DEVELOPMENT AND INFRASTRUCTURE SERVICES PERFORMANCE REPORT FQ3 2017/18
NotedCommittee1 paper
Environment, Development and Infrastructure Committee noted this item on Thursday 8 March 2018. Below is the council's own wording, with the papers it was decided on.
Decision The Committee noted the Development and Infrastructure Services departmental performance report and associated scorecards for performance in financial quarter three 2017-18 (October to December 2017). (Reference: Report by Executive Director – Development and Infrastructure Services dated March 2018, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Environment, Development and Infrastructure Committee
Recommendations
2.1It is recommended that the Committee reviews the scorecard as presented.
3.0DETAIL
3.1The performance scorecard for Development and Infrastructure Services was extracted from the Council’s Pyramid performance management system and is comprised of key performance indicators incorporating the services that make up Development and Infrastructure Services.
3.2Commentary on the indicators included within the scorecard can be interrogated via the Pyramid system. Some key points have been included below for ease.
Management Information
3.3Sickness absence has been an area of focus for the department and FQ3 has seen a marked improvement with an average of 2.90 days lost against a target of 2.98 days per employee. The department now has a dedicated HR Assistant to support managers in dealing effectively with absence cases which will help the department to maintain a focus on this area.
3 3.4 Completion of PRDs is currently at 86% against a target of 90%. Whilst performance against the profile can vary marginally throughout the year the department has a good track record of achieving targeted performance in this area and expects to be on target by the end of the year.
3.5In terms of the revenue budget the department is not currently projecting any significant variances against the overall outturn. This position continues to be closely monitored on a monthly basis.
Business Outcomes
3.6BO12 High standards of public health and health protection are promoted. The percentage of public health incidents responded to within 20 days is above the target of 80%. In quarter 2 performance in resolving service complaints was 74% of all environmental health service requests within the service standard of 20 working days, but this has increased to 90% in quarter 3.
3.7BO22 Economic Growth is supported The time to process planning application remains very good. The percentage of pre-application enquiries dealt with in 20 days is 75.7% against a target of 75%. The performance target has been met for the first time since FQ2 2016/17. The percentage of planning applications validated within 5 days is 89% against a target of 90%. Whilst the time to determine planning applications is the priority area of performance, the off target area of performance is subject to a process improvement project.
3.8BO27 Argyll and Bute if Open For Business The percentage of premises in Argyll and Bute covered by the digital network has increased from 83.3% in FQ2 to 86.8% in FQ3, which is above the 84% target. Going forward this will continue to be a focus of the department to ensure the percentage is maintained above the target.
3.9Performance in relation to complaint handling has improved in FQ3. In FQ3 67% of stage 1 complaints were responded to within the timescales against a target of 80% and 100% of stage 2 complaints were responded to within timescales against a target of 90%. Whilst stage 1 complaints are still below target, this is an improvement of 4% in this quarter. Improving performance in this area and achieving high levels of customer case is the subject of an ongoing project focused primarily on the Roads and Amenity service which has the highest volume of customer contacts.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment, Development and Infrastructure Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Review of public convenience estateDecision The Environment, Development and Infrastructure Committee – 1. noted the findings of the updated baseline re...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.