Decision The Committee agreed to this report being presented to the Council with the following recommendations:- 1. Note expectations that roads authorities will ‘take forward the design and delivery of a package of shared service initiatives (Option 30 report). 2. Agree to participate in the Northern Roads Collaboration Forum and recommend to Council to nominate the Chair and Vice-Chair of the Committee to represent the Council on the Forum. 3. Note that a meeting of the Forum took place in early March for Lead Members and supporting officers. 4. Note that the Forum is considered a precursor to forming a Joint Committee to support formal sharing/collaboration across roads services and that any proposal to form a Joint Committee will be submitted to a future meeting of Council. 5. Note that the Council have also been working with colleagues to the south of Argyll and Bute who have been gathering data relating to budgets, workforce and challenges and will continue with these discussions. (Reference: Report by Executive Director – Development and Infrastructure Services dated January 2016, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Environment, Development and Infrastructure Committee
Executive summary
1.1The National Roads Maintenance review in 2012 made 30 recommendations. 1 – 29 were generally operational management matters relating to good procurement, working practice etc. Argyll and Bute, like the majority of local authorities were already applying or at the very least working towards 1 – 29 in the delivery of the roads service. The 30th recommendation (option 30 as it has become known) considered a single roads authority for the whole of Scotland. Option 30, through COSLA, was put to Council Leaders who expressed concern regarding a dilution of local accountability should Option 30 be progressed. It was agreed that rather than progress with a single roads authority the existing 32 local authorities should deliver efficiencies through greater collaboration.
1.2There were a number of good examples of collaboration in place in a number of areas prior to the review, through SCOTS and local arrangements. However, a number of work streams from SCOTS have been enhanced through the Roads Collaboration Programme, facilitated by the Improvement Service. Argyll and Bute have been involved with both the former south west and northern collaborative groups. The south west group has been superseded by the City Deal group. This group is being co-ordinated by Glasgow City Council. To date we are not aware of any firm proposals coming out of the City Deal group, further updates will be provided as information is available. Argyll and Bute continue to be actively been involved with the northern group. Argyll and Bute have also been working with colleagues to the south of our area who have been gathering data relating to budgets, workforce and challenges.
1.3Subject to views from Members, Council approval will be sought to support the creation of the Northern Roads Collaboration Forum as a precursor to a future Joint Committee and to nominate the Chair and Vice-chair of this the Environment, Development and Infrastructure Committee as members of the said forum.
1.4It is recommended that Members agree to this this report being presented to Council with the following recommendations:
i. note expectations that roads authorities will ‘take forward the design and delivery of a package of shared service initiatives’ (Option 30 report);
1 ii. agree to participate in the Northern Roads Collaboration Forum and recommend to Council to nominate the Chair and Vice-chair of this Committee to represent the Council on the Forum;
iii. note that a meeting of the Forum took place in early March for Lead Members and supporting officers.
iv. note that the Forum is considered a precursor to forming a Joint Committee to support formal sharing/collaboration across roads services; and note that any proposal to form a Joint Committee will be submitted to a future meeting of Council.
v. note that the council have also been working with colleagues to the south of Argyll and Bute who have been gathering data relating to budgets, workforce and challenges and will continue with these discussions.
2 ARGYLL AND BUTE COUNCIL ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE COMMITTEE
DEVELOPMENT AND INFRASTRUCTURE SERVICES 7TH APRIL 2016
NORTHERN ROADS COLLABORATION FORUM
2.0INTRODUCTION
2.1This report outlines work currently being taken within the Scottish public roads sector to explore and develop opportunities for greater collaboration between roads authorities and highlights how this is being taken forward in the north of Scotland.
Recommendations
3.1It is recommended that Members agree to this report being presented to P&R with the following recommendations:
i. note expectations that roads authorities will ‘take forward the design and delivery of a package of shared service initiatives’ (Option 30 report);
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment, Development and Infrastructure Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Review of public convenience estateDecision The Environment, Development and Infrastructure Committee – 1. noted the findings of the updated baseline re...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.