Oban Lorn & The Isles Area Committee, Monday 11 April 2016 at 10.30am

NORTH PIER MARITIME QUARTER - PHASE 1 NORTH PIER MARITIME VISITOR CENTRE - ENHANCED DESIGN OPTIONS

Agreed Committee 1 paper

Oban Lorn & The Isles Area Committee agreed this item on Monday 11 April 2016. Below is the council's own wording, with the papers it was decided on.

Item11

Resolved

Decision The Committee:- 1. Agreed to proceed to the detailed design stage for Option One as set out in the appendix of the report; and 2. Noted the current progress with the Maritime Visitor Centre. (Ref: Report by Oban CHORD Project Manager dated 11 th March 2016, submitted).
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Oban Lorn & The Isles Area Committee

Executive summary

1.1The purpose of this paper is to present the recommendations for enhanced design options for the construction of the North Pier Maritime Visitor Centre that represent better value for money and will strengthen the existing approved Full Business Case (FBC).

1.2The attached presentation (appendix A), outlines 2 options proposed for consideration alongside the existing approved design to show how the re-design has evolved following the legal challenge and subsequent mediation discussions.

1.3It is recommended that the OLI area Committee:

 Determine to proceed to detailed design stage for Option One as set out in the attached appendix A on page 8.  Note the current progress with the Maritime Visitor Centre.

1 ARGYLL AND BUTE COUNCIL OBAN LORN and the ISLES AREA COMMITTEE

DEVELOPMENT AND INFRASTRUCTURE SERVICES 11th April 2016

North Pier Maritime Quarter – Phase 1 North Pier Maritime Visitor Centre – Enhanced Design Options

2.0INTRODUCTION

2.1The purpose of this paper is to update the OLI Area Committee on progress to date, present the enhanced design options for the development of the Maritime Visitor Centre, and secure agreement with the recommendation to progress with option 1 which will increase commercial space provision and thus provide the opportunity to strengthen the approved FBC.

Recommendations

3.1It is recommended that the OLI area Committee:

 Determine to proceed to detailed design stage for Option One as set out in the attached appendix A on page 8.  Note the current progress with the Maritime Visitor Centre.

4.0DETAILS

The development of the Maritime Visitor Centre has been in progress for three years. A timeline of key decisions is listed below in 4.1.

4.1September 12th 2013, Capita Symonds, architects appointed.

 October 22nd 2013 a workshop was attended by all the OLI councilors, the Deputy Leader of the Council, senior officers and partner stakeholders. It was unanimously agreed at this workshop that a new build option was to be delivered on the North Pier to replace the existing white building.

 December 11th 2013 OLI AC noted progress on the Maritime Visitor Centre. The paper stated that public consultation was ongoing and that target date for securing detailed design and full business case was to be September 2014.

 Following the OLI Area Committee decision on 9th April 2014, detailed design work commenced and a planning application and listed building consent

2 application were submitted on 26th June. The applications were validated and registered on 4th July.

 Conditional Planning Approval was granted by the PPSL Committee on 20th August, 2014.

 The Full Business case was signed off by Council on 25th September 2014 approving a budget allocation of £1.6 million.

 Following the issue of a Court Summons on 19th January 2015, all works on the Maritime Visitor Center ceased pending legal advice.

 Following client instruction Capita/Oberlanders submitted an amended planning application on 27th February 2015 for a revised design which reduced the scale of the canopy and the configuration of the edge to the area adjacent to the access strip at the rear of the restaurants. Once the designs were reviewed and costed the preparation of new technical drawings and tender documents was undertaken.

 Council legal officers met with counsel in Edinburgh in June 2015 to discuss a legal way forward. Mediation meeting took place on the 24th September 2015 and Heads of Terms were agreed in principal which would facilitate development to extend as far as the existing footprint of the existing white building.

 The Oban Project Manager used the interim period September – October 2015, to explore alternative options concentrating on function and affordability within the wider scheme. The main change was the scaling back of the roof canopy.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
NORTH PIER MARITIME QUARTER: PHASE 1 NORTH PIER MARITIME VISITOR CENTRE: ENHANCED DESIGN OPTIONSReport 1.2 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 9 attended
DC
David ClementsOfficer, expected
MD
Councillor Mary-Jean DevonMember, present
DF
Danielle FinlaySecretary, expected
AM
Councillor Alistair MacDougallMember, present
NM
Councillor Neil MacIntyreMember, present
IM
Councillor Iain MacLeanMember, present
RM
Councillor Roderick McCuishChair, present
JM
Councillor Julie McKenzieMember, present
ER
Councillor Elaine RobertsonVice-Chair, present

On this subject at Argyll and Bute

Search all
  1. NORTH PIER MARITIME QUARTER - PHASE 1 NORTH PIER MARITIME VISITOR CENTRE - ENHANCED DESIGN OPTIONSThis decision
  2. North pier pontoons - repair reportNoted
  3. Oban bay development / north pier extension proposalsAgreed
  4. Argyll and bute council: extension to existing car marshalling area and formation of vehicular access: land north west of the pier, craignure, isle of mull (ref: 20/00940/pp)Agreed
  5. Chord - oban: north pier harbour building and north pier pontoons - project closureNoted
  6. Chord - oban: north pier harbour building and north pier pontoons - project closureNoted

More from Argyll and Bute Oban Lorn & The Isles Area Committee

All decisions
MeetingDecisionOutcome
9 Sep 2026 Public question time part 1It was agreed therefore that the responses would not be read out but included in the minute and also emailed to the A... Agreed Open
9 Sep 2026 CHARTS (Argyll and Isles)Decision The Oban, Lorn and the Isles Area Committee considered and noted the information provided in the presentatio... Noted Open
9 Sep 2026 Roads and infrastructure updateDecision The Oban, Lorn and the Isles Area Committee noted the contents of the report. (Reference: Report by Executiv... Noted Open
9 Sep 2026 Oban PVA Flood Risk Management UpdateDecision The Oban, Lorn and the Isles Area Committee:- 1) considered the contents of this report; and 2) noted the co... Noted Open
9 Sep 2026 Argyll Square Project: Consolidated Financial Report and Delivery UpdateDecision The motion was carried by 4 votes to 2 and the Committee resolved accordingly. (Reference: A report by Secti... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies