Decision The Environment, development and Infrastructure Committee – 1. Noted the financial position. 2. Noted that engagement continues on the basis of the outline heads of terms approved at the Environment, Development and Infrastructure Committee in March and that a subsequent update would come forward to the next meeting of the Committee. (Reference: Report by Executive Director – Development and Infrastructure Services dated May 2018, Submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Environment, Development and Infrastructure Committee
Executive summary
1.1Members noted in the previous festive lighting update to the EDI Committee in March 2018 that a further report would come forward on the financial position in relation to the delivery of festive lighting across Argyll and Bute once full account had been taken of the 2017 costs, which is the purpose of this report.
1.2As expected, and previously indicated, the spend in Bute & Cowal and Mid- Argyll, Kintyre and the Isles was slightly more than half of what remained from the earmarked reserves for 2017/18 and 2018/19. This was principally due to the unprecedented level of repairs required for the assets in those two areas, and as such is expected to be a one-off spend. The remaining funds should be adequate to allow either the Council or a third-party to provide festive events on the basis of historic arrangements.
1.3Members are asked to:
Note the financial position; and Note that engagement continues on the basis of the outline heads of terms approved at EDI in March, and that a subsequent update will come forward to the next meeting of this committee. ARGYLL AND BUTE COUNCIL ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE COMMITTEE
DEVELOPMENT AND INFRASTRUCTURE SERVICES 7 JUNE 2018
FESTIVE LIGHTING UPDATE
2.0INTRODUCTION
2.1This report provides members with an update on the financial position of the reserves earmarked in 2016 for festive lighting.
2.2The fund allocated by members was some £300,000 for delivery of festive lighting on the basis of historic arrangements, and/or to support transition arrangements, up until 2018/19.
Recommendations
3.1Members are asked to:
i. Note the financial position; and
ii. Note that engagement continues on the basis of the outline heads of terms approved at EDI in March, and that a subsequent update will come forward to the next meeting of this committee.
4.0DETAIL
4.1At its budget meeting in February 2016 the Council allocated some £300,000 for the delivery of festive lighting across Argyll and Bute and to support the transition to community-led delivery by the end of financial year 2018/19. This allocation was made on the basis of historic spend of around £100,000 per annum to provide festive lighting across the Council area.
4.2In April 2017 members of the EDI committee resolved that the remaining funds after delivery in Year One be allocated equally to each administrative area. The remaining balance of festive funding which was delegated to area committees in April 2017 was £207,611 or £51,902 per area committee. In September 2017 the EDI committee noted that festive lighting would be delivered in 2017 on the basis of historic arrangements. Following delivery in 2017 the financial position in each area is in the table below. It should be noted that there were significant costs this year in repairing and replacing some of the assets which would not normally be incurred. This was a conscious decision to ensure that the assets are in the best possible condition prior to any potential transfer to communities
Administrative area Spend 2017/18 Remaining balance Mid-Argyll, Kintyre and the 31,174 20,728 Isles Oban, Lorn and the Isles 25,802 26,100 Bute and Cowal 27,345 24,557 Helensburgh and Lomond 21,939 29,963 TOTAL 106,260 101,348
4.3The remaining funds should be adequate to ensure events this year on the basis of historic arrangements. It is too early to say whether or not these events will be Council or community led – this will be a matter for discussion over the course of this year. Officers are currently in the process of engaging further with community groups across the Council area
5.0CONCLUSION
5.1The festive spend from 2017 was as expected, with the remaining balance being adequate to provide events on the basis of historic arrangements for this coming year.
6.0IMPLICATIONS
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment, Development and Infrastructure Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Review of public convenience estateDecision The Environment, Development and Infrastructure Committee – 1. noted the findings of the updated baseline re...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.