Decision The Policy and Resources Committee – 1. noted the project update relating to Oban Airport Business Park; and 2. noted that another update report including the Full Business Case would be reported back to Members for consideration in December 2024. (Reference: Report by Executive Director with responsibility for Commercial Services and Executive Director with responsibility for Development and Economic Growth dated 11 September 2024, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1At May 2024 Policy and Resources Committee it was agreed to allocate £8.05m from TIF to deliver the construction of roads, infrastructure, servicing and site works. This included an immediate draw down of £1.6m to deliver the Full Business Case for the overall project.
1.2Ongoing work is also progressing in relation to identifying and securing other funded investment in the business park including and the development of commercial buildings for lease. This Full Business Case is now well underway and this paper provides an update on progress.
Recommendation
That the Policy and Resources Committee:
i. Consider this project update relating to Oban Airport Business Park; and
ii. Note another update report including the Full Business Case will be reported back to Members for consideration in December 2024. ARGYLL AND BUTE COUNCIL POLICY AND RESOURCES COMMITTEE
COMMERCIAL SERVICES 10th OCTOBER 2024 DEVELOPMENT AND ECONOMIC GROWTH
LORN ARC TAX INCREMENTAL FINANCE PROGRAMME – OBAN AIRPORT BUSINESS PARK – UPDATE
2.0INTRODUCTION
2.1At May 2024 Policy and Resources Committee it was agreed to allocate £8.05m from TIF to deliver the construction of roads, infrastructure, servicing and site works. This included an immediate draw down of £1.6m to deliver the Full Business Case for the overall project.
2.2Ongoing work is also progressing in relation to identifying and securing other funded investment in the business park including and the development of commercial buildings for lease. This Full Business Case is now well underway and this paper provides an update on progress.
That the Policy and Resources Committee:
i. Consider this project update relating to Oban Airport Business Park; and
ii. Note another update report including the Full Business Case will be reported back to Members for consideration in December 2024. 4.0 DETAIL Background 4.1 The initial phase of investment at Oban Airport was for the installation of a road link and services to enable the development of a new business park adjacent to the airport – this was completed several years ago. Despite this investment there was nervousness of businesses to move into the site without additional infrastructure being provided. Following this market feedback, Estates have instructed site investigations, service assessments and costings and generated business interests in the site from aviation related businesses. The existing site and newly proposed service site layout is shown below:
EXISTING SITE
PROPOSED DEVELOPMENT LAYOUT 4.2 Officers have been working with Stantec and other specialist consultants to deliver a serviced site proposition for the private sector at Oban Airport. The Council has not created a new business park for several decades but now is in a progressed stage at this location and at Kilmory Business Park in Lochgilphead. Creating business park space can create spaces for local and incoming business to growth and trade plus it has the additional benefit of creating commercial income as part of the Council’s rental portfolio.
4.3At Oban Airport an Outline Business Case (OBC) has been produced and has secured funding from the TIF Executive (subject to Scottish Government approval) for the development of roads, infrastructure, servicing and site works and the OBC. This was detailed in full, including financial draw down and commitments, at the May P&R Committee. At that time the 2 initial lynchpin tenants of Bristow Search and Rescue and TSL were also identified as interested occupants of Plots 1 and 2.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Budget outlook 2027-28 to 2031-32Decision The Policy and Resources Committee noted the current Budget Outlook position for the period 2027-28 to 2031-...
Funding request from local organisationsDecision The Policy and Resources Committee – 1. agreed to award a one-off grant of £36,000, to be paid from the Prio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.