ROADS CAPITAL RECONSTRUCTION PROGRAMME 2018/19

Agreed Committee 2 papers

Environment, Development and Infrastructure Committee agreed this item on Thursday 8 March 2018. Below is the council's own wording, with the papers it was decided on.

Item10

Resolved

Decision The Environment, Development and Infrastructure Services Committee endorsed the proposed programme of capital works for 2018/19 and agreed that details of each Area Committees programme would be forwarded to individual elected members. (Reference: Report by Executive Director – Development and Infrastructure Services dated March 2018, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Environment, Development and Infrastructure Committee

Executive summary

1.1The Roads Reconstruction Programme has been structured in line with the Roads Asset Management and Maintenance Strategy. The focus has been to arrest the rate of decline and provide an overall improvement in condition as has been demonstrated in the Annual Status and Options Report. In previous years this has been achieved through the delivery of a mix of carriageway resurfacing, edge strengthening, patching/surface dressing and in-situ road surface recycling. These treatments have been designed to seal the road to stop the ingress of water, improve ride quality and reduce the amount of reactive repairs. This has resulted in an overall improvement in road condition. Without these works and investment there would have been a significant deterioration in condition. Additional funding was allocated at the Council Budget Meeting on 22 February 2018 for financial years 2018/19 and 2019/20. A summary of the available budgets in detailed in Table 1 in paragraph 4.2 of the report.

1.2Attached to this report is a draft programme for roads reconstruction and footway schemes for 2018/19. This programme has been designed using the Road Condition Index (RCI) which is produced by a national road condition survey. This survey information is used by officers to determine a programme. In addition to the RCI data, information such as road traffic collisions, known development, activities such as timber harvesting and a skid condition (of the carriageways surface) which is measured by a separate survey are also considered together with information brought from Elected Members, community groups and stakeholders. This information is considered at officer level when appropriate engineering judgement is also applied to ensure that maximum benefit can be derived from the available investment.

1.3The proposed capital works program is presented is based on carriageway condition late autumn/early winter. With the effect of winter this programme may need to be adjusted to ensure that any investment is targeted accordingly. Should any changes be required to the programme, the Policy Lead and Depute Policy Lead will be notified prior to any amended area scheme list being sent out to local members.

Recommendation

1.4That the Committee endorses the proposed programme of capital works for 2018/19, and also agrees that details of each area committees programme will be forwarded on to individual Elected Member.

1 ARGYLL AND BUTE COUNCIL ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE COMMITTEE

DEVELOPMENT AND INFRASTRUCTURE SERVICES 8th MARCH 2018

ROADS CAPITAL RECONSTRUCTION PROGRAMME 2018/19

2.0INTRODUCTION

2.1This report provides details of the proposed roads reconstruction programme for 2018/19.

Recommendations

3.1That the Committee endorses the proposed programme of capital works for 2018/19, and also agrees that details of each area committees programme will be forwarded on to individual Elected Members.

4.0DETAILS

4.1The focus of the roads reconstruction programme has been to recover the network through the delivery of a mix of carriageway resurfacing schemes, patching/surface dressing and in-situ road surface recycling, which follow the principles set out within the Roads Asset Management Plan.

4.2The proposed capital works programme is based on the funding allocation which was confirmed at the Council Budget Meeting held on 22 February 2018. The total allocation for 2018/19 and 2019/20 for roads is detailed in Table 1 below:

Table 1

2018/19 2019/20 £000 £000

Roads Capital in plan 2,882 5,250 Extra roads funding 5,500 2,800 allocated at Council meeting Total roads funding 8,382 8,050 Footways funding allocated 250 250 at Council meeting Grand Total 8,632 8,300

2 The area allocation is detailed in Table 2 below:

Table 2

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
ROADS CAPITAL RECONSTRUCTION PROGRAMME 2018/19Report 96 KB DownloadRead as text
PDF
Roads Capital Reconstruction Programme 2018-19. AppendixAppendix 197 KB Download

At this meeting

Whole meeting

Who was there

12 of 19 attended
SC
Stewart ClarkCouncil Staff, expected
HM
Hazel MacInnesSecretary, expected
FM
Fiona McCallumSecretary, expected
JA
Councillor John ArmourMember, present
GB
Councillor Gordon BlairMember, present
BG
Councillor Bobby GoodMember, absent
DK
Councillor Donald KellyMember, present
DK
Councillor David KinniburghMember, present
JL
Councillor Jim LynchMember, present
DM
Councillor Donald MacMillanMember, present
RM
Councillor Roderick McCuishChair, present
SJ
Councillor Sir Jamie McGrigorMember, apologies

All 19 on the meeting page

On this subject at Argyll and Bute

Search all
  1. ROADS CAPITAL RECONSTRUCTION PROGRAMME 2018/19This decision
  2. Roads capital reconstruction programme 2026-27 - update reportAgreed
  3. Roads capital reconstruction programme 2026-27Agreed
  4. Roads capital reconstruction programme - 2025/26Agreed
  5. Roads capital reconstruction programme 2024/25 - update reportAgreed
  6. Roads capital reconstruction programme 2024/25Agreed

More from Argyll and Bute Environment, Development and Infrastructure Committee

All decisions
MeetingDecisionOutcome
9 Oct 2026 A816 bealach mor permanent solution updateDecision The Environment, Development and Infrastructure Committee noted the following key points – 1. the £1.1m appr... Noted Open
9 Oct 2026 Review of public convenience estateDecision The Environment, Development and Infrastructure Committee – 1. noted the findings of the updated baseline re... Noted Open
9 Oct 2026 Review of roads and infrastructure services updateDecision The Environment, Development and Infrastructure Committee – 1. noted the progress to date on the RIS Review;... Noted Open
9 Oct 2026 Winter service policy 2026/27Decision The Environment, Development and Infrastructure Committee – 1. approved the 2026/27 Winter Maintenance Polic... Approved Open
9 Oct 2026 Waste management updateDecision The Environment, Development and Infrastructure Committee noted the content of the report. (Reference: Repor... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies