Decision The Policy and Resources Committee – 1. Noted progress of the Rural Growth Deal to date, upcoming milestones and the emerging draft full deal documentation included in Appendices 1-3 to the submitted report. 2. Approved a further drawdown of funding from the Inward Investment Fund (circa £150k). 3. Agreed that authority for approving the drawdown of this funding is delegated to the Chief Executive and 2 Executive Directors of the Council up to a maximum value of £150k and subject to them being satisfied that the monies are for the purpose of delivering the Rural Growth Deal. Any further funding required in excess of the approved value would require further approval from the Policy and Resources Committee. (Reference: Report by Executive Director with responsibility for Development and Economic Growth dated 18 January 2022, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1The main purpose of this report is to provide an update on progress with the Rural Growth Deal to date. This report also seeks approval from the P & R Committee to commit further financial resources to support the development of project business cases and associated project feasibility and development work. This will be necessary to secure the government approvals required to achieve the signing of the full deal, which represents the next key milestone of the Rural Growth Deal (RGD) process.
1.2At the P& R Committee on 10th December 2020, it was approved that £150k of funding from the Inward Investment Fund could be drawn down, as required, to support the development of Outline Business Cases for the Rural Growth Deal. It was also agreed that authority for approving the drawdown of this sum was delegated to the Chief Executive and the 2 Executive Directors of the Council. The initial sum of £150k has been now been approved for expenditure relating to consultancy support to progress initial scoping and development of Outline Business Cases.
1.3The consultancy support also includes development of associated Levelling Up Fund applications which have synergies with the Rural Growth Deal programme. This maximises the resources available and avoids abortive costs in the event of funding bids being unsuccessful. It is anticipated that the initial phases of consultancy support will utilise the majority of the £150k budget previously approved from the Inward Investment Fund.
1.4The RGD Programme Management Office (PMO) are seeking approval from the P&R Committee for a further drawdown of funding from the Inward Investment Fund (circa £150k). It is anticipated that this funding will be required to purchase future services such as design work, further phases of business case support, legal advice and other project related expenditure such as survey work and planning fees. As with the initial tranche of funding, it is proposed that authority for approving future spend will be delegated to the Chief Executive and the 2 Executive Directors of the Council via the Rural Growth Deal Internal Programme Board. ARGYLL AND BUTE COUNCIL POLICY AND RESOURCES COMMITTEE
DEVELOPMENT AND INFRASTRUCTURE 17 FEBRUARY 2022
RURAL GROWTH DEAL – PROGRESS UPDATE AND RESOURCING OF BUSINESS CASES
2.0INTRODUCTION
2.1This report provides an update on progress with the Rural Growth Deal and seeks approval from the P & R Committee to commit further financial resources to support the development of project business cases and associated project development work. This will be necessary to achieve the signing of the full deal, which represents the next key milestone of the Rural Growth Deal (RGD) process.
Recommendations
3.1It is recommended that Members note progress of the Rural Growth Deal to date, upcoming milestones and the emerging draft full deal documentation included in Appendices 1-3.
3.2Approval is also sought from the P&R Committee for a further drawdown of funding from the Inward Investment Fund (circa £150k). It is recommended that authority for approving the drawdown of this funding is delegated to the Chief Executive and 2 Executive Directors of the Council up to a maximum value of £150k and subject to them being satisfied that the monies are for the purpose of delivering the Rural Growth Deal. Any further funding required in excess of the approved value will require further approval from the P&R Committee.
4.0DETAIL
Rural Growth Deal Progress Update
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Budget outlook 2027-28 to 2031-32Decision The Policy and Resources Committee noted the current Budget Outlook position for the period 2027-28 to 2031-...
Funding request from local organisationsDecision The Policy and Resources Committee – 1. agreed to award a one-off grant of £36,000, to be paid from the Prio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.