RESOLVED that 1 The outturn capital expenditure and in particular the key variances identified in section 5.6 be noted. 2 The carry forward of £24.389m from the 2010/11 capital programme to 2011/12 including £0.42m relating to projects approved in 2009/10 (see paragraph 5.7) be approved. 3 The financing of capital expenditure as shown in Table 2 be noted. 4 The sum of £350,000 to be added to the Capital Programme in 2011/12 for highway maintenance relating to the additional grant allocated to the Council by Department for Transport (see paragraph 5.11) be approved.
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
a) Notes the outturn capital expenditure and in particular the key variances identified in section 5.6. b) Approves the carry forward of £24.389m from the 2010/11 capital programme to 2011/12 including £0.42m relating to projects approved in 2009/10 (see paragraph 5.7). c) Notes the financing of capital expenditure as shown in Table 2. d) Approves the sum of £350,000 to be added to the Capital Programme in 2011/12 for highway maintenance relating to the additional grant allocated to the Council by Department for Transport (see paragraph 5.11)
Reasons for recommendations
3.1The reasons for the recommendations are set out in section 5 below.
Alternative options considered
4.1Not Applicable
5 SUPPORTING INFORMATION
Additions to Capital Programme
5.1As a result of work undertaken as part of the Final Accounts process it has been necessary to gross up certain budgets where expenditure has been incurred but funded from external contributions from other bodies. As such the Approved Budget for 2010/11 has increased from the previously reported figure of £61.768m to £62.261m. This has no impact on the level of expenditure funded by the Council’s own resources.
Outturn Capital Expenditure
5.2The capital programme for 2010/11 consisted of £62.261m on projects and programmes. The projected outturn is £36.906m (59% of approved expenditure) which is consistent with performance in previous years. These figures remain subject to change, pending external audit. However, no significant movement is anticipated. The capital programme is monitored on a monthly basis by officers and reported formally to the Corporate Management Team on a quarterly basis and through to Members in the Performance Monitoring Reports.
5.3The published capital budget is based on scheme approvals and does not reflect the anticipated cash flow. As part of the capital monitoring for 2010/11 cash budgets were introduced to reflect the spend profile of the capital works. The actual spend is 97% of the cash budget (£37.872m) and highlights the importance of setting cash budgets as well as scheme approvals. Many of the capital schemes are both technically and logistically complex to implement. Issues such as planning approvals, land transfers and inclement weather can all lead to unavoidable delays. In addition, their financial scale requires a lengthy tender process to ensure that best value is obtained prior to letting the works contract. It is therefore extremely difficult to complete such schemes within the financial year in which they are approved. Cash budgets are therefore a more accurate way of monitoring spend and performance.
5.4Table 1 summarises the outturn position for schemes managed by Service Departments based on latest information available. The detailed monitoring sheets are provided at Annexes A-D.
Table 1: Capital outturn for each Service Annexe Service Approved Estimated Carry (Under) budget Outturn forward /Over spend £’000 £’000 £’000 £’000 A Council Wide 6,356 4,439 1,814 -104 A Corporate Services 1,095 584 527 17 B Children, Young People & 40,185 23,657 16,141 -387 Learning C Adult Social Care & Health 1,126 367 759 0 D Environment, Culture & 13,499 7,859 5,148 -492 Communities Total Capital Programme 62,261 36,906 24,389 -966 % spent 59%
5.5The total carry forwards requested by service departments amount to £24.389m and have been reflected in the cash budgets mentioned above. Many of the projects are either close to being completed or are contractually committed and underway.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo...
Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.