Environment, Development and Infrastructure Committee noted this item on Thursday 2 September 2021. Below is the council's own wording, with the papers it was decided on.
Decision The Environment, Development and Infrastructure Committee – 1. Endorsed the content of the submitted report. 2. Noted that the full Business Case would be brought back to the Environment, Development and Infrastructure Committee in December 2021. 3. Noted that construction of the final scheme would be subject to approval of Full Business Case prior to tender award. (Reference: Report by Executive Director with responsibility for Roads and Infrastructure dated 2 September 2021, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Environment, Development and Infrastructure Committee
ARGYLL AND BUTE COUNCIL ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE COMMITTEE
ROADS & INFRASTRUCTURE 2 SEPTEMBER 2021 SERVICES <<
CAMPBELTOWN FLOOD PROTECTION SCHEME
1.0INTRODUCTION 1.1 This report provides an update on progress with the Campbeltown Flood Protection Scheme (CFPS), including work completed, key dates and risks going forward.
2.0RECOMMENDATIONS 2.1 The Committee is asked to:
Endorse this report and note that the full Business Case will be brought back to EDI Committee in December 2021. Construction of the final scheme will be subject to approval of Full Business Case prior to tender award. 3.0 DETAIL Background
3.1The Environment, Development and Infrastructure (EDI) Committee on 5 December 2019 confirmed the Campbeltown Flood Protection Scheme (CFPS) with modification and recommended to Council to approve additional budget to take the project to tender readiness.
3.2In line with Section 65 of the Flood Risk Management (Scotland) Act 2009, Scottish Ministers directed, under Section 57 of the Town and Country Planning (Scotland) Act 1998, that planning permission for the development is deemed to be granted, subject to conditions.
3.3Confirmation Notice was issued from 15 May 2020 to 26 June 2020 inclusive, in accordance with paragraph 11 of Schedule 2 of the Flood Risk Management (Scotland) Act 2009. CFPS became operative six weeks after Notice of its confirmation was first published in a locally circulating newspaper, as is required under paragraph 10(2)(d) of Schedule 2 of the above Act, as no appeals in accordance with paragraph 12 of Schedule 2 of the above Act were made against the Scheme in the period of the Confirmation Notice. 3.4 CFPS is the first scheme being promoted in Argyll and Bute under the Act and has received £3.972m of Scottish Government funding to date. The scheme is estimated to cost £9.330m and this would be 80% funded by the Scottish Government (£7.464m) and 20% by Argyll and Bute Council (£1.866m).
3.5The EDI Committee on 3 June 2021 approved the issuing of the invitation to tender for CFPS works.
Stakeholder Consultation
3.6Significant consultation has been undertaken during development of the scheme with stakeholders. This has included statutory stakeholder workshops with Scottish Water, SEPA, Scottish Natural Heritage and the local Planning Department to discuss section of the preferred scheme. We have also had significant consultation with the local community during the scheme development. The level of engagement has been successful with only three objections to the scheme from affected land owners. These were resolved successfully with minor amendments to the design and the scheme noticed again as modified. Officers will continue to engage with the local community as the scheme progresses particularly when planning construction work which by its nature will involve some managed disruption.
Design Progress
3.7The Principal Designer has completed 95% of the design.
3.8Draft Controlled Activities Regulation (CAR) Licence has been approved by SEPA. Official licence will be submitted w/c 2 nd August.
3.9Discharge of planning conditions is being completed as part of the detailed design progresses. Several planning conditions have been written into the contract documents and will become the responsibility of the Principal Contractor through the contract.
Land Acquisition
3.10A review of required land acquisition is being carried out by the Council’s technical advisors, there may be a possibility of reducing the required land take.
3.11Some areas of land have been identified as part of a value engineering exercise which can be realised whilst increasing storage capacities along Tomaig Road.
3.12Colleagues in Estates are currently assisting the project team by negotiating compensation arrangements for acquisition and rights of access.
Tenders
3.13Construction tender selection stage has been completed. Five successful contractors will be invited to tender. One submission did not meet the requirements of the selection stage criteria.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment, Development and Infrastructure Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Review of public convenience estateDecision The Environment, Development and Infrastructure Committee – 1. noted the findings of the updated baseline re...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.