TRANSFORMATIONAL PROJECTS & REGENERATION TEAM - LARGE SCALE PROJECT UPDATE REPORT
NotedCommittee1 paper
Environment, Development and Infrastructure Committee noted this item on Thursday 3 March 2022. Below is the council's own wording, with the papers it was decided on.
Decision The Environment, Development and Infrastructure Committee noted the progress contained within the submitted report. (Reference: Report by Executive Director with responsibility for Development and Economic Growth dated 18 January 2022, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Environment, Development and Infrastructure Committee
Executive summary
1.1The purpose of this report is to update Environment, Development and Infrastructure Committee on progress of the large-scale, externally funded project work of the Transformational Projects and Regeneration Team, and to highlight key issues that may impact on the successful delivery of projects.
1.2The last update report was considered by Environment Development and Infrastructure Committee in September 2021.
1.3The Team is currently responsible for the delivery of projects with a cumulative value of £37m. Projects are listed in Appendix A.
Recommendations
It is recommended that the Environment, Development and Infrastructure Committee consider, and note the current progress contained within the report. ARGYLL AND BUTE COUNCIL ENVIRONMENT, DEVELOPMENT & INFRASTRUCTURE COMMITTEE
DEVELOPMENT AND ECONOMIC 3 MARCH 2022 GROWTH
TRANSFORMATIONAL PROJECTS & REGENERATION TEAM – LARGE SCALE PROJECT UPDATE REPORT
2. INTRODUCTION
2.1This report sets out the current position of the large-scale projects, which are currently being delivered by the Transformational Projects and Regeneration Team.
2.2Transformational Projects and Regeneration sits within the council’s Development and Economic Growth Service and works region-wide. The Team has a particular focus on ‘place’, heritage regeneration, the creative industries, and works closely with communities and businesses to realise positive change.
2.3The Team’s work broadly includes the following areas of work:
Drafting/submitting bids to secure external funding of various scale, such as for Conservation Area Regeneration Scheme (CARS) programmes; Development/delivery of regeneration projects with a particular emphasis or theme, such as the suite of measures to encourage shopping locally; Development/delivery of a number of place-based engagement projects, working in partnership with the community and key partners, leading to action plans, such as charrettes, and working with communities to realise these community ambitions; Development of the economic opportunities for Argyll and Bute across Film, Creative Industry and Renewable sectors, with the objective of securing income to the area and delivering local economic benefit, including support to community organisations working across these sectors; Support to third sector organisations involved in the delivery of their own individual economic regeneration projects, as well as support to third sector organisations delivering regeneration focused projects where council funding is involved and/or where projects align with council outcomes, such as Regeneration Capital Grant Funded (RCGF) projects; Administration of the Council’s, Strategic Events and Festivals Grant; and; Overseeing the delivery programme and financial administration of projects supported through funding from Scottish Government, such as the Town Centre Fund (TCF) and Place Based Investment Fund (PBI). 2.4 This paper also seeks to report on key issues that may impact on the current status of each project, such as any amendments to project scope or timeframe.
2.5The 18 large-scale projects currently in delivery are included within the table in Appendix 1, and have a cumulative total value of £37m.
3.1It is recommended that the Environment, Development and Infrastructure Committee consider, and note the current progress contained within the report.
4. DETAILS
4.1The following sections summarise the progress associated with each of the large- scale projects that are currently in delivery and managed by the Transformational Projects and Regeneration Team. The projects are listed in Appendix 1.
Conservation Area Regeneration Scheme (CARS) Projects
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment, Development and Infrastructure Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Review of public convenience estateDecision The Environment, Development and Infrastructure Committee – 1. noted the findings of the updated baseline re...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.