RESOLVED that a) the works undertaken to improve the facilities at Hucknall Leisure Centre and the plans to consider further improvements of a combined spend up to the value of £1.3m as part of the new Leisure Operator contract tender, be noted and endorsed; b) delegated authority be granted to the Director of Place and Communities, in consultation with the Leader of the Council, to enter into discussions with the Governing Body of Edgewood Primary and Nursery School to come to a mutual agreement regarding the Council withdrawing from the operational management agreement for Edgewood Leisure Centre; c) in accordance with Article 12 of the Constitution, the Director of Legal and Governance be authorised to complete, sign and serve any documentation which is necessary as part of the mutually agreed withdrawal from the operational management agreement for Edgewood Leisure Centre on the instructions of the Director of Place and Communities and in consultation with the Leader of the Council.
Word for word from the decision Ashfield published for this meeting.Source: democracy.ashfield.gov.uk
To update Cabinet on the Leisure Transformation Programme in relation to Hucknall and Edgewood Leisure Centres.
This report seeks to inform Cabinet of the works undertaken to improve the facilities at Hucknall Leisure Centre and plans to consider further improvements as part of the re-tendering of the Leisure Operator contract.
The report also seeks delegated authority to consider the Council’s withdrawal from the operational management contract for Edgewood Leisure Centre and the transfer back of the facility through mutual agreement to Edgewood School. Recommendation(s)
Cabinet is asked:
1) To note and endorse the works undertaken to improve the facilities at Hucknall Leisure Centre and the plans to consider further improvements of a combined spend up to the value of £1.3m as part of the new Leisure Operator contract tender;
2) To grant delegated authority to the Director of Place and Communities, in consultation with the Leader of the Council, to enter into discussions with the Governing Body of Edgewood Primary and Nursery School to come to a mutual agreement regarding the Council withdrawing from the operational management agreement for Edgewood Leisure Centre; and
3) In accordance with Article 12 of the Constitution, to authorise the Director of Legal and Governance to complete, sign and serve, any documentation which is necessary as part of the mutually agreed withdrawal from the operational management agreement for Edgewood Leisure Centre on the instructions of the Director of Place and Communities and in consultation with the Leader of the Council.
Reasons for Recommendation(s)
A key project within the Ashfield District Council Corporate Plan (2019 to 2023) is to prioritise the health and wellbeing of the residents of Ashfield and to implement the agreed outcomes from the Leisure Transformation Programme by exploring and implementing options for the future of the Council’s Leisure Centre stock.
Approval of the recommendations will enable the Leisure Transformation Programme to continue to be developed to the next stage, including capital investment into Hucknall’s leisure offer and the delivery of revenue savings through an “invest to save” approach resulting in a reduction in revenue costs at the point where the Council retenders the leisure operator contract.
Alternative options considered
Maintaining the current operation does not allow the Authority to achieve the aims of the Corporate Plan through asset rationalisation as recommended in the Leisure Facilities Strategy.
Do nothing: Not recommended for a number of reasons. The Leisure Facilities Review has allowed the Council to understand the appropriateness of its current leisure stock and future requirements. The provision of an effective facility infrastructure will be central to the successful delivery of the health and wellbeing objectives within the Corporate Plan and to achieving savings through the leisure contract.
Detailed Information
The Council’s Vision
The Council’s vision is for local people to have access to modern leisure facilities to help lead healthier lifestyles. A clear approach to providing facilities has been identified, including investment and rationalising the use of the Council’s assets alongside coordinated provision from other sources.
To help sustain leisure provision into the future, the Council’s Vision is ‘to secure a districtwide network of quality, affordable, accessible and sustainable Leisure Centres and services for the benefit of all residents of Ashfield'.
In order to achieve the Council’s vision, key projects have been identified within the new Corporate Plan (2019–2023) under the Health and Happiness priority: to deliver the Leisure Transformation programme, maximising the wellbeing benefits whilst reducing costs.
Leisure Review
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Plan Year End Delivery 2025/26RESOLVED that a) the levels of delivery achieved against the Corporate Plan Priorities, as outlined in the report, be...
Corporate Risk Year End 2025/26 PositionRESOLVED that the current significant items on the Corporate Risk Register, as presented, be received and noted. Reas...
Appropriation of Land at Kingsway ParkRESOLVED that a) it be noted that the Secretary of State for Housing, Communities & Local Government granted consent ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.