ISLAND-BASED STRATEGIC TOURISM INFRASTRUCTURE DEVELOPMENT PROJECTS
NotedCommittee2 papers
Environment, Development and Infrastructure Committee noted this item on Thursday 20 March 2025. Below is the council's own wording, with the papers it was decided on.
Decision The Environment, Development and Infrastructure Committee – 1. considered the content of the paper and Appendix 1 of the report; 2. noted the origin of the projects listed in Table 1 and that the STID was a live document; 3. agreed that the three projects noted in section 1.5 of the report, Bute Forest (Bute), Royal Society for the Protection of Birds (Islay) and Hynish Trust ( Tiree ) could be taken forward to the Design Grant (available throughout 2025) and/or full Rural Tourism Infrastructure Fund application stage, as appropriate, in time for the deadline of the end of April 2025. (Reference: Report by Executive Director with responsibility for Development and Economic Growth dated 17 February 2025, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Environment, Development and Infrastructure Committee
ARGYLL AND BUTE COUNCIL ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE
DEVELOPMENT & ECONOMIC 20TH MARCH 2025 GROWTH
ISLAND-BASED STRATEGIC TOURISM INFRASTRUCTURE DEVELOPMENT PROJECTS
1.0INTRODUCTION
1.1The purpose of this paper is to inform the Environment, Development and Infrastructure (EDI) Committee of a recent review of a limited number of island- based projects and to seek approval, based on officer recommendations, on three island-based projects out of this series of previously identified Strategic Tourism Infrastructure Development (STID) proposals to take forward for 2025/26 Rural Tourism Infrastructure Fund funding applications. The proposals were initially developed locally by community groups, or charitable bodies, and further assessed using £35k of funding awarded to the council from VisitScotland in 2023. None of these projects are council-led, nor council funded.
1.2The Scottish Government, through VisitScotland, introduced a Rural Tourism Infrastructure Fund (RTIF) to help alleviate pressures from increased numbers of tourists in fragile areas (hotspots). Argyll and Bute Council has, to date, been successful in securing £1.98 million of funding from RTIF for a number of projects, including one council-led project at Fionnphort. Applications for RTIF funding are submitted by a local authority, or a National Park, on behalf of external organisations or internal departments. The council has no financial commitments in the case of external organisations, except officer time.
1.3In 2022, VisitScotland introduced a small fund to help develop projects before submission for full RTIF funding (up to £700k). This new fund was called the Strategic Tourism Infrastructure Development (STID) fund where up to £35k could be awarded to each STID application. One of the introduced criteria for STID is that it must cover a large number of projects over a considerable geographic area, islands in this case, and not focus on a single project.
1.4In 2023, following discussions with VisitScotland on projects that arose from community engagement by the Staycation and the Settlement Officers, the council was invited by VisitScotland to submit an application for projects that were island- based. Officers subsequently submitted the application comprising 11 proposals for STID funding. This application was then awarded £35k of funding to procure consultants to prepare a STID Plan. Ironside Farrar secured the commission and the final STID Plan was completed in May 2024 (see Appendix 1). 1.5 Each of the 11 projects (Table 1.) was advised of the possibility of an application being submitted to both a Design Award to enable them to further develop their project (e.g. for the planning process and drawings) and full RTIF application in early February 2025. Project leaders were emailed requesting an indication of readiness/willingness to apply for funding. A deadline of 5 pm on 17th February 2025 was given. At the time of writing (18th February 2025) three projects have registered an interest in proceeding, one with the full RTIF application only (Bute Forest P 27 of Appendix 1.) and two with both the Design Grant and full RTIF applications (Hynish Trust Page 20 of Appendix 1., RSPB Page 79 of Appendix 1.). It is proposed that officers progress these applications subject to member approval (note that the remaining projects may still apply for a Design Grant at any time in 2025 as this has no deadline and may subsequently apply to a potential RTIF funding round, should one be announced).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment, Development and Infrastructure Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Review of public convenience estateDecision The Environment, Development and Infrastructure Committee – 1. noted the findings of the updated baseline re...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.