Decision The Helensburgh and Lomond Area Committee: 1. provided comments on the draft programme contained at appendix 1 of the report, which were noted by the Head of Roads and Infrastructure Services; and 2. noted that the programme would go forward to the Environment, Development and Infrastructure Committee on 21 March 2024 for endorsement. (Reference: Report by Executive Director with responsibility for Roads and Infrastructure Services, dated February 2024, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1Attached to this report is a draft programme for roads reconstruction schemes for 2024/25 in the Helensburgh and Lomond area. This programme has been designed using the current Road Condition Index (RCI) which is produced by the national road condition survey data. In addition to the RCI data, information such as road traffic collisions, known development, activities such as timber harvesting and skid condition (of the carriageways surface) which is measured by a separate survey are also considered together with information brought forward from Elected Members during agreed Area Business Days with officers from Roads and Infrastructure Service. This information is considered at officer level when appropriate engineering judgement is also applied to ensure that maximum benefit can be derived from the available investment.
1.2The Roads Reconstruction Programme has been structured in line with the Roads Asset Management and Maintenance Strategy. The focus has been to arrest the rate of decline and provide an overall improvement in condition as has been demonstrated in the Annual Status and Options Report. In previous years this has been achieved through the delivery of a mix of carriageway resurfacing, edge strengthening, patching/surface dressing and in-situ road surface recycling. These treatments have been designed to seal the road to stop the ingress of water, improve ride quality and reduce the number of reactive repairs. This has resulted in an overall improvement in road conditions. Without this investment and works there would have been a significant deterioration in condition and a detriment to the travelling public, economic opportunity and tourism.
1.3Following the Council’s Budget Meeting, which took place on 22 nd February 2024, £8M has been confirmed for the Capital Roads Reconstruction budget.
1.4As per previous years any post winter deterioration may result in some adjustment to the programme to ensure that the best rates of return in terms of whole life costs can be achieved. 2.0 RECOMMENDATION
2.1It is recommended that the Helensburgh and Lomond Area Committee:
• Provide comments on the draft programme that is contained in Appendix 1 of this report. • Note that the programme will go forward to the Environment, Development and Infrastructure Committee on 21 March 2024 for endorsement.
3.0DETAIL
3.1The focus of the roads reconstruction programme has been to recover the network through the delivery of a mix of carriageway resurfacing schemes, patching/surface dressing and in-situ road surface recycling, which follow the principles set out within the Roads Asset Management Plan.
3.2This Council has approximately £122M of backlog maintenance (based on figures produced by SCOTS) across the road network. This means that over £122M would need to be invested to bring the road network up to an ‘A1’ standard. Most councils are in a very similar position. During these challenging financial times, it is very unlikely we will benefit from the level of investment required to bring the road network up to an ‘A1’ condition.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Helensburgh & Lomond Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Area performance report - fq1 2026/27Decision The Helensburgh and Lomond Area Committee noted the performance and supporting commentary as presented. (Ref...
Supporting communities fund 2026/27Decision The Helensburgh and Lomond Area Committee agreed that the 18 applications, marked as Award’ and ‘Partial Awa...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.