Resolved
Decision The Committee considered and noted the contents of the report. (Ref: Report by Head of Economic Development and Strategic Transportation dated 14 March 2018, submitted)
Oban Lorn & The Isles Area Committee noted this item on Wednesday 14 March 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision The Committee considered and noted the contents of the report. (Ref: Report by Head of Economic Development and Strategic Transportation dated 14 March 2018, submitted)
1.1This report provides an update for OLI Members on progress with the two current projects in construction phase within the Lorn Arc programme. These projects are the North Pier in Oban and Kirk Road upgrade in Dunbeg.
1.2The North Pier Harbour Building CHORD project is nearing completion and provides:- showers for visiting yachtsmen; harbour-masters office; and retail / office space for lease. The public realm work around the new building has been completed to enhance the environment for both visitors and locals utilising this area.
1.3The Kirk Road upgrade project consists of :- installing a new water main and sewer; widening the road to full two lane width; creation of a shared cycleway / footpath, and junction realignment / reconfiguration.
These improvement works have the benefit of :- enabling the ongoing development of the European Marine Science Park at Dunstaffnage (subject to phase two of Kirk Road upgrade works taking place which is expected to be undertaken in the near future by HIE). enabling the new development of up to 300 new homes. All of these new homes will be affordable homes which will enable young people and families to remain in the Lorn area to the benefit of the wider community and economy.
1.4It is recommended that the OLI Area Committee:
1. Consider the updates on the North Pier and Kirk Road projects within the Lorn Arc programme provided in the paper. ARGYLL AND BUTE COUNCIL OBAN, LORN & THE ISLES (OLI) AREA COMMITTEE
DEVELOPMENT & 14 MARCH 2018 INFRASTRUCTURE SERVICES
LORN ARC - UPDATE REPORT AS FEBRUARY 2018
2. INTRODUCTION
2.1This report provides an update for OLI Members on progress with the two current projects in construction phase within the Lorn Arc programme. These projects are the North Pier in Oban and Kirk Road upgrade in Dunbeg.
3.1It is recommended that the OLI Area Committee:
1. Consider the updates on the Lorn Arc programme provided in the paper.
4. DETAILS
4.1North Pier Extension: With the recent opening of the CHORD Transit Berthing Facility, the North Pier is becoming more tourist focused. The new North Pier Harbour Building will be operational in March 2018 and the new tenant hopes to open for business in April.
4.2During the final phases of construction on the pontoons in July 2017, it was decided that a defect noted in the North Pier face should be repaired while the opportunity was available with all the contractors, engineers, and equipment on site. Officers and contractors actioned this by temporarily relocating a pontoon and instructing pointing and surveys. The survey results were given in January 2018 and further works will be completed in April when the pontoons will be put back to their intended position.
4.3This has not affected the options for extending the pier and the consultants will now be re-engaged to proceed with the substantiation of the option appraisals. It was decided in July 2017 to stand down the consultants working on the option appraisal until the survey data became available in January 2018.
4.4The success of the pontoons last summer, and the high level of interest from new businesses wishing to operate from the facility and new cruise liner bookings, have proven the attractiveness of Oban and the North Pier as a substantial marine visitor hub for the West of Scotland. The success of the breakwater for large vessel use has resulted in interest from multiple users wishing to relocate their itineraries to Oban and we are experiencing an increase in enquiries from Scandinavia and Benelux countries.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
LORN ARC UPDATEReport | 83 KB | DownloadRead as text |
Follow Oban Lorn & The Isles Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Sep 2026 | Public question time part 1It was agreed therefore that the responses would not be read out but included in the minute and also emailed to the A... | Agreed | Open |
| 9 Sep 2026 | CHARTS (Argyll and Isles)Decision The Oban, Lorn and the Isles Area Committee considered and noted the information provided in the presentatio... | Noted | Open |
| 9 Sep 2026 | Roads and infrastructure updateDecision The Oban, Lorn and the Isles Area Committee noted the contents of the report. (Reference: Report by Executiv... | Noted | Open |
| 9 Sep 2026 | Oban PVA Flood Risk Management UpdateDecision The Oban, Lorn and the Isles Area Committee:- 1) considered the contents of this report; and 2) noted the co... | Noted | Open |
| 9 Sep 2026 | Argyll Square Project: Consolidated Financial Report and Delivery UpdateDecision The motion was carried by 4 votes to 2 and the Committee resolved accordingly. (Reference: A report by Secti... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.