Environment, Development and Infrastructure Committee approved this item on Thursday 3 June 2021. Below is the council's own wording, with the papers it was decided on.
Decision The Environment, Development and Infrastructure Committee – 1. Approved the invitation to tender for the construction of the main flood scheme and supply and installation of property flood resilience measures. 2. Noted that a paper detailing the full Business Case would be brought back to the Committee in September 2021. Construction of the final scheme would be subject to approval of Full Business Case prior to tender award. (Reference: Report by Executive Director with responsibility for Roads and Infrastructure dated 10 May 2021, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Environment, Development and Infrastructure Committee
Executive summary
1.1This report provides an update on progress with the Campbeltown Flood Protection Scheme (CFPS), including the funding position and makes recommendations in order for the project to progress.
1.2The report provides details on the strategic fit, options appraisal, commercial aspects, affordability, achievability and risks associated with the project.
1.3The Committee is asked to: Approve the invitation to tender for the Construction of the main flood scheme and Supply and installation of property flood resilience measures. Note a paper detailing the full Business Case will be brought back to EDI Committee in September 2021. Construction of the final scheme will be subject to approval of Full Business Case prior to tender award. ARGYLL AND BUTE COUNCIL ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE COMMITTEE
ROADS AND INFRASTRUCTURE 3 JUNE 2021
CAMPBELTOWN FLOOD PROTECTION SCHEME
2. INTRODUCTION
2.1This report provides an update on progress with the Campbeltown Flood Protection Scheme (CFPS), including the funding position and makes recommendations in order for the project to progress.
Recommendations
3.1The Committee is asked to: Approve the invitation to tender for the Construction of the main flood scheme and Supply and installation of property flood resilience measures. Note a paper detailing the full Business Case will be brought back to EDI Committee in September 2021. Construction of the final scheme will be subject to approval of Full Business Case prior to tender award.
4. DETAIL
Background
4.1The Environment, Development and Infrastructure (EDI) Committee on 5 December 2019 confirmed the Campbeltown Flood Protection Scheme with modification and recommended to Council to approve additional budget to take the project to tender readiness.
4.2On 28 January 2020 the Council submitted, in accordance with Regulation 14 (2) of the Flood Risk Management (Flood Protection Schemes, Potentially Vulnerable Areas and Local Plan Districts (Scotland)) Regulations 2010, a request for Scottish Ministers to direct that deemed planning permission be granted to Campbeltown Flood Protection Scheme (CFPS). In line with Section 65 of the Flood Risk Management (Scotland) Act 2009, Scottish Ministers directed, under Section 57 of the Town and Country Planning (Scotland) Act 1998, that planning permission for the development is deemed to be granted, subject to conditions.
4.3Confirmation Notice was issued from 15 May 2020 to 26 June 2020 inclusive, in accordance with paragraph 11 of Schedule 2 of the Flood Risk Management (Scotland) Act 2009. CFPS became operative six weeks after Notice of its confirmation was first published in a locally circulating newspaper, as is required under paragraph 10(2)(d) of Schedule 2 of the above Act, as no appeals in accordance with paragraph 12 of Schedule 2 of the above Act were made against the Scheme in the period of the Confirmation Notice.
4.4CFPS is the first scheme being promoted in Argyll and Bute under the Act and has received £3.972m of Scottish Government funding to date. The scheme is estimated to cost £9.330m and this would be 80% funded by the Scottish Government (£7.464m) and 20% by Argyll and Bute Council (£1.866m).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment, Development and Infrastructure Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Review of public convenience estateDecision The Environment, Development and Infrastructure Committee – 1. noted the findings of the updated baseline re...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.