Decision The Policy and Resources Committee – 1. Noted and endorsed that officers would continue to negotiate with Scottish Government to seek extension of the TIF project completion and debt repayment deadlines. 2. Noted the progress made relating to Dunbeg Gateway Features and Halfway House Roundabout. 3. Agreed that officers would develop a business case for further Council investment at the Oban Airport Business Park site for the development of a new headquarters office / hanger building to be leased on completion to TSL Contractors Limited (TSL) including utilising the remainder of funding previously approved by the P&R Committee for Oban Airport Business Park. 4. Agreed that officers would continue to progress with the other innovative proposals for the Oban Airport Business Park while the funding and tender bids were awaiting conclusion. 5. Noted that TSL would concurrently progress with the planning process in respect of the proposed development. 6. Noted the re-establishment of the Dunbeg Corridor Working Group that had held its first meeting with key stakeholders. (Reference: Report by Executive Director with responsibility for Development and Economic Growth dated 18 January 2022, submitted) *
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1This report updates Members on progress in respect of the Lorn Arc TIF initiative. 1.2 The timescale for delivery of many of the Lorn Arc Projects has changed from that which was originally anticipated at its inception. This is due in part to market conditions over a sustained period of time, project complexity in terms of delivery and most recently the restrictions associated with the pandemic. The report outlines that reflecting this changed timescale it will be prudent to seek to amend certain clauses of the TIF Agreement between the Council and the Scottish Government. Accordingly officers propose to begin negotiation with the Scottish Government to achieve realistic adjustment to the timescales set within the agreement, such that the project completion date and the TIF repayment period are extended. 1.3 Currently there are two live projects being taken forward. The first is the Dunbeg Gateway Feature/Halfway House Roundabout which has been progressing well since the approval of start up costs of £640k. This is a complex development with many stages to work through with development partners prior to a site start. The report outlines in detail the various elements of site investigation work which have been completed, and explains the immediate tasks going forward. In addition Dunbeg Corridor Working Group has been successfully reinstated with its first meeting held in December 2021. 1.4 The second project concerns the Oban Airport Business Park. Following the initial road infrastructure investment potential occupiers reported there were still too many unknown costs such as utilities and ground conditions to make a commitment. During 2020/21 Estates & Property Development undertook a number of studies to resolve these outstanding issues which has resulted in a number of substantial interests being received.In order to move forward it is proposed to prepare the business case for council investment in the further development of the site. Initially this involves a possible new headquarters office / hanger building to be leased on completion to TSL Contractors Limited (TSL). RECOMMENDATIONS
It is recommended Members:
Note and endorse that officers will continue to negotiate with Scottish Government to seek extension of the TIF project completion and debt repayment deadlines. Note the progress made relating to Dunbeg Gateway Features and Halfway House Roundabout. Consider and agree that officers should develop a business case for further Council investment at the Oban Airport Business Park site for the development of a new headquarters office / hanger building to be leased on completion to TSL Contractors Limited (TSL) including utilising the remainder of funding previously approved by the P&R Committee for Oban Airport Business Park. Consider and agree that officers should continue to progress with the other innovative proposals for the Oban Airport Business Park while the funding and tender bids are awaiting conclusion. Note that TSL will concurrently progress with the Planning process in respect of the proposed development. Note the re-establishment of the Dunbeg Corridor Working Group that has held its first meeting with key stakeholders. ARGYLL AND BUTE COUNCIL POLICY AND RESOURCES COMMITTEE
2.1This report provides an update to Members on the Lorn Arc Inititaive 2.2 It contains sections which deal with proposed amendments to the Tax Incremental Finance Agreement (TIF) between the Council and the Scottish Government. It also provides detailed updates on the current live projects at Dunbeg and Oban Airport.
Recommendations
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Budget outlook 2027-28 to 2031-32Decision The Policy and Resources Committee noted the current Budget Outlook position for the period 2027-28 to 2031-...
Funding request from local organisationsDecision The Policy and Resources Committee – 1. agreed to award a one-off grant of £36,000, to be paid from the Prio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.