Resolved
RESOLVED that the Forum note the progress being made with the implementation of the first phase of construction projects under the Primary Capital Strategy for Change.
Schools Forum noted this item on Thursday 17 June 2010. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Forum note the progress being made with the implementation of the first phase of construction projects under the Primary Capital Strategy for Change.
1.1The purpose of this report is to inform the Schools Forum about the progress of the first phase of construction projects under the Primary Capital Strategy for Change.
2.1That the Schools Forum NOTE the progress being made with the implementation of the first phase of construction projects under the Primary Capital Strategy for Change.
3.1This is a significant capital programme that is of interest to all schools in the borough.
4.1These were considered during the master planning stages.
5 SUPPORTING INFORMATION
5.1DCSF approved the Council’s Primary Capital Strategy for Change (PCSfC) in September 2008, and awarded the Council £8.378m of Primary Capital Programme grant for the current spending review period that ends in March 2011. At the same time the DCSF indicated that Primary Capital Funding would be made available for a further 14 years, subject to spending review decisions. In accordance with DCSF criteria for receiving the funding, the strategy had been agreed following extensive consultation with pupils, all primary, infant and junior schools, the diocesan authorities, the Council’s senior management team and the full Executive.
5.2The PCSfC is designed to be a strategic approach to capital investment for primary schools, with the agreed high investment priorities being sufficiency of school places, building condition and suitability of accommodation, medium priorities being disability access and low attainment and achievement, with high deprivation the lowest priority. In December 2009 the Executive approved the appointment of EC Harris as capital Managing Partners to help the Council deliver the PCSfC. The Council has also agreed to contribute £0.600m to the programme in 2010-11 from its own capital resources, with the strategy also setting out the conditions on which schools will be asked to make a financial contribution. Rising School Rolls – Additional School Places
5.3The local authority has a statutory duty to provide sufficient pupil places. Bracknell Forest’s Admissions Arrangements aspire to providing a school place for every child in the Designated Area (DA) or school catchments area in which they live. Every school has a designated area and the Council’s Admissions Policy gives first preference to DA residents.
5.4The trend of falling school rolls of the past five years has reversed and primary pupil numbers are now increasing. Pressure is most acute in the North of the Borough, and based on current forecasts in the 2009-14 School Places Plan (SPP), there will be a deficit of primary pupil places in North Bracknell of up to 10% of places across all North Bracknell primary schools over the next five years. This amounts to approximately 350 places, or 50 per year group.
5.5Additional school places are required to meet this deficit. Two additional forms of entry will be provided, one each at the Meadow Vale and Holly Spring schools. This amounts to 420 new places or 60 per year group (numbers have been rounded up to meet Infant Class Size Regulations). This will also provide headroom of circa 2% or 75 places across North Bracknell, to allow for parental preference and in case of further expansion in the future. These two schools have been chosen following a review of all North Bracknell Primary Infant & Junior schools.
5.6There will be sufficient pupil places in South Bracknell with the construction of the new 2FE Jennett’s Park Primary school (420 places) which is currently planed to be open in September 2011.
5.7For the Crowthorne & Sandhurst area the SPP forecasts that the current surplus of places will fall to as low as only 2 places (circa 1% ) in the intake year, therefore we will create 20 additional places at Owlsmoor Primary School increasing the Published Admission Number (“PAN”) from 70 to 90 to meet this need.
Additional Capacity
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Primary Capital Strategy for ChangeReport | 36 KB | DownloadRead as text |
Follow Schools Forum at Bracknell Forest and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 12 Mar 2026 | High Needs Block 2026-27RESOLVED that: i . The High Needs Block deficit budget be set at £11.5 million ii. The local authority take all avail... | Decided | Open |
| 14 Jan 2026 | Early Years Budgets 2026-27RESOLVED that for the 2026-27 financial year the Executive Member for Children, Young People and Learning sets out th... | Approved | Open |
| 14 Jan 2026 | Exclusion of Public and PressRESOLVED that pursuant to Section 100A of the Local Government Act 1972, as amended, and having regard to the public ... | Decided | Open |
| 4 Dec 2025 | Minutes and Matters ArisingIt was agreed that further investigation and clarification was needed, with an update to be brought to the next meeting. | Agreed | Open |
| 4 Dec 2025 | Initial proposals for the 2026-27 Early Years Funding Formula and 2026-27 Early Years BudgetRESOLVED that the Schools Forum; Approves proposed changes to the Deprivation Supplement from April 2026; Approves pr... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.