Environment, Development and Infrastructure Committee approved this item on Thursday 2 September 2021. Below is the council's own wording, with the papers it was decided on.
Decision The Environment, Development and Infrastructure Committee – 1. Approved that £10k of the £250k fund be used to start a marketing campaign to target low take-up areas for Superfast Broadband. 2. Approved that the remaining £240k be distributed as outlined in Option 2 at paragraph 4.5 of the submitted report. (Reference: Report by Executive Director with responsibility for Development and Economic Growth dated 22 July 2021, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Environment, Development and Infrastructure Committee
Executive summary
1.1The purpose of this report is to present before members of the Environment Development and Infrastructure Committee, a set of options and criteria for the £250K Tackling Digital Exclusion Fund that the council approved at its budget meeting in February 2021. 1.2 Five Options are outlined in the report with an associated options appraisal conveying each options advantages and disadvantages. 1.3 At this moment in time officers are still waiting for the release of the full R100 intervention area, as of 21st July 2021 officers have been advised that this is still 4-6 weeks away. This is due to the R100 North lot intervention area being with Building Digital UK (BDUK) for assurance. BDUK are currently working with the Scottish Government and Openreach to close off questions from their technical reviewers after which it will be submitted to the board for approval. 1.4 The following options have been developed after detailed discussions with Government Officials from both the UK and Scottish Governments together with the private sector infrastructure providers. 1.5 It is recommended that Members: a) Approve that £10k of the £250k fund is used to start a marketing campaign to target low take-up areas for Superfast Broadband. b) Approve that the remaining £240k be distributed as outlined in Option 2. ARGYLL AND BUTE COUNCIL ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE COMMITTEE DEVELOPMETN AND ECONOMIC GROWTH 2 SEPTEMBER 2021
Tackling Digital Exclusion in Argyll and Bute
2.0INTRODUCTION
2.1The purpose of this report is to present before members of the Environment Development and Infrastructure Committee, a set of options and criteria for the £250K Tackling Digital Exclusion Fund that the council approved at its budget meeting in February 2021.The options are described in detail below with the advantages and disadvantages for each option also identified.
Recommendation
3.1It is recommended that Members: a) Approve that £10k of the £250k fund is used to start a marketing campaign to target low take-up areas for Superfast Broadband. b) Approve that the remaining £240k be distributed as outlined in Option 2.
4.0DETAIL
4.1Argyll and Bute Council’s Tackling Digital Exclusion Fund
The purpose of the Tackling Digital Exclusion fund was outlined in the approved motion which stated the following:- “Establishes the Tackling Digital Exclusion Top Up Fund to support communities and in some cases individuals that are missing out on national programmes due to logistics and economies of scale. While vouchers are available from the UK and Scottish Governments in some cases these do not cover the full cost of infrastructure builds. Instructs the Executive Director with responsibility for Development and Economic Growth to bring a report outlining criteria for distribution to the EDI Committee in June.”
4.2It is recommended that £10,000 of the Fund is used to start a marketing campaign to drive take-up of available Superfast Broadband. Working with the councils Community Planning Partnership (CPP). It is proposed that a targeted campaign in low take-up areas be established. This will also potentially identify reasons of take-up failings whether it be knowledge, desire or affordability. 4.3 For the remainder of the fund, there are 5 potential options and criteria for application of the fund and these are outlined below. This is then followed by a summary appraisal table with each of the options ranked accordingly, with Option 2 being the preferred option recommended by Officers. The options have been developed after detailed discussions with Government Officials from both the UK and Scottish Governments together with the private sector infrastructure providers.
4.4Option1: Work with Scottish Government Voucher Team to top-up SBVS where required, at individual premises level, to allow that premise Gigabit Speeds 100Mbps
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment, Development and Infrastructure Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Review of public convenience estateDecision The Environment, Development and Infrastructure Committee – 1. noted the findings of the updated baseline re...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.