Decision The Environment, Development and Infrastructure Committee - 1. Noted the detail of Electric Vehicle Charging Strategy Part 1 Introduction and Cost Recovery Model at Appendix One of the submitted report. 2. Agreed the outline development methodology at Appendix Two of the submitted report. 3. Noted that more detailed discussions with members regarding potential sites in their areas at a Member Development Day would be held prior to a further report being considered at Committee before a consultation exercise. (Reference: Report by Executive Director with responsibility for Roads and Infrastructure dated 13 April 2021, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Environment, Development and Infrastructure Committee
ARGYLL AND BUTE COUNCIL ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE
ROADS AND INFRASTRUCTURE SERVICES 3rd JUNE 2021
ELECTRIC VEHICLE CHARGING STRATEGY
1.0INTRODUCTION
1.1This report provides members with a further update on the development of a medium to long-term future strategy for electric vehicle charging infrastructure across Argyll and Bute following on from the December update.
1.2Following the Council’s budget meeting in February this year, fees for use of electric chargers have been introduced as below. These came into effect on 9 th April 2021. The attached strategy document at Appendix One provides far more detail on the cost recovery methodology. In summary, the fees include a fixed rate plus a rolling cost; a rate is charged to use the charge point and customers are also charged per unit of electricity consumed - this model provides certainty for the Council over coverage of fixed and variable costs and transparency for users. The fees are:
Net VAT Gross kWh and Maintenance £0.21p £0.04 £0.25 - charge based on 20p to cover Council's electricity costs and 1p to contribute to future maintenance costs Minimum Charge £1.50 £0.30 £1.80 - covers management costs e.g. admin, banking fees, merchant fees etc
1.3Now that the cost recovery model is in place income and feedback will be monitored over the course of the next year, and any implications/proposed variations will be reported to Members as required.
1.4Attention now turns to the future development of the network, with a view to ultimately agreeing a consolidated long list of potential future sites based on an agreed set of criteria. The outline development methodology is appended to this report at Appendix Two. The intention is to agree this high-level methodology with a view to having more detailed discussions with Members about potential sites in their areas at a Member Development Day prior to reporting back to EDI on the consolidated long list then seeking public feedback via consultation on the methodology and long list of sites. Ultimately the exercise should produce an approved list of sites for future installs which can be worked through as external funding arises. The expectation is that national government will provide significant levels of funding for this area of work in future years, therefore it is important that the Council has a development plan which is logical, detailed and has benefitted from public feedback/ buy in.
2.0RECOMMENDATION Members are asked to: 2.1 Consider the detail of EVC Strategy Part 1 Introduction and Cost Recovery Model at Appendix One of this report; and 2.2 Agree the outline development methodology at Appendix Two of this report; 2.3 Note that more detailed discussions with members regarding potential sites in their areas at a Member Development Day will be had prior to a further report being considered at Committee before a consultation exercise.
3.0DETAIL 3.1 With the benefit of over £700,000 of funding provided by Transport Scotland on behalf of the Scottish Government, Argyll and Bute Council has to date installed a reasonable network of chargers across the area. These are located in towns including Campbeltown, Dunoon, Helensburgh, Lochgilphead, Oban, as well as on Islay, Mull and Coll,
3.2As of April 2021 there were a total of 39800 sessions and total consumption of 428776.97 kWh, with the Council previously having absorbed those electricity costs prior to the new policy of cost recovery coming into effect.
3.3The cost recovery model has been advertised for users via various methods:
On site signage with details of a specific EV webpage including FAQs Members of Charge Place Scotland (CPS), within our postcode catchment areas, were notified via email directly from CPS Press releases and social media
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment, Development and Infrastructure Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Review of public convenience estateDecision The Environment, Development and Infrastructure Committee – 1. noted the findings of the updated baseline re...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.