RESOLVED that i. the outturn capital expenditure as outlined in Table 1 and detailed in Annex A is noted. ii. the carry forward of £47.334m from the 2023/24 capital programme to 2024/25 is approved including that the Executive RECOMMENDS that Council approves the specific schemes listed in paragraph 5.5. iii. the financing of capital expenditure as shown in Table 2 is noted. iv. the capital virements in para. 5.16 is approved.
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
1.1At its meeting on 22 February 2023, the Council approved a capital programme for 2023/24-2025/26. This report informs Members of the outturn expenditure position, subject to audit, for the financial year 2023/24 and requests approval for the carry forward of the remaining capital programme, the majority of which is committed but not yet spent. The report also sets out how the 2023/24 expenditure is to be financed.
Recommendations
2.1That the Executive:
a) Notes the outturn capital expenditure as outlined in Table 1 and detailed in Annex A b) Approves the carry forward of £47.334m from the 2023/24 capital programme to 2024/25 including recommending that Council approves the specific schemes listed in paragraph 5.5 c) Notes the financing of capital expenditure as shown in Table 2. d) Approves the capital virements in para. 5.16
Reasons for recommendations
3.1The reasons for the recommendations are set out in section 5 below.
Alternative options considered
4.1Not Applicable
5 SUPPORTING INFORMATION
Outturn Capital Expenditure 5.1 The capital programme budget for 2023/24 consisted of £86.168m. The projected outturn is £32.411m (37% of approved budget). These figures remain subject to change, pending external audit. However, no significant movement is anticipated.
5.2Table 1 summarises the outturn position for schemes managed by Directorates based on latest information available, with the detailed schemes listed in Annex A. Unrestricted
Table 1: Capital outturn for each Directorate
Capital Monitoring Out-turn 2023/24
Budgets Variance Total Cash Actual to be from Total Scheme Budgets Expenditure carried Scheme Directorate/Service Budgets 2023/24 2023/24 forward Budgets
Place 32,128 15,632 13,613 12,398 -6,119 Communities 11,984 9,344 9,344 2,629 -11 People - CYPL 25,131 4,067 3,853 21,064 -213 People - ASCHH 16,925 6,345 5,601 11,243 -81
Total 86,168 35,409 32,411 47,334 -6,424
Underspend 5.3 According to Financial Regulations, departments are required to manage their budgets to ensure that the overall department capital programme is not exceeded. As can be seen above the overall capital programme is underspent against budget. However, there are a number of individual variances which are required to be drawn to the attention of Members (>£50,000). The two major areas of underspend relate to projects that are outside the direct control of the Council, namely Town Centre Regeneration and Warfield Memorial Grounds. In both these projects the Council has an agency role that depends significantly on external partners. The most significant areas of underspends are;
Adult Social Care, Health and Housing • Heathlands (Underspend £76k) There remain retention payments to be finalised however the overall spend is within budget and the balance of the contingency can be released as an underspend.
Children, Young People and Learning • Holly Spring Fusion (Underspend £91k) Project reviewed and decision taken to cancel the scheme.
Place • Town Centre Regeneration (Underspend £2m) Further progress on the Town Centre is dependent on both external partners and the current economic cycle. The full budget is not required going forward based on the likely opportunities for development over the next 2 years. As such, £4m of the budget is being surrendered until there is greater clarity on future external investment. • Warfield Memorial Grounds and Pavilion (Underspend £2.1m) This project has been unable to proceed over the last 2 years due to a number of factors beyond the control of the Council. It is proposed to pause this project in light of the current circumstances and surrender the budget allocation (S106 Funding). More details are provided later in the report. Unrestricted
Carry Forwards 5.4 The total carry forwards requested by service departments amount to £49.334m. Many of the projects are either close to being completed or are contractually committed and underway.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo...
Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.