CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Argyll and Bute Council
Environment, Development and Infrastructure Committee, Thursday 2 September 2021 at 10.30am

ROADS CAPITAL RECONSTRUCTION PROGRAMME UPDATE 2021/22

Noted Committee 1 paper

Environment, Development and Infrastructure Committee noted this item on Thursday 2 September 2021. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

Decision The Environment, Development and Infrastructure Committee – 1. Endorsed the progress made on delivering the programme of capital works for 2021/22. 2. Noted that the council had been successful in securing an additional £1.249M through the Scottish Timber Transport fund. 3. Noted that progress updates were provided regularly on the Council website. 4. Noted and endorsed the allocation of funding for footway schemes. (Reference: Report by Executive Director with responsibility for Roads and Infrastructure dated July 2021, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Environment, Development and Infrastructure Committee

Recommendations

2.1It is recommended that the Committee: 1) endorses the progress made on delivering the programme of capital works for 2021/22; 2) notes that the council has been successful in securing an additional £1.249M through the Scottish Timber Transport fund; 3) notes that progress updates are provided regularly on the Council website; 4) notes and endorses the allocation of funding for footway schemes.

3.0DETAIL 3.1 The March EDI report confirmed Roads and Infrastructure were in the process of delivering a £10M roads capital for 2021/22, after a successful bid through the Scottish Timber Transport Scheme, we now also have an extra £1.249M secured through the Scottish Timber Transport Fund for predetermined routes within Argyll and Bute. These routes all being used to haul harvested timber. 3.2 The focus of the roads reconstruction programme has been to recover the network through the delivery of a mix of carriageway resurfacing schemes, patching/surface dressing and in-situ road surface recycling, which follow the principles set out within the Roads Asset Management Plan. 3.3 As in previous years, the roads reconstruction programme is being delivered by a mixed economy model with the Councils in-house team delivering carriageway reconstruction and patching works. The surface dressing element of the programme is being delivered by an external specialist contractor and a number of SMEs are being used to supplement. In order to ensure that the programme provides maximum benefit to the overall network, there will be a minimum of £3.1M (£2M has been carried forward from 2020/21 Budget due to COVID-19) of surface dressing work carried out. This enables the maximum surface area to be covered which will help to seal carriageway cracks, prevent the ingress of water and reduce the amount of reactive maintenance for potholes. 3.4 Good progress is being made with the programme which is on schedule to be completed this financial year. Works have had to be adjusted to accommodate the additional external funding secured. The regularly updated programme can be viewed here: Roads Capital Programme (argyll-bute.gov.uk) 3.5 Whilst the programme is currently on target for completion this financial year, Members should note that we are starting to see some disruption in material supplies, for example cement supplies in many local builders merchants have been depleted due in part to demands from other large UK construction projects, the ability for some European cement production to be maintained on reported logistical challenges due mainly to limited numbers of truck drivers. In addition to this, key materials such as cement and bitumen have seen double figure percentage increases in cost which is reflected in the actual costs of works. 3.6 This year’s programme will see 229.3km of roadway treated which is equivalent to 10.16% of the total adopted network.

Footway Schemes 3.7 The Council invested £0.5m for enhancing and improving footpaths and pavements in rural, remote, island and urban communities at the budget meeting in February 2021. This is in addition to the allocation of £0.4m allocated last year for green transport and travel. This provides us with a funding pot of £0.9m which has been used to form a programme of schemes which is appended to this report at Appendix 1. Members’ views were sought via a communication to the Area Committee Chairs on potential schemes and where possible these have been incorporated into the programme.

4.0CONCLUSION 4.1 This report provides details of the proposed roads reconstruction programme for 2021/22.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
ROADS CAPITAL RECONSTRUCTION PROGRAMME UPDATE 2021/22Report 359 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

15 of 18 attended
RC
Councillor Rory ColvilleVice-Chair, present
HM
Hazel MacInnesSecretary, expected
FM
Fiona McCallumSecretary, expected
JA
Councillor John ArmourMember, present
RC
Councillor Robin CurrieChair, present
DK
Councillor Donald KellyMember, apologies
DK
Councillor David KinniburghMember, present
RM
Councillor Roderick McCuishMember, present
SJ
Councillor Sir Jamie McGrigorMember, present
JM
Councillor Jean MoffatMember, present
AM
Councillor Aileen MortonMember, present
GM
Councillor Gary MulvaneyMember, present

All 18 on the meeting page

On this subject at Argyll and Bute

Search all
  1. ROADS CAPITAL RECONSTRUCTION PROGRAMME UPDATE 2021/22This decision
  2. Roads capital reconstruction programme 2026-27 - update reportAgreed
  3. Roads capital reconstruction programme 2026-27Agreed
  4. Roads capital reconstruction programme - 2025/26Agreed
  5. Roads capital reconstruction programme 2024/25 - update reportAgreed
  6. Roads capital reconstruction programme 2024/25Agreed

More from Argyll and Bute Environment, Development and Infrastructure Committee

All decisions
MeetingDecisionOutcome
9 Oct 2026 A816 bealach mor permanent solution updateDecision The Environment, Development and Infrastructure Committee noted the following key points – 1. the £1.1m appr... Noted Open
9 Oct 2026 Review of public convenience estateDecision The Environment, Development and Infrastructure Committee – 1. noted the findings of the updated baseline re... Noted Open
9 Oct 2026 Review of roads and infrastructure services updateDecision The Environment, Development and Infrastructure Committee – 1. noted the progress to date on the RIS Review;... Noted Open
9 Oct 2026 Winter service policy 2026/27Decision The Environment, Development and Infrastructure Committee – 1. approved the 2026/27 Winter Maintenance Polic... Approved Open
9 Oct 2026 Waste management updateDecision The Environment, Development and Infrastructure Committee noted the content of the report. (Reference: Repor... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies