
Councillor Anne HornMember, present
LI
Lynsey InnisSecretary, expected
DK
Councillor Donald KellyMember, present
DM
Councillor Donald MacMillanVice-Chair, present
JM
Councillor John McAlpineMember, present
DP
Councillor Douglas PhilandMember, present
ST
Councillor Sandy TaylorMember, present

On this subject at Argyll and Bute

Search all
  1. Schools Redevelopment ProjectsThis decision
  2. New schools redevelopment project update for dunoon primary schoolNoted
  3. New schools redevelopment project, oban high school updateNoted
  4. New schools redevelopment project update for dunoon primary schoolNoted
  5. New schools redevelopment project oban high school updateNoted
  6. New schools redevelopment projectNoted

More from Argyll and Bute Mid Argyll, Kintyre & the Islands Area Committee

All decisions
MeetingDecisionOutcome
2 Sep 2026 Charts (argyll and the isles)Decision The Mid Argyll, Kintyre and the Islands Area Committee noted the information provided. (Reference: Presentat... Noted Open
2 Sep 2026 Supporting communities fund 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee agreed that the 21 applications, marked as ‘Award’ an... Agreed Open
2 Sep 2026 Roads and infrastructure services updateDecision The Mid Argyll, Kintyre and the Islands Area Committee noted the contents of the report. (Reference: Report ... Noted Open
2 Sep 2026 Lochgilphead conservation area regeneration scheme (cars) - final project reportDecision The Mid Argyll, Kintyre and the Islands Area Committee noted: 1. the content of the report and noted that Lo... Noted Open
2 Sep 2026 Area committee quarterly performance reports – fq1 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee noted the performance and supporting commentary as pr... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies