Decision The Committee – 1. Noted that the current position of the Lorn Arc Programme had been reported to the Oban, Lorn and the Isles Area Committee for information. 2. Noted that Argyll and Bute Council had sent a letter to Derek MacKay MSP (Cabinet Secretary for Finance and the Constitution) formally requesting confirmation from Scottish Government of their intention to engage with the Council to find an alternative approach for the delivery of the Lorn Arc Programme and its associated outcomes. 3. Agreed that a more substantive report be prepared and reported to the first appropriate Council Committee following the planned meeting with Scottish Government Ministers on 29 March 2017. 4. Agreed that the Lorn Arc team would be delegated the authority to engage with Scottish Government officials and the Scottish Futures Trust on potential solutions and alternative funding/financing models following the substantive report to the appropriate Council Committee. 5. Noted that work continues on all current project sites. (Reference: Report by Executive Director – Development and Infrastructure Services dated 31 January 2017, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1Since the last progress update in October 2016, the following matters have been progressed.
1.2The last TIF Executive meeting with Scottish Government (“SG”) and Scottish Futures Trust (“SFT”) took place on the 5th December 2016, where the financial model update that took into account a property market conditions review was reported. The Commercial Agent’s (Ryden) report, taken together with Argyll & Bute Council’s (“ABC’s”) own knowledge of the prevailing local market conditions, suggests that timing and magnitude of future development and the associated incremental Non Domestic Rates (“NDR”) generation is unlikely to be forthcoming as anticipated in the 2013 Full Business Case (“FBC”). The result of this re-modelling exercise is that in all cases (best to worst case scenarios), there is a cash sweep deficit over the 25 year TIF period for the full potential capital spend programme of £14.74m. This exercise demonstrates that, in the present form, the full TIF programme of £14.74m is not currently affordable, based on the current NDR assumptions. It should be noted however, that the current level of approved drawdown (£1.388m, of which £0.664m has actually been drawn down and spent), is forecast as being capable of being repaid from TIF income over the life of the project.
1.3No one event or issue has led to the current affordability position, rather a combination of a number of factors such as change in property market assumptions, new business eligibility for the Scottish Government reliefs & exemptions in terms of NDR, change in Government support for the renewables industry and change in land ownership at the Barcaldine site.
1.4Given the critical nature of delivering the Project to the local area, the programme of works can be considered live and the planning and scoping of individual projects continues to be progressed. Notwithstanding this progress, the project team continues to take a cautious and prudent approach in terms of delivery and the drawdown of any further TIF Debt will continue to be subject to affordability testing and internal governance processes as outlined in the Project Initiation Document (“PID”). In this regard the Council are seeking assurance from SG and SFT that both parties will work with us to identify alternative funding sources and/ or new financing models, for the programme of works, in order that critical economic and social outcomes are secured for the Argyll & Bute area.
1.5The project team remains fully committed to delivering a programme of enabling infrastructure in the Lorn Arc area, which will bring wide ranging economic and social benefits at both a local and national level. In fact, the Project has already delivered positive outcomes for Argyll & Bute in terms of enabled development, NDR creation and an increase in local community and business confidence.
1.6Argyll & Bute Council has submitted a letter, signed by the Leader of the Council and the Policy Lead for Sustainable Economic Development, seeking confirmation from the Scottish Government of their willingness to engage with us to find alternative funding sources and/ or financing models for the delivery of the Lorn Arc programme and its associated social and economic outcomes.
1.7In addition, an options appraisal is being undertaken on how best to proceed with the development of the proposed Oban Airport Business Park, which will be presented to the first appropriate OLI Area Committee and Policy & Resources Committee.
1.8Budget: Detailed below is the current budget position for both the revenue and capital approved budget allocations.
REVENUE £000s Total approved funds 1,607 Total project spend to date January 2017 322 Balance 1,285 CAPITAL £000s Total borrowing approved 1,388 Total project spend to date January 2017 664 Balance 724
1.9It is recommended that the Policy & Resources Committee:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Budget outlook 2027-28 to 2031-32Decision The Policy and Resources Committee noted the current Budget Outlook position for the period 2027-28 to 2031-...
Funding request from local organisationsDecision The Policy and Resources Committee – 1. agreed to award a one-off grant of £36,000, to be paid from the Prio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.