WASTE PPP AND LANDFILL BAN COMPLIANCE - PROGRESS UPDATE ON OPTIONS
NotedCommittee1 paper
Environment, Development and Infrastructure Committee noted this item on Thursday 3 March 2022. Below is the council's own wording, with the papers it was decided on.
Decision The Environment, Development and Infrastructure Committee – 1. Endorsed the report and the approach being taken to determine the most appropriate option for the Council regarding waste disposal. 2. Noted that a further report detailing an options appraisal would come forward to the September Environment, Development and Infrastructure Committee, providing information on the preferred option and outlining any capital and revenue cost implications. (Reference: Report by Executive Director with responsibility for Roads and Infrastructure dated 11 January 2022, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Environment, Development and Infrastructure Committee
Executive summary
1.1This report is an update on the options being appraised to identify the most appropriate choice for the future of the Waste PPP that supports compliance with the Landfill ban and provides overall best value to Argyll & Bute Council. The transition to Landfill ban compliance will result in increased revenue costs from a combination of a higher gate fee and haulage costs. The purpose of the options appraisal is to identify what option offers the best overall value and the option that is the most deliverable. The review will identify and future proof the Councils journey in the respect of the handback of the PPP contract and will focus on the workable solution to accommodate the landfill ban ensuring that appropriate timescales are identified and the work process that is to be undertaken.
Recommendations
Members are recommended to:-
Endorse the report and the approach being taken to determine the most appropriate option for the Council regarding waste disposal; To note that a further report detailing an options appraisal will come forward to the September EDI Committee, providing information on the preferred option and outlining any capital and revenue cost implications. ARGYLL AND BUTE COUNCIL ENVIRONMENT, DEVELOPMENT & INFRASTRUCTURE COMMITTEE
ROAD AND INFRASTRUCTURE SERVICES 3 MARCH 2022
WASTE PPP AND LANDFILL BAN COMPLIANCE - PROGRESS UPDATE ON OPTIONS
2.0INTRODUCTION
2.1This report is an update on progress on the options to identify the most suitable option for the future of the Waste PPP contract to enable Officers to support compliance with the Landfill ban and provide overall best value to Argyll & Bute Council. The recommendations of this report form the basis of the request to the Scottish Government to mitigate against increased costs resulting from the PPP agreement. 2.2 The Council have a Waste PPP agreement with Renewi (formerly Shanks) that began in 2001. The 25 year PPP agreement subsists until September 2026. 2.3 Within the PPP area, around 25,000 tonnes of residual (general) waste is processed every year. The Waste PPP agreement covers the majority of the Council’s area and population. Argyll & Bute Council is the most expensive cost per household out of all of the local authorities in Scotland at around £200 per premise; the national average is around £100 per premise for waste disposal due to geography and PPP contract which processes general waste to provide a higher level of diversion from landfill than provided by many other Scottish Authorities. 2.4 The ban on the disposal of Biodegradable Municipal Waste ban to Landfill is a measure brought in under the Waste (Scotland) Regulations 2012. The alternative to Landfill is a transition from Waste Disposal to Waste recovery via Energy from Waste (EfW). The Scottish Government announced a national review of EfW which will run until March 2022. Further information on the outputs from this review will be shared with members post March 2022.
2.5To comply with the Landfill ban the Council is required to ensure that residual waste will go for recovery via EfW rather than disposal at landfill. Increasing uncertainty in terms of national policy for waste disposal is impacting on the Council’s time line for having in place a compliant solution. 3.0 RECOMMENDATIONS
3.1Members are recommended to:-
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment, Development and Infrastructure Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Review of public convenience estateDecision The Environment, Development and Infrastructure Committee – 1. noted the findings of the updated baseline re...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.