RESOLVED that 1 The award of contract for the Phase 1 and 2 works at the Holly Spring Schools to the preferred supplier, subject to the final lump sum not exceeding the amount set out in the confidential Appendix, be approved. 2 Approval of the awards of construction contracts for the Crown Wood Phases 2 and 3, Sandy Lane Phase 3, Owlsmoor and Kennel Lane Schools be delegated to the Director of Children and Young People and Learning, subject to the final lump sum not exceeding the amounts set out in the confidential Appendix be approved.
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
2.1That the Executive approves the award of contract for the Phase 1 and 2 works at the Holly Spring Schools to the preferred supplier, subject to the final lump sum not exceeding the amount set out in the confidential Appendix.
2.2That the Executive agrees to delegate approval of the awards of construction contracts for the Crown Wood Phases 2 and 3, Sandy Lane Phase 3, Owlsmoor and Kennel Lane Schools to the Director of Children and Young People and Learning, subject to the final lump sum not exceeding the amounts set out in the confidential Appendix.
Reasons for recommendations
3.1The value of these contracts constitutes a Key Decision and under the Council’s Contract Regulations Executive approval is required.
3.2Delegated approval to award the contracts at recommendation 2.1. is being sought because the programmes for these projects require them to be completed for the start of the new school term in September 2011 and therefore contractually committed during the period when the Executive is not meeting during the local elections in May 2011.
Alternative options considered
4.1Masterplans and options appraisals have been undertaken for all the schools which have been subject of consultation and agreement with the Headteachers and Governing Bodies.
4.2Doing nothing is not an option because the Council has a statutory duty to provide sufficient pupil places.
5 SUPPORTING INFORMATION
Background
5.1In July 2008 the Executive approved the Primary Capital Strategy for Change (PCSfC) for Bracknell Forest, which secured £8.378m of Primary Capital Programme grant. 5.2 The PCSfC originally included an ambitious programme of school transformation works over a 15 year period, however following cancellation of further PCP grant by the coalition government this programme has been reviewed by EC Harris and the Council and re-focussed down to address only the essential works required to meet the Council’s statutory duty to provide sufficient pupil places for September 2011.
5.3The works deemed essential include basic teaching classrooms, accommodation for pupil support, library facilities, ICT suites and specialist subjects some of which is being provided in dual use multi-purpose spaces to reduce the overall floor area requirement and cost. Additional toilets, staff facilities and parking are also being provided where necessary to support the creation of the additional capacity in schools.
5.4The Executive has previously approved the use of nearly £4m of funding for the redevelopment of Kennel Lane School, mainly from DfE grants, most notably the Targeted Capital Fund. This project will bring the schools accommodation into line with its admission numbers and address high priority condition, suitability and access works in the school.
Holly Spring Schools
5.5Holly Spring Infant and Junior schools are being expanded under the PCSfC by one form of entry from 2FE (420 places) up to 3FE (630 places), to meet rising school rolls across North Bracknell.
5.6This work is being implemented in phases over seven years to keep pace with pupil numbers in the schools as they move up from the intake (Reception) year through to Year 6.
5.7Phase 1 and 2 are being implemented together and will provide three additional classrooms for the nursery, reception and year one. Providing accommodation for 60 new pupils, 30 in Reception and 30 in year one. Planning permission has been granted and the work is programmed for completion in September 2011.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo...
Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.