Resolved
Decision The Environment, Development and Infrastructure Committee – 1. noted that the proposed Helensburgh Waste Transfer Station no longer provided the optimum solution to ensure Biodegradable Municipal Waste compliant disposal arrangements in the Helensburgh and Lomond area; 2. agreed that officers should not progress further with the development and delivery of the Helensburgh Waste Transfer Station Project; 3. recommended to the Policy and Resources Committee that the remainder of the £3m of budget earmarked for this project be retained to support other funding related pressures within the waste service; and 4. noted that should circumstances change, specifically the cost benefit ration, that the scheme could be revisited. (Reference: Report by Executive Director with responsibility for Roads and Infrastructure Services dated February 2025, submitted)