Decision The Environment, Development and Infrastructure Committee – 1. Noted the progress of the R100 programme and delays that had hindered its progress and the measures Scottish Government had taken to mitigate these delays. 2. Agreed to pause further development of a bid to the Rural Gigabit Fund (renamed “Place”) with the recommendation that these sites had been given early indication by Scottish Government officials that they were covered within the R100 Programme. (Reference: Report by Executive Director with responsibility for Development and Economic Growth dated 28 April 2021, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Environment, Development and Infrastructure Committee
Executive summary
1.1The original purpose of this report was to bring, to the members of the Environment Development and Infrastructure Committee, a set of options and criteria for the administering of the £250K Tackling Digital Exclusion Fund that the council approved at its budget meeting in February 2021. However due to the current complexity of the Scottish Government’s R100 contract, that will see significant investment in Argyll and Bute, it is proposed that these options be delayed. A paper will instead be brought to the September ED&I meeting, as at this point the full R100 intervention area will have been published. This will enable officers to present a clear direction, ensuring that the fund targets those premises that require further assistance to provide the much needed connectivity. 1.2 This report will provide an overview of the current position of the ongoing Scottish Government Reaching 100% (R100) programme and explain the reasons behind the delays to the implementation to this national initiative. 1.3 The report also provides an update on the proposed bid to the UK Govt.’s Rural Gigabit Fund as Scottish Govt. officials have given an early indication that these remote sites are now covered within the forthcoming R100 programme. 1.4 Finally, the report provides a brief summary of the current position for the ongoing plans for the implementation of the Gigabit Jura proposals that is part funded through Crown Estate funding previously agreed by the council at its February 2021 budget meeting.
Recommendations
2.1The recommendations are:-. (i) To note the progress of the R100 programme and delays that have hindered its progress and the measures Scottish Government have taken to mitigate these delays.
(ii) For members to agree to pause further development of a bid to the Rural Gigabit Fund (renamed “Place”) until the full intervention area of the R100 is released, with the recommendation that these sites have been given early indication by Scottish Government officials that they are covered within the R100 Programme. ARGYLL AND BUTE COUNCIL ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE COMMITTEE DEVELOPMENT AND ECONOMIC GROWTH 3RD JUNE 2021
DIGITAL UPDATE
3.0INTRODUCTION
3.1The original purpose of this report was to bring, to the members of the Environment Development and Infrastructure Committee, a set of options and criteria for the administering of the £250K Tackling Digital Exclusion Fund that the council approved at its budget meeting in February 2021. However due to the current complexity of the Scottish Government’s R100 contract, that will see significant investment in Argyll and Bute, it is proposed that these options be delayed. A paper will instead be brought to the September ED&I meeting, as at this point the full R100 intervention area will have been published. This will enable officers to present a clear direction, ensuring that the fund targets those premises that require further assistance to provide the much needed connectivity. 3.2 The report provides an overview regarding the progress of the Scottish Government’s Reaching 100% (R100) initiative. 3.3 This is a very complex and costly programme that if not done correctly could have significant impact of rural communities across the area. It is essential that there is cross departmental cooperation to ensure any issues are mitigated at the earliest opportunity.
4.1The recommendations are:- (i) To note the progress of the R100 programme and delays that have hindered its progress and the measures Scottish Government have taken to mitigate these delays;
(ii) For members to agree to pause further development of a bid to the Rural Gigabit Fund (renamed “Place”) with the recommendation that these sites have been given early indication by Scottish Government officials that they are covered within the R100 Programme.
5.0DETAIL
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment, Development and Infrastructure Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Review of public convenience estateDecision The Environment, Development and Infrastructure Committee – 1. noted the findings of the updated baseline re...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.