RESOLVED that a) the progress in appointing a new Leisure Operating Contractor for the period of April 2021 onwards for a duration of 10 years with a Council retained ability to extend for a further 5 years, be noted; b) delegated authority be granted to the Director of Place and Communities in conjunction with the Corporate Finance Manager, the Leader and the Deputy Leader (Inward focus) to enter the Council into contract with the successful tenderer for the construction of the new Kirkby Leisure Centre; c) delegated authority be also granted to the Director of Place and Communities in conjunction with the Corporate Finance Manager, the Leader and the Deputy Leader (Inward focus) to enter the Council into contract with the successful tender for the enabling works package of initial capital works onsite; d) the Council continues to work with the current leisure operator SLM and delegated authority be granted to the Director of Place and Communities, in conjunction with the Corporate Finance Manager (and Section 151 Officer), the Leader and Deputy Leader of the Council, to support ongoing operations until the new contract commences in April 2021.
Word for word from the decision Ashfield published for this meeting.Source: democracy.ashfield.gov.uk
To update Cabinet in terms of the progress with the Leisure Transformation Programme including the procurement of a new Operating Contractor and the due diligence progress towards the development of the new Leisure Centre in Kirkby which will replace Festival Hall.
To gain approval from Cabinet to enter into a suitable build contract following the completion of the ongoing tender process.
Recommendation(s)
1) That Cabinet notes the progress in appointing a new Leisure Operating Contractor for the period of April 2021 onwards for a duration of 10 years with a Council retained ability to extend for a further 5 years.
2) That Cabinet gives Delegated Authority to the Director of Place & Communities in conjunction with the Corporate Finance Manager and The Leader and Deputy Leader (Inward focus) to enter the Council into contract with the successful tenderer for the construction of the new Kirkby Leisure Centre.
3) That Cabinet gives Delegated Authority to the Director of Place & Communities in conjunction with the Corporate Finance Manager, the Leader and Deputy Leader (Inward focus) to enter the Council into contract with the successful tender for the enabling works package of initial capital works onsite.
Reasons for Recommendation(s)
Cabinet will recall the previous reports regarding progress with the procurement of the Leisure Operating Contract, including the report from January 2019 which outlined the Delegated Authority to the Director of Place and Communities to enter into the resultant contract following the conclusion of the procurement process.
Council officers continue to progress with the procurement of the leisure operating contractor and the current programme will see them appointed in good time to achieve contract start in April 2021. The procurement of this is being completed in conjunction with the development of the new leisure centre at Kirkby in Ashfield.
The Leisure Centre development at Kirkby has already achieved Planning Permission and has concluded design to RIBA 4 stage. The works are currently out to tender and we anticipate that works will commence in Q3 of the 2020/21 financial year.
Previous reports for the development of the leisure centre have enabled officers to progress with the appointment of the design team and to commence the procurement process. This report requests further approvals to appoint the successful tenderer to construct and complete the new leisure centre development.
The timing of the tender return (17th September) and then completion of the necessary due diligence will fall between applicable governance meetings at the Council and delegated authority to the Director of Place and Communities, Corporate Finance Manager, the Portfolio Holder and the Leader and Deputy Leader (Inward Focus), is sought to ensure continuing momentum with this development.
Alternative options considered
Leisure Operating Contract – do not proceed (Not recommended)
Cabinet can consider whether to continue supporting the procurement of a new Leisure Operating Contractor. This is not recommended.
The existing operating contract with SLM has run for many years. It is due to cease at the end of March 2021 and there is no contractual ability to extend the existing contract.
Leisure Operating Contract – run services in-house (Not recommended)
Cabinet can consider whether it is appropriate to operate the leisure centres in-house. This is not recommended.
Given the levels of competition within the sector, the lack of expertise and experience within the Council, this is not considered a viable option with which to progress. Additionally this route will not achieve the necessary revenue savings to cross fund the development of the new Leisure Centre.
Kirkby Leisure Centre – do not proceed (Not recommended)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Plan Year End Delivery 2025/26RESOLVED that a) the levels of delivery achieved against the Corporate Plan Priorities, as outlined in the report, be...
Corporate Risk Year End 2025/26 PositionRESOLVED that the current significant items on the Corporate Risk Register, as presented, be received and noted. Reas...
Appropriation of Land at Kingsway ParkRESOLVED that a) it be noted that the Secretary of State for Housing, Communities & Local Government granted consent ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.