Decision The Policy and Resources Committee – 1. Noted the Revenue Budget Monitoring Report as at 28 February 2018. 2. Noted the Capital Plan Monitoring Report as at 28 February 2018 and approved the cost changes, the project slippages and accelerations noted within appendix 7 of the submitted Capital Plan Monitoring Report. 3. Noted the Treasury Monitoring Report as at 28 February 2018. 4. Noted the Reserves and Balances Report as at 28 February 2018. 5. Noted the progress of the service choices policy saving options as at 28 February 2018. 6. Agreed to recommend to Council that the cremation charges for adults aged 16 and over is amended to £665 for 2018-19. (Reference: Report by Head of Strategic Finance dated 30 April 2018, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
ARGYLL AND BUTE COUNCIL POLICY AND RESOURCES COMMITTEE
STRATEGIC FINANCE 24 MAY 2018
EXECUTIVE SUMMARY FINANCIAL UPDATE – FEBRUARY 2018
1. INTRODUCTION
1.1This report provides a financial update as at the end of February 2018. The reports attached to this update are:
Revenue Budget Monitoring Report as at 28 February 2018 Capital Plan Monitoring Report as at 28 February 2018 Treasury Monitoring Report as at 28 February 2018 Reserves and Balances as at 28 February 2018
The web link to the detailed reports is as follows: http://www.argyll-bute.gov.uk/financial-monitoring
1.2As we are one month from the end of the financial year, the financial risks report hasn’t been included as any areas where a financial risk has materialised will now be built into the estimated outturn position with the exception of the overspend on the Health and Social Care Partnership which is the subject of a separate report on the agenda. A summary of the progress with implementation of service choices savings agreed in February 2016 is included in paragraph 2.5.
1.3The fees and charges for 2018-19 were approved at the Council meeting on 22 February 2018. There are a couple of minor adjustments to the fees and charges schedule as noted in paragraph 2.6.
2. DETAIL
2.1Revenue Budget Monitoring Report
2.1.1 This report provides a summary of the current revenue budget monitoring position to ensure net expenditure is contained within budget. It provides corporate and departmental information with comparisons on a forecast outturn and a year to date basis.
2.1.2 There is a forecast underspend of £1.299m as at the end of February 2018. The underspend is in respect of the following:
Underspend within NPDO (utilities and deductions) as a result of enhanced contract management £0.098m. Over recovery of vacancy savings within Customer Services and Development and Infrastructure of £0.483m. Grant income in Development and Infrastructure relating to expenditure in the previous year £0.097m. Underspend in fleet of £0.132m relating to a delay in replacing vehicles over 5 years old. Over-recovery of income within regulatory services (fish export certifications, private landlord registration and appraisal of water supplies, shellfish programme) amounting to £0.101m. Over recovering of income within piers and harbours as a result of RET £0.200m. Underspend of £0.095m in relation to Housing related services. £0.079m over recovery of commercial waste income. £0.050m relating to other small underspends in D&I. Underspend of £0.245m relating to a provision for superannuation costs that is no longer required. Apprenticeship levy estimated to be £0.090m below budget. Estimated £0.395m underspend within utilities across the Council. Over recovery of Council Tax income amounting to £0.600m. Overspend of £0.177m in relation to dangerous buildings. Increased demand within ASN support and residential schools placement estimated overspend of £0.199m. Under recovery of planning fee income estimated to be £0.240m. Overspend of £0.100m in ferries due to ASP payment. Estimated winter maintenance overspend of £0.650m. This was the figure calculated as at the end of December, however, due to the snow in January, this overspend is likely to increase and a further estimate will be calculated.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Budget outlook 2027-28 to 2031-32Decision The Policy and Resources Committee noted the current Budget Outlook position for the period 2027-28 to 2031-...
Funding request from local organisationsDecision The Policy and Resources Committee – 1. agreed to award a one-off grant of £36,000, to be paid from the Prio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.