Mid Argyll, Kintyre & the Islands Area Committee agreed this item on Wednesday 6 April 2016. Below is the council's own wording, with the papers it was decided on.
Decision Members thanked the Schools Development Project Manager and all those involved in bringing this project forward and developing a good news story for Campbeltown and agreed to note:- 1. the project milestone of reaching Financial Close for the Campbeltown Grammar School and Oban High School redevelopment project; and 2. the key construction dates for Campbeltown Grammar School as set out in Paragraph 4.6 of the report. (Ref: Report by Executive Director of Community Services, dated 6 April 2016, submitted.)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Mid Argyll, Kintyre & the Islands Area Committee
Executive summary
1.1This report provides Members with progress on the new schools redevelopment project in partnership with hubNorth Scotland Ltd (hubNorth) to build the new Campbeltown Grammar School.
1.2The Stage 2 Submission for the Campbeltown/Oban Design Build Finance and Maintain (DBFM) was received from hubNorth in December 2015. The Submission has been reviewed by the schools redevelopment project team with support from the Council’s external Financial, Legal and Technical advisors.
1.3At its meeting on 17 March 2016, the Policy and Resources Committee agreed: the Stage 2 Submission for the Campbeltown/Oban schools project; and that the project could proceed to a Financial Close within the financial envelope agreed by the Council in its Capital Plan and Revenue Outlook at the budget meeting of 11 February 2016.
1.4The Scottish Futures Trust (SFT) has carried out its Key Stage Review (KSR) of the Stage 2 Submission and the SFT’s approval was received on Wednesday 23 March 2016.
1.5Financial Close on the Campbeltown/Oban schools redevelopment project was reached on Thursday 24 March 2016.
1.6The key programme construction dates for the new Campbeltown Grammar School are set out in Paragraph 4.6 hereof.
Recommendations
It is recommended that Members note: 1 The project milestone of reaching Financial Close for the Campbeltown Grammar School/Oban High School redevelopment project; and
2 The key construction dates for Campbeltown Grammar School are as set out in Paragraph 4.6 hereof.
1 ARGYLL AND BUTE COUNCIL MAKI AREA COMMITTEE
COMMUNITY SERVICES 6 APRIL 2016
NEW SCHOOLS REDEVELOPMENT PROJECT
2.0INTRODUCTION
2.1This report provides Members with progress on the Council’s new schools redevelopment project in partnership with hubNorth Scotland Ltd (hubNorth) to build a new secondary school in Campbeltown. The new school to be delivered through the Scottish Government’s Schools for the Future Programme.
2.2The Project will deliver in Campbeltown the construction of a new secondary school for pupils aged between 12 to 18, with a capacity for 500 pupils, to replace the existing Campbeltown Grammar School on the current school site, and will include the demolition of the existing school buildings, provision of an enlarged car park, landscaping and a 3G artificial turf pitch.
3.0RECOMMENDATIONS It is recommended that Members note:
3.1The project milestone of reaching Financial Close for the Campbeltown Grammar School and Oban High School redevelopment project; and
3.2The key construction dates for Campbeltown Grammar School as set out in Paragraph 4.6 hereof.
4.0DETAIL
4.1The Stage 2 Submission for the Campbeltown/Oban Design Build Finance and Maintain (DBFM) project was received from hubNorth in December 2015 and was reviewed by the schools redevelopment project team with support from the Council’s external Financial, Legal and Technical advisors. 4.2 Prior to the conclusion of the SFT’s Key Stage Review (KSR) of the Stage 2 Submission, the Council was required to discuss the progress and proposals of the project with the Scottish Government (SG) and the SFT. The discussions took the form of a presentation and workshop held on Wednesday 2 March 2016, at the SFT’s offices in Edinburgh.
The Council’s project team demonstrated through its presentation, how it has responded to achieving Scotland’s Schools for the Future 2 Programme goals within the project.
Namely: Efficient & Effective Procurement; Cost Efficiency; Delivery of Schools by the Council’s Target Date of March 2018; and Delivery of the Schools Estate Strategy Principles.
The outcome for the workshop has been a clear understanding between the parties (SG, SFT, and the Council) that the school projects are on track to achieving the four key programme goals.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Mid Argyll, Kintyre & the Islands Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Supporting communities fund 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee agreed that the 21 applications, marked as ‘Award’ an...
Roads and infrastructure services updateDecision The Mid Argyll, Kintyre and the Islands Area Committee noted the contents of the report. (Reference: Report ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.