Leisure Transformation Programme - Replacement Leisure Centre in Kirkby-in-Ashfield

Agreed Executive 1 paper

Cabinet agreed this item on Thursday 22 June 2017. Below is the council's own wording, with the papers it was decided on.

ItemCA.6

Resolved

a) That Cabinet agrees to progress to the next stage of determining the feasibility of the preferred option to replace the existing leisure centre with a new flagship leisure destination in Kirkby-in-Ashfield, on the preferred key town centre site identified in the evaluation and within the prescribed time frame; b) That if land acquisition of the preferred site cannot be achieved, Cabinet agrees to progress to the next stage of determining the feasibility of the redevelopment of the current Festival Hall site option (retaining the existing site for use during construction for as long as possible); c) That Cabinet agrees to commence the re-tendering of the Leisure Management Contract by producing a ‘shadow bid’ followed by soft market testing; d) That opportunities for obtaining external funding be explored in order to help meet the costs of the project; e) That Cabinet agrees an exemption under Part 11 of the Contractual Procedure Rules to enable the Chief Executive (in consultation with the Portfolio Holder) to further commission the existing consultants for the recommended and associated works, subject to this commission being tested and found to represent value for money.
Word for word from the decision Ashfield published for this meeting. Source: democracy.ashfield.gov.uk

Follow this further

Built from Ashfield's papers

What the report saysPro

Report to Cabinet

Purpose of report

Following an extensive feasibility study, to update Cabinet on the Leisure Facilities Transformation Programme and to seek authorisation to proceed with the next steps towards delivering the Council’s aspiration to deliver a new flagship leisure destination in Kirkby-in- Ashfield.

Recommendation(s)

a. i) Progress the next stage of the feasibility into the preferred option which is to replace the existing Leisure Centre with a new flagship Leisure destination in Kirkby in Ashfield on the preferred key town centre site identified in the evaluation and within the prescribed timeframe or ii) if land acquisition of the preferred site cannot be achieved, progress the feasibility into the redevelopment of the current Festival Hall site option (retaining the existing site for use during construction for as long as possible). b. To commence the retendering of the Leisure Management contract by producing a ‘shadow bid’ followed by soft market testing. c. To explore external funding opportunities. In order to deliver the project there needs to be a combination of capital, revenue and external funding. d. Due to the specialist nature of the work and knowledge already gained by the existing consultant, Cabinet is requested to grant an exemption from Contract Procedure Rules enabling the Chief Executive (in consultation with the Portfolio Holder) to further commission the existing consultants for the recommended and associated works if the value for money has been tested. (Exemption Part 11 of the contractual procedural rules paragraph 66.6) Reasons For Recommendation(s)

This report is to update Cabinet on Key Projects within the Council’s Corporate Plan (2016- 2019) including, the feasibility for a replacement for the Festival Hall Leisure Centre (informed by the Leisure Review).

Alternative Options Considered (With Reasons Why Not Adopted)

Do nothing: not recommended for a number of reasons. The Leisure Facilities Review has allowed the Council to understand the appropriateness of its current leisure stock and future requirements. The provision of an effective facility infrastructure will be central to the successful delivery of the health and wellbeing objectives within the Corporate Plan (2016- 2019).

Detailed Information

Background

1.1The Council’s Vision

The Council vision is for local people to have access to modern leisure facilities to help lead healthier lifestyles. A clear approach to providing facilities has been identified including maximizing and rationalizing the use of the Council’s assets alongside coordinated provision from other sources.

To help sustain leisure provision into the future, the Council’s Vision is ‘to secure a district- wide network of quality, affordable, accessible and sustainable Leisure Centres and services for the benefit of all residents of Ashfield'. In order to achieve the Council’s vision Key Projects have been identified within the Corporate Plan: firstly was to carry out a Leisure Facilities Review (July 2016) and secondly, to explore the feasibility for a replacement for the Festival Hall Leisure Centre (informed by the Leisure Review).

1.2Leisure Review

The council recognises the need to invest in its sport and leisure infrastructure to meet the objectives of reducing inactivity and improving the health and wellbeing of its residents; as well as ensuring the most cost effective provision. In order to address Corporate Plan priorities, an extensive Leisure Facilities Review was undertaken and Cabinet endorsed the findings on 14th July 2016.

The transformation programme for leisure centre provision has a clear approach to providing future facilities, including maximising and rationalising the use of Council assets, alongside coordinated provision from other sources.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Leisure Transformation Programme: Replacement Leisure Centre in Kirkby-in-AshfieldReport 448 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 14 attended
CB
Craig BonarOfficer, in attendance
AB
Councillor Amanda BrownCommittee Member, present
TB
Councillor Tim BrownCommittee Member, present
CB
Councillor Cheryl ButlerChair, present
DD
Councillor Don DavisCommittee Member, present
RD
Ruth DennisOfficer, in attendance
TH
Councillor Tom HollisGuest, present
JJ
Councillor Jackie JamesCommittee Member, present
SL
Sharon LynchOfficer, in attendance
RM
Councillor Rachel MaddenGuest, present
AM
Alan MaherOfficer, in attendance
RM
Robert MitchellOfficer, in attendance

All 14 on the meeting page

On this subject at Ashfield

Search all
  1. Leisure Transformation Programme - Replacement Leisure Centre in Kirkby-in-AshfieldThis decision
  2. Leisure Transformation Programme - UpdateNoted
  3. Leisure Transformation Programme - UpdateNoted
  4. Leisure Transformation Programme - UpdateNoted
  5. Leisure Transformation Programme: Hucknall Leisure Centre CostingsNoted
  6. Leisure Transformation ProgrammeNoted

More from Ashfield Cabinet

All decisions
MeetingDecisionOutcome
27 Jul 2026 Local Government Reorganisation (Verbal Update and Q/A Session)RESOLVED that a) the information provided and the ongoing work being undertaken to support the transition programme, ... Noted Open
27 Jul 2026 Corporate Plan Year End Delivery 2025/26RESOLVED that a) the levels of delivery achieved against the Corporate Plan Priorities, as outlined in the report, be... Noted Open
27 Jul 2026 Corporate Risk Year End 2025/26 PositionRESOLVED that the current significant items on the Corporate Risk Register, as presented, be received and noted. Reas... Noted Open
27 Jul 2026 Update - Charitable Trust Issues at Lord Francis Park (Kirkby-in-Ashfield), Hucknall Leisure Centre and Titchfield Park (Hucknall)RESOLVED that a) the current position relating to Charitable Trust Issues at Lord Francis Park (Kirkby-In-Ashfield), ... Noted Open
27 Jul 2026 Appropriation of Land at Kingsway ParkRESOLVED that a) it be noted that the Secretary of State for Housing, Communities & Local Government granted consent ... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies