Environment, Development and Infrastructure Committee noted this item on Thursday 20 June 2024. Below is the council's own wording, with the papers it was decided on.
Decision The Environment, Development and Infrastructure Committee – 1. noted the content of the submitted report; and 2. endorsed the proposals by officers to lobby for funding and explore external funding opportunities and agreed that the Chair engages with the Scottish Government to try and secure additional resource to mitigate flooding issues in Oban. (Reference: Report by Executive Director with responsibility for Roads and Infrastructure Services dated May 2024, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Environment, Development and Infrastructure Committee
Recommendations
2.1It is recommended that the Environment, Development and Infrastructure Committee:
i. Consider and note this report. ii. Endorse the proposals by officers to lobby for funding and to explore external funding opportunities
3.0DETAIL
3.1SEPA’s Flood maps (Appendices 1,2 and 3) show areas susceptible to Coastal, Fluvial (watercourse) and Surface Water flooding. Full map coverage available from Flood Maps | SEPA - Flood Maps | SEPA
3.2Coastal flooding is influenced by high astronomical tides and tidal surges caused by low atmospheric pressure and storm events. In certain conditions, when high spring tides are worsened by tidal surge, sea water will flood into the tidal reach of the Black Lynn burn. The combination of tidal and high flows in the Black Lynn burn cause flooding in adjacent areas. Subject to the necessary permissions it is proposed that some clearance work is carried out. Whilst these works will provide some additional water storage capacity, they are not expected to mitigate against any significant weather event.
3.3In addition to this the Scottish Water combined sewers (drains that contain both storm water and foul sewerage) can also surcharge adding raw sewerage to the combined source flood waters. The Lochavullin car park has a pumping system which copes with low levels of water, however, above a certain level there is nowhere to pump water to and the pumps become ineffective.
3.4The consequences of these flooding events can often result in roads having to be closed for safety resulting in significant diversions and significant flood damage to adjacent businesses.
3.5Climate change is very likely to increase the severity and frequency of flood events. Current guidance (SEPA Climate change allowances for flood risk assessment in land use planning) points to the following changes:
• By 2100 Peak River Flows in Argyll increase by 59% of the 2017 values • By 2080 Peak Rainfall Intensities increase by 46% of the 2017 values • By 2100 cumulative rise in sea level above 2017 levels will be 0.86m
3.6In Cycle 1 of the Highland and Argyll Local Flood Risk Management Plan 2016- 22 Oban was identified as a Potentially Vulnerable Area (PVA) for flooding and an Action was placed on the Council to carry out a Flood Study and Surface Water Management Plan.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment, Development and Infrastructure Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Review of public convenience estateDecision The Environment, Development and Infrastructure Committee – 1. noted the findings of the updated baseline re...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.