Decision The Policy and Resources Committee – 1. Noted the updates on the Lorn Arc Programme provided in the submitted report. 2. Approved the Oban Strategic Development Framework Initiation Document contained at Appendix A to the submitted Report. (Reference: Report by Executive Director – Development and Infrastructure Services dated April 2018, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1This report provides an update to the Policy and Resources Committee on progress with the Lorn Arc programme and latest budget position as at the end of March 2018.
1.2Members will be aware that the funding for this project relies on forecast incremental Non-Domestic Rates (NDR) being sufficient to service debt before a project can be taken forward to implementation stage. Tax Incremental Financing (TIF) was regarded as an innovative approach to exploring a potential funding mechanism for a range of economic development and infrastructure projects that otherwise could not be delivered within available Council budgets. The original programme consisted of 9 individual projects across various locations, namely: Barcaldine, Oban Airport, Dunbeg Corridor, and Oban town centre. This list of 9 projects was reduced to 7 following agreement from the Scottish Government and the Council in recognition of private investment coming forward for Barcaldine which is now on site.
1.3This original TIF business case has proven to be non-viable due to changes in anticipated rateable values, rates and reliefs, and significant changes in the National economy.
1.4Following agreement from the Scottish Government (SG) in February 2017 and the Council in March 2017 to continue to support the social and economic objectives of the Lorn Arc Programme work has been progressing to find alternative routes for funding of the programme including examining the use of alternative innovative funding models to support inclusive growth.
1.5At the March 2017 Policy & Resource Committee meeting, the Lorn Arc team was authorised to engage with SG and the Scottish Future Trust (SFT) to progress alternative solutions for the delivery for the Lorn Arc programme. This engagement has been progressing including a number of discussions on a possible growth accelerator model or being part of the emerging Rural Growth Deal. In order for this to be progressed further greater clarity will have to be given to the list of potential projects that can take best advantage of this approach
1.6The TIF Programme Board have noted that the likely solution for the programme would be the progression of a case for use of a growth model such as the Growth Accelerator or a Rural Growth Deal. Moving forward with an alternative funding model, however, would require clarity on the projects that would form the basis of that deal. Work on this has been ongoing, and is being developed in parallel with the Scottish Government and Scottish Futures Trust. A list of potential projects is currently being developed.
1.7Individual projects are being progressed in different ways that are detailed in the report.
1.8Budget: Detailed below is the current budget position for both the revenue and capital approved budget allocations.
REVENUE £000s Total approved funds 1,607 Total project spend to date March 2018 618 Balance 989 CAPITAL £000s Total borrowing approved 1,388 Total project spend to date March 2018 869 Balance 519
1.9It is recommended that the Policy and Resources Committee:
Note the updates on the Lorn Arc programme provided in the paper. Approve the Oban Strategic Development Framework Initiation Document contained in Appendix A ARGYLL AND BUTE COUNCIL POLICY & RESOURCES COMMITTEE
DEVELOPMENT & 24th MAY 2018 INFRASTRUCTURE SERVICES
LORN ARC - UPDATE REPORT AS MARCH 2018
2. INTRODUCTION
2.1This report provides the Policy and Resources Committee with an update on progress in relation to the Lorn Arc TIF, and the latest budget position as at the end of March 2018.
Recommendations
3.1It is recommended that the Policy and Resources Committee:
Note the updates on the Lorn Arc programme provided in the paper. Approve the Oban Strategic Development Framework Initiation Document contained in Appendix A
4. DETAILS
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Budget outlook 2027-28 to 2031-32Decision The Policy and Resources Committee noted the current Budget Outlook position for the period 2027-28 to 2031-...
Funding request from local organisationsDecision The Policy and Resources Committee – 1. agreed to award a one-off grant of £36,000, to be paid from the Prio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.