BUSINESS GATEWAY LOCAL GROWTH ACCELERATOR - ERDF APPLICATION
AgreedCommittee1 paper
Environment, Development and Infrastructure Committee agreed this item on Thursday 7 April 2016. Below is the council's own wording, with the papers it was decided on.
Decision The Committee agreed to:- 1. Note the scope of the proposed support to businesses. 2. Note the scale of the programme. 3. Note that no additional Council funding is required. 4. Approve the proposed launch, nothing that timescales are dependent on Scottish Government approval timescales. 5. Note the success of the application. (Reference: Report by Executive Director – Development and Infrastructure Services, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Environment, Development and Infrastructure Committee
Executive summary
1.1The new Structural Funds programme 2014-20 gives the Council the opportunity to leverage European Regional Development Fund (ERDF) monies to increase the scale and scope of support to local businesses with growth potential, via Business Gateway.
1.2In March 2015 Argyll and Bute Council submitted a Strategic Intervention application, outlining the strategic rationale, costs, outputs and activities proposed.
1.3The Strategic Intervention was approved by the Scottish Government on 14th October 2015. This gave approval to submit an Operation Application.
1.4The Operation Application was submitted on 2nd November 2015 and outlined the operation activities to support the programme approved in the Strategic Intervention. It detailed a £544,200 programme for 2015-2018 known as the Business Gateway Local Growth Accelerator Programme (BG LGAP) and requested £272,100 of ERDF funding. The proposed programme included specialist advice, growth grants, graduate placements, growth workshops, regional specific entrepreneurial support and key sector support.
1.5The £272,100 match funding contribution required from the Council can be wholly met by existing Business Gateway and Economic Development budgets. This is because existing Business Gateway activity supporting growth companies can be considered as match funding.
1.6The Scottish Government advised that they expected to make a decision on Operation Applications before the end of December 2015. In January 2016 we were advised that this had been extended to the end of March 2016.
1.7The launch of BG LGAP is wholly dependent on the timing of approval by the Scottish Government. If approved by 1st April 2016, BG LGAP activity could be ‘soft launched’ in May 2016 to businesses already engaged with Business Gateway, followed by a full launch in June 2016.
1 1.8 It is recommended that members of the Environment Development and Infrastructure Committee: note the scope of the proposed support to businesses; note the scale of the programme; note that no additional Council funding is required; and approve the proposed launch approach, noting that timescales are dependent on Scottish Government approval timescales.
2 ARGYLL AND BUTE COUNCIL Environment Development and Infrastructure Committee
DEVELOPMENT AND INFRASTRUCTURE SERVICES 7th April 2016
Business Gateway Local Growth Accelerator Programme – ERDF Application
2.0INTRODUCTION
2.1The new Structural Funds programme 2014-20 gives the Council the opportunity to leverage European Regional Development Fund (ERDF) monies to increase the scale and scope of support to local businesses with growth potential, via Business Gateway.
2.2Unlike previous programmes which operated as a competitive bid process, for this programme period the Managing Authority (Scottish Government) for the Scottish programme identified Lead Partners to deliver strategic interventions under each theme of the Structural Funds programme.
2.3Argyll and Bute Council is one of the Lead Partners agreed for the ERDF Competitiveness theme 03: Enhancing the competitiveness of small and medium sized enterprises.
2.4In March 2015 Argyll and Bute Council submitted a Strategic Intervention application, outlining the strategic rationale, costs, outputs and activities proposed.
2.5The Strategic Intervention was approved by the Scottish Government on 14th October 2015 and the Council was invited to submit a more detailed Operation Application by 2nd November 2015.
2.6The Operation Application was submitted to deadline, and outlined the operation activities to support the programme approved in the Strategic Intervention. It detailed a £544,200 programme for 2015-2018 known as the Business Gateway Local Growth Accelerator Programme (BG LGAP) and requested £272,100 of ERDF funding.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment, Development and Infrastructure Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Review of public convenience estateDecision The Environment, Development and Infrastructure Committee – 1. noted the findings of the updated baseline re...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.