Decision The Committee:- 1. Agreed to proceed to the detailed design stage for Option One as set out in the appendix of the report; and 2. Noted the current progress with the Maritime Visitor Centre. (Ref: Report by Oban CHORD Project Manager dated 11 th March 2016, submitted).
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1The purpose of this paper is to present the recommendations for enhanced design options for the construction of the North Pier Maritime Visitor Centre that represent better value for money and will strengthen the existing approved Full Business Case (FBC).
1.2The attached presentation (appendix A), outlines 2 options proposed for consideration alongside the existing approved design to show how the re-design has evolved following the legal challenge and subsequent mediation discussions.
1.3It is recommended that the OLI area Committee:
Determine to proceed to detailed design stage for Option One as set out in the attached appendix A on page 8. Note the current progress with the Maritime Visitor Centre.
1 ARGYLL AND BUTE COUNCIL OBAN LORN and the ISLES AREA COMMITTEE
DEVELOPMENT AND INFRASTRUCTURE SERVICES 11th April 2016
North Pier Maritime Quarter – Phase 1 North Pier Maritime Visitor Centre – Enhanced Design Options
2.0INTRODUCTION
2.1The purpose of this paper is to update the OLI Area Committee on progress to date, present the enhanced design options for the development of the Maritime Visitor Centre, and secure agreement with the recommendation to progress with option 1 which will increase commercial space provision and thus provide the opportunity to strengthen the approved FBC.
Recommendations
3.1It is recommended that the OLI area Committee:
Determine to proceed to detailed design stage for Option One as set out in the attached appendix A on page 8. Note the current progress with the Maritime Visitor Centre.
4.0DETAILS
The development of the Maritime Visitor Centre has been in progress for three years. A timeline of key decisions is listed below in 4.1.
October 22nd 2013 a workshop was attended by all the OLI councilors, the Deputy Leader of the Council, senior officers and partner stakeholders. It was unanimously agreed at this workshop that a new build option was to be delivered on the North Pier to replace the existing white building.
December 11th 2013 OLI AC noted progress on the Maritime Visitor Centre. The paper stated that public consultation was ongoing and that target date for securing detailed design and full business case was to be September 2014.
Following the OLI Area Committee decision on 9th April 2014, detailed design work commenced and a planning application and listed building consent
2 application were submitted on 26th June. The applications were validated and registered on 4th July.
Conditional Planning Approval was granted by the PPSL Committee on 20th August, 2014.
The Full Business case was signed off by Council on 25th September 2014 approving a budget allocation of £1.6 million.
Following the issue of a Court Summons on 19th January 2015, all works on the Maritime Visitor Center ceased pending legal advice.
Following client instruction Capita/Oberlanders submitted an amended planning application on 27th February 2015 for a revised design which reduced the scale of the canopy and the configuration of the edge to the area adjacent to the access strip at the rear of the restaurants. Once the designs were reviewed and costed the preparation of new technical drawings and tender documents was undertaken.
Council legal officers met with counsel in Edinburgh in June 2015 to discuss a legal way forward. Mediation meeting took place on the 24th September 2015 and Heads of Terms were agreed in principal which would facilitate development to extend as far as the existing footprint of the existing white building.
The Oban Project Manager used the interim period September – October 2015, to explore alternative options concentrating on function and affordability within the wider scheme. The main change was the scaling back of the roof canopy.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Oban Lorn & The Isles Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Roads and infrastructure updateDecision The Oban, Lorn and the Isles Area Committee noted the contents of the report. (Reference: Report by Executiv...
Oban PVA Flood Risk Management UpdateDecision The Oban, Lorn and the Isles Area Committee:- 1) considered the contents of this report; and 2) noted the co...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.