OBAN HIGH SCHOOL REDEVELOPMENT PROJECT

Noted Committee 1 paper

Oban Lorn & The Isles Area Committee noted this item on Monday 11 April 2016. Below is the council's own wording, with the papers it was decided on.

Item9

Resolved

Decision The Committee:- 1. Noted the project milestone of reaching Financial Close for the Campbeltown Grammar School and Oban High School redevelopment project; and 2. Noted the key construction dates for Oban High School as set out in Paragraph 4.6 hereof. (Ref: Report by Schools Development Project Manager dated 29 th March 2016, submitted).
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Oban Lorn & The Isles Area Committee

Executive summary

1.1This report provides Members with progress on the new schools redevelopment project in partnership with hubNorth Scotland Ltd (hubNorth) to build the new Oban High School.

1.2The Stage 2 Submission for the Campbeltown/Oban Design Build Finance and Maintain (DBFM) was received from hubNorth in December 2015. The Submission has been reviewed by the schools redevelopment project team with support from the Council’s external Financial, Legal and Technical advisors.

1.3At its meeting on 17 March 2016, the Policy and Resources Committee agreed:  the Stage 2 Submission for the Campbeltown/Oban schools project; and  that the project could proceed to a Financial Close within the financial envelope agreed by the Council in its Capital Plan and Revenue Outlook at the budget meeting of 11 February 2016.

1.4The Scottish Futures Trust (SFT) has carried out its Key Stage Review (KSR) of the Stage 2 Submission and the SFT’s approval was received on Wednesday 23 March 2016.

1.5Financial Close on the Campbeltown/Oban schools redevelopment project was reached on Thursday 24 March 2016.

1.6The key programme construction dates for the new Oban High School are set out in Paragraph 4.6 hereof.

Recommendations

It is recommended that Members note: 1 The project milestone of reaching Financial Close for the Campbeltown Grammar School and Oban High School redevelopment project; and

2 The key construction dates for Oban High School as set out in Paragraph 4.6 hereof.

1 ARGYLL AND BUTE COUNCIL OLI AREA COMMITTEE

COMMUNITY SERVICES 11 APRIL 2016

NEW SCHOOLS REDEVELOPMENT PROJECT

2.0INTRODUCTION

2.1This report provides Members with progress on the Council’s new schools redevelopment project in partnership with hubNorth Scotland Ltd (hubNorth) to build a new secondary school in Oban. The new school to be delivered through the Scottish Government’s Schools for the Future Programme.

2.2The project will deliver in Oban the construction of a new secondary school for pupils aged between 12 to 18, with capacity for 1300 pupils, to replace the existing Oban High School on the current school site and will include demolition of the existing school buildings, provision of an enlarged car park, landscaping, and provision of a pedestrian footway with lighting from the new school facilities to the grass pitches owned by the Council at Glencruitten, Oban. The existing 3G artificial turf carpet will be replaced with a new 3G carpet and shock-pad suitable for football and rugby in Year 1 of Operation.

3.0RECOMMENDATIONS It is recommended that Members note:

3.1The project milestone of reaching Financial Close for the Campbeltown Grammar School and Oban High School redevelopment project; and

3.2The key construction dates for Oban High School as set out in Paragraph 4.6 hereof.

4.0DETAIL

4.1The Stage 2 Submission for the Campbeltown/Oban Design Build Finance and Maintain (DBFM) project was received from hubNorth in December 2015 and was reviewed by the schools redevelopment project team with support from the Council’s external Financial, Legal and Technical advisors.

4.2Prior to the conclusion of the SFT’s Key Stage Review (KSR) of the Stage 2 Submission, the Council was required to discuss the progress and proposals of the project with the Scottish Government (SG) and the SFT. The discussions took the form of a presentation and workshop held on Wednesday 2 March 2016, at the SFT’s offices in Edinburgh.

2 The Council’s project team demonstrated through its presentation, how it has responded to achieving Scotland’s Schools for the Future Programme goals within the project.

Namely:  Efficient & Effective Procurement;  Cost Efficiency;  Delivery of Schools by the Council’s Target Date of March 2018; and  Delivery of the Schools Estate Strategy Principles.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
OBAN HIGH SCHOOL REDEVELOPMENT PROJECTReport 107 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 9 attended
DC
David ClementsOfficer, expected
MD
Councillor Mary-Jean DevonMember, present
DF
Danielle FinlaySecretary, expected
AM
Councillor Alistair MacDougallMember, present
NM
Councillor Neil MacIntyreMember, present
IM
Councillor Iain MacLeanMember, present
RM
Councillor Roderick McCuishChair, present
JM
Councillor Julie McKenzieMember, present
ER
Councillor Elaine RobertsonVice-Chair, present

On this subject at Argyll and Bute

Search all
  1. OBAN HIGH SCHOOL REDEVELOPMENT PROJECTThis decision
  2. Oban High SchoolNoted
  3. Oban High SchoolNoted
  4. Highland holidays: extensions and alterations to the internal layout of existing holiday park, including the installation of new water storage tanks and a sewage treatment plant (part retrospective): oban caravan and camping park gallanachmore, gallanach road, oban (ref: 24/00745/pp)Agreed
  5. Oban High SchoolNoted
  6. Oban High School Attainment ReportNoted

More from Argyll and Bute Oban Lorn & The Isles Area Committee

All decisions
MeetingDecisionOutcome
9 Sep 2026 Public question time part 1It was agreed therefore that the responses would not be read out but included in the minute and also emailed to the A... Agreed Open
9 Sep 2026 CHARTS (Argyll and Isles)Decision The Oban, Lorn and the Isles Area Committee considered and noted the information provided in the presentatio... Noted Open
9 Sep 2026 Roads and infrastructure updateDecision The Oban, Lorn and the Isles Area Committee noted the contents of the report. (Reference: Report by Executiv... Noted Open
9 Sep 2026 Oban PVA Flood Risk Management UpdateDecision The Oban, Lorn and the Isles Area Committee:- 1) considered the contents of this report; and 2) noted the co... Noted Open
9 Sep 2026 Argyll Square Project: Consolidated Financial Report and Delivery UpdateDecision The motion was carried by 4 votes to 2 and the Committee resolved accordingly. (Reference: A report by Secti... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies