CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Argyll and Bute Council

FESTIVE LIGHTING UPDATE

Noted Committee 3 papers

Environment, Development and Infrastructure Committee noted this item on Thursday 8 March 2018. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

Decision The Environment, Development and Infrastructure Committee – 1. Noted the successful delivery of festive lighting across Argyll and Bute by the council and by community groups in 2017. 2. Agreed the draft principles/template heads of terms at Appendix One to the submitted report, and delegated authority to the Head of Roads and Amenity Services to progress agreements on that basis. 3. Agreed the draft methodology for disposal of lighting assets at Appendix Two to the submitted report and delegated authority to the Head of Roads and Amenity Services to progress matters on that basis. 4. Agreed the strategy for use of any unspent funds at the end of 2018/19 outlined at 4.3.2 of the submitted report. 5. Noted that the final accounts were yet to be settled and that final figures would be reported to the Environment, Development and Infrastructure Committee in June. 6. Noted the advice of officers at paragraph 4.4 of the submitted report and agreed that costs to provide single switch-on points were prohibitive and that no further work should be done in this area, but that any future public realm projects should consider the inclusion of the required cabling improvements to enable single switch- ons as part of their overall scope, with individual decisions to be made on a case by case basis in the context of any overall future project. (Reference: Report by Executive Director – Development and Infrastructure Services dated 31 January 2018, submitted) *
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Environment, Development and Infrastructure Committee

Executive summary

1.1In February 2016 Argyll and Bute Council took the decision to look at alternative, community-led delivery methods for festive lighting with £300,000 earmarked from reserves to support council delivery and transitional arrangements for the following three financial years – 2016/17, 2017/18 and 2018/19

1.2The EDI committee in August 2016 determined that the council should deliver in 2016 on the basis of historic arrangements, with the intention that 2017/18 and 2018/19 by transition years. Community engagement began in earnest in the early part of 2017 and was successful in the sense that officers were able to begin dialogue and establish outline agreements in principle in all areas where there is an existing relationship with a third party that these groups would work towards a community-led solution.

1.3In April 2017 members of the EDI committee determined that the remaining balance of the central allocation would be divided by administrative area (£51,902 per area).

1.4At the September meeting of the same committee it was determined that the council would deliver again in 2017 on the basis of historic arrangements but that if a community group felt it was ready to take full responsibility they could apply to the festive lighting fund for monies to support their events.

1.5Grant funding was provided via area committees to Tobermory and Helensburgh, with the remaining Christmas lights switch-on events delivered successfully by the council, on the agreed basis of historic arrangements.

1.5This report updates members on the position and intended next steps and seeks approval for these next steps.

Recommendations

Members of the committee are asked to:  Note the successful delivery of festive lighting across Argyll and Bute by the council and by community groups in 2017;

 Agree the draft principles/template heads of terms at Appendix One, and delegate authority to the Head of Roads and Amenity Services to progress agreements on this basis;

 Agree the draft methodology for disposal of lighting assets at Appendix Two and delegate authority to the Head of Roads and Amenity Services to progress matters on this basis;

 Agree the strategy for use of any unspent funds at the end of 2018/19 outlined at 4.3.2 of this report;

 Note that the final accounts are yet to be settled and that final figures will be reported to EDI in June;

 Note the advice of officers at 4.4 and agree that costs to provide single switch-on points are prohibitive and that no further work should be done in this area, but that any future public realm projects should consider the inclusion of the required cabling improvements to enable single switch- ons as part of their overall scope, with individual decisions to be made on a case by case basis in the context of any overall future project ARGYLL AND BUTE COUNCIL ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE

DEVELOPMENT AND 8 MARCH 2018 INFRASTRUCTURE SERVICES

FESTIVE LIGHTING UPDATE

1.0INTRODUCTION

2.1This report summarises the work in relation to festive lighting following on from the previous update to this committee in September 2017, as well as setting out the preferred principles/methodology to govern the next stage of community engagement where officers will make best endeavours to take the verbal in principle agreements of 2017 to formal agreements for community led solutions from 2019 onwards, if not before, depending on the individual circumstances in each area/of each group

Members of the committee are asked to:

3.1Note the successful delivery of festive lighting across Argyll and Bute by the council and by community groups in 2017;

3.2Agree the draft principles/template heads of terms at Appendix One, and delegate authority to the Head of Roads and Amenity Services to progress agreements on this basis;

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
FESTIVE LIGHTING UPDATEReport 89 KB DownloadRead as text
PDF
Festive Lighting Appendix 1Appendix 41 KB Download
PDF
Festive Lighting Appendix 2Appendix 36 KB Download

At this meeting

Whole meeting

Who was there

12 of 19 attended
SC
Stewart ClarkCouncil Staff, expected
HM
Hazel MacInnesSecretary, expected
FM
Fiona McCallumSecretary, expected
JA
Councillor John ArmourMember, present
GB
Councillor Gordon BlairMember, present
BG
Councillor Bobby GoodMember, absent
DK
Councillor Donald KellyMember, present
DK
Councillor David KinniburghMember, present
JL
Councillor Jim LynchMember, present
DM
Councillor Donald MacMillanMember, present
RM
Councillor Roderick McCuishChair, present
SJ
Councillor Sir Jamie McGrigorMember, apologies

All 19 on the meeting page

On this subject at Argyll and Bute

Search all
  1. FESTIVE LIGHTING UPDATEThis decision
  2. Festive lighting community transition - end project reportNoted
  3. Festive lighting updateNoted
  4. Festive lighting updateNoted
  5. Festive lightingNoted
  6. Festive LightingAgreed

More from Argyll and Bute Environment, Development and Infrastructure Committee

All decisions
MeetingDecisionOutcome
9 Oct 2026 A816 bealach mor permanent solution updateDecision The Environment, Development and Infrastructure Committee noted the following key points – 1. the £1.1m appr... Noted Open
9 Oct 2026 Review of public convenience estateDecision The Environment, Development and Infrastructure Committee – 1. noted the findings of the updated baseline re... Noted Open
9 Oct 2026 Review of roads and infrastructure services updateDecision The Environment, Development and Infrastructure Committee – 1. noted the progress to date on the RIS Review;... Noted Open
9 Oct 2026 Winter service policy 2026/27Decision The Environment, Development and Infrastructure Committee – 1. approved the 2026/27 Winter Maintenance Polic... Approved Open
9 Oct 2026 Waste management updateDecision The Environment, Development and Infrastructure Committee noted the content of the report. (Reference: Repor... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies