CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Argyll and Bute Council

TIREE, ROTHESAY AND CRINAN CANAL CHARRETTE UPDATE

Agreed Committee 1 paper

Environment, Development and Infrastructure Committee agreed this item on Thursday 7 April 2016. Below is the council's own wording, with the papers it was decided on.

Item14

Resolved

Decision The Committee agreed to note the content of the report and the timelines for delivery of each charrette. (Reference: Report by Executive Director – Development and Infrastructure Services dated 29 February 2016, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Environment, Development and Infrastructure Committee

Executive summary

1.1This report seeks to update Members on the delivery mechanism and timescale for three charrettes, which are currently being delivered across Argyll and Bute. The charrette projects, which have secured funding from Scottish Government cover the areas of: Isle of Tiree, Rothesay town centre and the Crinan Canal corridor, including Lochgilphead and Ardrishaig.

1.2A charrette is an intensive master planning session where the community and designers collaborate to create a vision for an area. A series of discussions and workshops are held over a dedicated timeframe to generate ideas. These are subsequently distilled down into deliverable outcomes set out within an action plan. Each charrette results in a body of work which seeks to inform policy making, the future development of the areas and inform the review of the Local Development Plan (LDP).

1.3This report follows a paper considered and approved by the Planning Protective Services and Licensing Committee on 24th June 2015, which outlines three tranches of proposed charrettes within the context of the LDP Community Plans, and a subsequent report to SMT on 22nd December 2015 which outlined the scope and methodology behind each charrette, and sought the support of colleagues council-wide in relation to attending and inputting into the process.

1.4As each charrette has been instigated and taken forward by different lead partners and communities, each is noticeably different, especially in relation to the principal area of focus and emerging themes, which in turn makes the approach to delivery for each quite different from the others.

1.5The purpose of this report is therefore to provide an update on each charrette and the next steps. ARGYLL AND BUTE COUNCIL ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE COMMITTEE

DEVELOPMENT AND 7TH APRIL 2016 INFRASTRUCTURE SERVICES

TIREE, ROTHESAY AND CRINAN CANAL CHARRETTE UPDATE

Recommendations

2.1That Members note the content of this report and the timelines for the delivery of each charrette.

3.0INTRODUCTION

3.1This report seeks to update Members on the delivery mechanism and timescale for three charrettes which are currently being delivered across Argyll and Bute. The charrette projects, which secured funding from Scottish Government cover the areas of: Isle of Tiree, Rothesay town centre and the Crinan Canal corridor, including Lochgilphead and Ardrishaig.

3.2A charrette is an intensive master planning session where the community and designers collaborate to create a vision for an area. A series of discussions and workshops are held over a dedicated timeframe to generate ideas. These are subsequently distilled down into deliverable outcomes set out within an action plan. Each charrette results in a body of work which seeks to inform policy making, the future development of the areas and inform the review of the Local Development Plan (LDP).

3.3This report follows a paper considered and approved by the Planning Protective Services and Licensing Committee on 24th June 2015, which outlines three tranches of proposed charrettes within the context of the LDP Community Plans, and a subsequent report to SMT on 22nd December 2015 which outlined the scope and methodology behind each charrette and sought the support of colleagues council-wide in relation to attending and inputting into the process.

3.4As each charrette has been instigated and taken forward by different lead partners and communities, each is noticeably different, especially in relation to the principal area of focus and emerging themes, which in turn makes the approach to delivery for each quite different from the others.

3.5The purpose of this report is therefore to provide an update on each charrette and the next steps.

4.0DETAIL

Background

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
TIREE, ROTHESAY AND CRINAN CANAL CHARRETTE UPDATEReport 90 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

15 of 18 attended
JA
Councillor John ArmourMember, present
AH
Councillor Anne HornMember, present
DK
Councillor David KinniburghMember, apologies
AM
Councillor Alistair MacDougallMember, present
RG
Councillor Robert Graham MacIntyreVice-Chair, present
DM
Councillor Donald MacMillanMember, present
BM
Councillor Bruce MarshallMember, present
JM
Councillor John McAlpineMember, present
AM
Councillor Alex McNaughtonMember, present
AM
Councillor Aileen MortonMember, present
EM
Councillor Ellen MortonChair, present
ER
Councillor Elaine RobertsonMember, present

All 18 on the meeting page

More from Argyll and Bute Environment, Development and Infrastructure Committee

All decisions
MeetingDecisionOutcome
9 Oct 2026 A816 bealach mor permanent solution updateDecision The Environment, Development and Infrastructure Committee noted the following key points – 1. the £1.1m appr... Noted Open
9 Oct 2026 Review of public convenience estateDecision The Environment, Development and Infrastructure Committee – 1. noted the findings of the updated baseline re... Noted Open
9 Oct 2026 Review of roads and infrastructure services updateDecision The Environment, Development and Infrastructure Committee – 1. noted the progress to date on the RIS Review;... Noted Open
9 Oct 2026 Winter service policy 2026/27Decision The Environment, Development and Infrastructure Committee – 1. approved the 2026/27 Winter Maintenance Polic... Approved Open
9 Oct 2026 Waste management updateDecision The Environment, Development and Infrastructure Committee noted the content of the report. (Reference: Repor... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies