Decision The Committee noted and approved the contents of the report, specifically the financial summaries as detailed in Appendix 7, and approved the roll forward of any over or underspends in relation to expenditure and income as part of the year end process. (Ref: Report by Section 95 Officer dated 25 June 2020, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1This provides an update on the position of the capital budget as at 31 March 2020. The report provides information on the financial position in respect of the capital plan and also the performance in terms of delivery of capital plan projects.
1.2Financial Position:
Outturn for 2019-20 – actual expenditure for the full financial year is £19,321k compared to an annual budget of £19,435k giving rise to an underspend for the year of £114k (0.6%). Total Capital Plan – the forecast total net project costs on the total capital plan are £217,158k compared to a total budget for all projects of £217,194k giving rise to a forecast underspend for the overall capital plan of £36k (0.02%).
1.3Project Delivery:
Asset Sustainability – Out of 92 projects there are 86 projects (93%) on track and 6 projects (7%) off track but recoverable. Service Development - Out of 28 projects there are 24 projects (86%) on track and 4 projects (14%) off track but recoverable. Strategic Change – Out of 29 projects there are 21 projects (72%) on track, 7 projects (24%) off track but recoverable and 1 project (3%) off track.
1.4The Capital Programme is funded by various income streams as detailed in Appendix 4. Changes during March relate to Hermitage Park which has been funded from external income and revenue funded capital works. ARGYLL AND BUTE COUNCIL BUSINESS CONTINUITY COMMITTEE FINANCIAL SERVICES 25 JUNE 2020 CAPITAL BUDGET MONITORING REPORT – 31 MARCH 2020 ,
2 INTRODUCTION 2.1 This provides an update on the position of the capital budget as at 31 March 2020. The report provides information on the financial position in respect of the capital plan and also the performance in terms of delivery of capital plan projects.
3 RECOMMENDATIONS 3.1 Note the contents of this report, specifically the financial summaries as detailed in Appendix 7, and approve the roll forward of any over or underspends in relation to expenditure and income as part of the year end process. 4 OUTTURN FINANCIAL POSITION 2019-20 4.1 Overall Position
Actual net expenditure for the full financial year is £19,321k compared to an annual budget of £19,435k giving rise to an underspend for the year of £114k (0.6%).
4.2Project/Department Position
The table shows the actual expenditure and budget for the year by project type and service:
Annual Budget Outturn Variance Project Type: £'000 £'000 £'000 Asset Sustainability 13,426 13,194 232 Service Development (46) (29) (17) Strategic Change 6,055 6,156 (101) Total 19,435 19,321 114 Service: ICT 1,469 1,468 1 Education 5,272 4,498 774 Live Argyll 1,176 1,011 165 Health & Social Care Partnership 615 495 120 Shared Offices 1,693 1,012 681 Roads & Infrastructure 8,193 8,918 (725) Development & Economic Growth (1,500) (1,343) (157) Major Projects 2,517 3,262 (745) Total 19,435 19,321 114
Material variances are explained in Appendix 1 and there are a number of smaller variances contributing to the underspend. 5 TOTAL PROJECT COSTS 5.1 Overall Position The forecast total net project costs on the total capital plan are £217,158k compared to a total budget for all projects of £217,194k giving rise to a forecast underspend for the overall capital plan of £36k (0.02%). 5.2 Project/Department Position
The table shows the forecast expenditure and budget for the total capital plan by project type and service:
Capital Forecast Capital Plan Project Plan Budget Costs Variance Project Type: £'000 £'000 £'000 Asset Sustainability 54,293 54,258 35 Service Development 61,563 61,562 1 Strategic Change 101,338 101,338 0 Total 217,194 217,158 36 Service: ICT 6,318 6,318 0 Education 42,337 42,337 0 Live Argyll 3,942 3,942 0 Health & Social Care Partnership 4,001 4,001 0 Shared Offices 21,593 21,593 (0) Roads & Infrastructure 34,950 34,915 35 Development & Economic Growth 52,152 52,151 1 Major Projects 51,901 51,901 0 Total 217,194 217,158 36
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Budget outlook 2021-22 to 2025-26Decision The Committee noted the current estimated budget outlook position for the period 2021-22 to 2025-26. (Ref: R...
Budget planning 2021-22 and beyondDecision The Committee:- 1. Agreed to the overall budget approach for 2021-22 and the themed reviews as identified in...
Public conveniences remobilisationDecision The Committee:- 1. Agreed to Option 2, that is to keep the current 35 public conveniences open until the end...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.