Decision The Committee noted the content of the report. (Ref: Report by Special Projects and Quality Improvement Manager, dated 12 April 2017, submitted).
Oban Lorn & The Isles Area Committee noted this item on Wednesday 12 April 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision The Committee noted the content of the report. (Ref: Report by Special Projects and Quality Improvement Manager, dated 12 April 2017, submitted).
1.1This report provides Members with progress on the Council’s Schools Redevelopment Project in partnership with hubNorth Scotland Ltd (hubNorth) to build a new secondary school in Oban.
1.2The project continues to make good progress. The metal decking and all concrete floor slabs have been completed to each floor. The roofing works and secondary steelwork are nearing completion and the cladding to the building along with the external blockwork has commenced.
The construction of the new grass pitch on the existing blaise pitch at Mossfield is on schedule.
1.3Progress on the construction of the new school building is illustrated in a series of photographs in Paragraph 4.3
1.4The third quarterly newsletter was made available at the end of February and through the dedicated Oban High School project website, hosted by Morrison Construction, at www.ohsproject.co.uk
1.5The school redevelopment projects have provided already a number of community benefits and through the projects it has been agreed that modern apprenticeships will be provided at each site. In addition, discussions are ongoing with the Facilities Management (FM) contractor to provide apprenticeships over the 25 year life span of the Design Build Finance and Maintain (DBFM) contract.
1.6Planning for the decant of pupils, staff and resources has commenced. Regular meetings will continue to take place and information will be issued at appropriate times from now through to the decant itself which is due to take place in February 2018.
1.7Partnerships Bulletin – Partnerships Awards 2017
HubNorth Scotland Ltd and Galliford Try nominated the Campbeltown and Oban DBFM project for the Partnerships Awards 2017 and the Project Team has been notified that the Campbeltown/Oban DBFM project has been shortlisted under two separate categories: 1 Best Education Project; and Public Sector Procurer of the Year.
Separately, ABC Schools has nominated the current NPDO schools project which has been shortlisted for Best Operational Project.
The Gold and Silver Award winners in each category will be announced on Thursday 11 May 2017.
It is recommended that Members note the content of this report.
2 ARGYLL AND BUTE COUNCIL OLI AREA COMMITTEE
COMMUNITY SERVICES 12 APRIL 2017 CUSTOMER SERVICES
NEW SCHOOLS REDEVELOPMENT PROJECT OBAN HIGH SCHOOL UPDATE
2.0INTRODUCTION
2.1This report provides Members with progress on the Council’s Schools Redevelopment Project in partnership with hubNorth Scotland Ltd (hubNorth) to build a new secondary school in Oban.
It is recommended that Members note the content of this report.
4.0DETAIL
4.1The new Oban High School Redevelopment Project is a Design Build Finance and Maintain (DBFM) Project being delivered as a part of the Scottish Government’s Schools for the future Programme pipeline with hubNorth Scotland Ltd, the Council’s project partner.
4.2Key Programme Dates
The key contract programme dates for Oban High School are:
Date Description Comment May 2016 – Phase 1 – Construction of March 2018 new school building Pupils/staff move March/April Oban High School Decant into new school 2018 building Demolition of existing school April 2018 – Phase 2 buildings, February External Works construction of 2019 car park, bus drop- off and landscaping All works completed February Phase 2 Completion and whole school 2019 availability
At this stage in the Phase 1 construction period, there is no change to the intended programme. 3 As part of the Planning approval for the new school, a compensatory grass pitch is a planning requirement and this needs to be delivered as part of the project for the new Oban High school. This is a matter that has been reported previously to the Council’s Policy and Resources committee and the local area committee.
The construction of the new grass pitch is underway at Mossfield and is currently on schedule for completion April 2017.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
NEW SCHOOLS REDEVELOPMENT PROJECT: OBAN HIGH SCHOOLReport | 769 KB | DownloadRead as text |
Follow Oban Lorn & The Isles Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Sep 2026 | Public question time part 1It was agreed therefore that the responses would not be read out but included in the minute and also emailed to the A... | Agreed | Open |
| 9 Sep 2026 | CHARTS (Argyll and Isles)Decision The Oban, Lorn and the Isles Area Committee considered and noted the information provided in the presentatio... | Noted | Open |
| 9 Sep 2026 | Roads and infrastructure updateDecision The Oban, Lorn and the Isles Area Committee noted the contents of the report. (Reference: Report by Executiv... | Noted | Open |
| 9 Sep 2026 | Oban PVA Flood Risk Management UpdateDecision The Oban, Lorn and the Isles Area Committee:- 1) considered the contents of this report; and 2) noted the co... | Noted | Open |
| 9 Sep 2026 | Argyll Square Project: Consolidated Financial Report and Delivery UpdateDecision The motion was carried by 4 votes to 2 and the Committee resolved accordingly. (Reference: A report by Secti... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.