Environment, Development and Infrastructure Committee noted this item on Thursday 20 June 2024. Below is the council's own wording, with the papers it was decided on.
Decision The Environment, Development and Infrastructure Committee – 1. noted the update regarding discussions held with Scottish Government on the Waste PPP contract; 2. noted the implications of Argyll and Bute Council not receiving the derogation from the Scottish Government, and approved the variation of the Waste PPP contract with Renewi to enable the conversion of the Mechanical Biological Treatment (MBT) plants into Waste Transfer Stations for Biodegradable Municipal Waste (BMW) ban compliance; 3. noted the discussion relating to financial support from Scottish Government and instructed Officers to continue to pursue the Scottish Government for the additional costs for compliance with the BMW ban (circa £1.5m); 4. agreed that the Chair of the Committee engages with the Cabinet Secretary to secure financial support from Scottish Government for the additional costs for compliance with the BMW ban (circa £1.5m); and 5. noted that Renewi had formally notified officers that their UK operation, including the Argyll and Bute Contract, was being taken over by Biffa. (Reference: Report by Executive Director with responsibility for Roads and Infrastructure dated May 2024, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Environment, Development and Infrastructure Committee
ARGYLL AND BUTE COUNCIL ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE COMMITTEE
ROAD AND INFRASTRUCTURE SERVICES 20 JUNE 2024
WASTE UPDATE
1.0INTRODUCTION
1.1Argyll and Bute Council currently has a 3 model waste disposal arrangement in place. This consists of island landfill sites which the Council operate, a third party off taker for the refuse collected in Helensburgh and Lomond and a PPP contract for the remainder of the Council area which runs until September 2026.
1.2Scottish Government are introducing a Biodegradable Municipal Waste (BMW) Landfill ban at the end of December 2025. The landfill ban will mean that almost all biodegradable material (food, card, paper, pet feces, garden waste etc) will no longer be able to go to landfill. Landfill sites will be retained to take non- biodegradable materials such as rubble and some limited biodegradable materials such as plaster board and animal remains from slaughterhouse processes.
1.3The Council’s island landfill sites have had works carried out to facilitate waste transfer ahead of the BMW ban. The Helensburgh and Lomond area has third party off taker currently in place for its waste disposal and an Energy from Waste (EFW) provider will be in place for the 2026 BMW ban.
1.4The Council’s PPP contract which covers the remainder of Argyll and Bute currently operates Mechanical Biological Treatment (MBT) plants. MBT plants reduce the amount of material which goes to landfill through processing, separation of materials and the production of compost like output (CLO) which is used in landfill restoration. The MBT process will not be permitted with the BMW ban. In December 2022 the Council Leader wrote to Scottish Government (SG) requesting either a derogation, to allow the MBT plant to continue under the PPP contract for a 9 month period beyond the BMW ban when the PPP contract came to a natural end or for the additional costs to be made available to the Council, c£1.5M to enable the PPP contract to be varied to be compliant with the BMW ban.
1.5At the March 2024 meeting of the Environment, Development and Infrastructure Committee, Members considered a report covering a number of work streams regarding recycling and waste disposal. This report provides an update regarding the Council’s request to Scottish Government for a derogation for the Council’s PPP contract. 2.0 RECOMMENDATIONS
2.1It is recommended that Members of the Environment, Development and Infrastructure Committee:-
i. Consider and note the update regarding discussions held with Scottish Government on the Waste PPP contract; ii. Consider the implications of Argyll and Bute Council not receiving the derogation from the Scottish Government, and approve the variation of the Waste PPP contract with Renewi to enable the conversion of the MBT plants into Waste Transfer Stations for BMW ban compliance; iii. Note the discussion relating to financial support from Scottish Government and instruct Officers to continue to pursue the Scottish Government for the additional costs for compliance with the BMW ban (circa £1.5m). iv. Note that Renewi have formally notified officers that their UK operation, including the Argyll and Bute Contract, is being taken over by Biffa
3.0DETAIL
3.1Waste PPP
3.1.1 In December 2022, the Council’s Environment, Development and Infrastructure Committee agreed to pursue a derogation from the Scottish Government, from the implementation date of the Biodegradable Municipal Waste Ban of 1 January 2026 to the end of the Council’s Waste PPP contract in September 2026.
3.1.2 The Council has in place a 25 year Waste PPP contract which ends in September 2026. The Waste PPP contract covers Oban and Lorn, Mid Argyll and Kintyre, Bute and Cowal together with the inner islands.
3.1.3 The Scottish Government are due to introduce a Biodegradable Municipal Waste (BMW) landfill ban from the end of December 2025. The last 9 months of the PPP 25 year contract will not be compliant with the new regulation.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment, Development and Infrastructure Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Review of public convenience estateDecision The Environment, Development and Infrastructure Committee – 1. noted the findings of the updated baseline re...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.