RESOLVED that the report be accepted and Cabinet p rovided the appropriate challenge to the financial outcomes in the report; continued to support appropriate financial control procedures agreed by Council and noted the budgetary control and monitoring procedures in place within the Capital Team, to safeguard Authority funding (Option 1).
Word for word from the decision Blaenau Gwent published for this meeting.Source: democracy.blaenau-gwent.gov.uk
Cabinet and Council only Date signed off by the Monitoring Officer: 10.11.23 Date signed off by the Section 151 Officer: 16.11.23
Committee: Cabinet Date of meeting: 29 November 2023 Report Subject: Capital Budget Monitoring, Forecast For 2023/2024 Financial Year (As at 30 September 2023) Portfolio Holder: Cllr S Thomas – Leader & Cabinet Member Corporate Overview & Performance Report Submitted by: Rhian Hayden – Chief Officer Resources
Reporting Pathway Directorate Corporate Portfolio Governan Democratic Scrutiny Cabinet Council Other Management Leadership Holder / ce & Audit Services Committee (please Team Team Chair Committee Committee state) 26/10/2023 09.11.23 16/11/23 29/11/23 (Briefing)
1. Purpose of the Report 1.1 To provide Members with an overview of each Portfolio’s actual and forecast capital expenditure against funding approvals for the 2023/2024 financial year, as at 30th September 2023.
2. Scope and Background 2.1 This report provides details on the following:
• Forecast financial position to 31st March 2024 across all portfolios. • Details of any significant adverse and/or favourable variances
2.2This report forms part of the councils financial reporting framework.
3. Options for Recommendation 3.1 Option 1 (Recommended Option)
• Members to consider and provide appropriate challenge to the financial outcomes in the report. • Continue to support appropriate financial control procedures agreed by Council. • To note the budgetary control and monitoring procedures in place within the Capital Team, to safeguard Authority funding.
3.2Option 2 Do not accept the report.
4. Evidence of how this topic supports the achievement of the Corporate Plan / Statutory Responsibilities / Blaenau Gwent Well-being Plan 4.1 This report supports the Forward-Looking Corporate Plan 2022/27 as it ensures effective forward financial planning arrangements are in place to support the Council’s financial resilience. This is a key element to achieving “An ambitious and innovative council delivering quality services at the right time and in the right place”. 5. Implications Against Each Option
5.1Impact on Budget (short and long term impact)
5.1.1 The current capital programme is approximately £116m and is funded by: -
WG Grant - £82m Other grant funding - £12m Council Resources - £22m
The Capital programme has been updated to include the projects recently agreed by Council, it is forecast that expenditure of £66.35m will be incurred on capital projects / schemes during 2023/24, with the remainder allocated for use in future years.
The overall financial position as forecast at 30th September 2023 indicates a breakeven position against a total in year capital budget of £66.35m.
The overall position across all Portfolios is shown below: -
Total Future In year Forecast Actual Forecast Approvals funding funding Expenditure Expenditure to to Variance Q2 30/09/2023 underspent 31/03/2024 (Month 6) / (Sept (overspent) 2023)
£000 £000 £000 £000 £000 £000
116,284 49,931 66,353 66,353 23,445 -
5.1.2 Previous reports have identified overspends against the Childcare Offer – Swffryd Scheme project, totalling £72,248. A variation request has been submitted to Welsh Government for virement of funding from an existing approved scheme, that no longer requires the funding. It has been presented to Sustainable Communities for Learning Panel and are awaiting Ministerial approval. In anticipation of the variation request being approved the project has been shown as fully funded.
5.2Risk including Mitigating Actions
5.2.1 Expenditure against external funding approvals needs to be maximised in order to avoid loss of funding. If significant delays in capital expenditure are anticipated or contract costs rise due to the impact of Covid-19, inflation pressures and the cost of living crisis, liaison with funding bodies will be required at the earliest opportunity in order to secure approval for funding re-profile.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.