RESOLVED that the Executive: i. Notes the outturn capital expenditure as outlined in Table 1 and detailed in Annex A. ii. Approves the carry forward of £34.114m from the 2022/23 capital programme to 2023/24 including those specific schemes listed in Annexe B. iii. Notes the financing of capital expenditure as shown in Table 2. iv. Notes the 2023/24 Budget amendments identified in para 5.10 relating to the Joint Venture v. Approves the supplementary capital approval of £0.081m for the increased costs associated with the Berkshire Records Office as outlined in para 5.11. vi. Approves the virements requested in para 5.13.
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
1.1At its meeting on 24th February 2022, the Council approved a capital programme for 2022/23-2024/25. This report updates the Executive on the capital outturn expenditure position for 2022/23 and requests approval for the carry forward of the remaining capital programme, the majority of which is committed but not yet spent. The report also sets out how the 2022/23 expenditure is to be financed.
Recommendations
2.1That the Executive:
a) Notes the outturn capital expenditure as outlined in Table 1 and detailed in Annex A b) Approves the carry forward of £34.114m from the 2022/23 capital programme to 2023/24 including those specific schemes listed in Annexe B c) Notes the financing of capital expenditure as shown in Table 2. d) To note the 2023/24 Budget amendments identified in para 5.10 relating to the Joint Venture e) Approve the supplementary capital approval of £0.081m for the increased costs associated with the Berkshire Records Office as outlined in para 5.11 f) Approve the virements requested in para 5.13
Reasons for recommendations
3.1The reasons for the recommendations are set out in section 5 below.
Alternative options considered
4.1Not Applicable
5 SUPPORTING INFORMATION
Outturn Capital Expenditure 5.1 The capital programme budget for 2022/23 consisted of £58.792m on projects and programmes. The projected outturn is £23.701m (40% of approved budget). These figures remain subject to change, pending external audit. However, no significant movement is anticipated.
5.2Table 1 summarises the outturn position for schemes managed by Directorates based on latest information available. Unrestricted
Underspend 5.3 According to Financial Regulations, departments are required to manage their budgets to ensure that the overall department capital programme is not exceeded. As can be seen above the overall capital programme is underspent against budget. However, there are a number of individual variances which are required to be drawn to the attention of Members (>£50,000). The most significant areas of underspends are;
Adult Social Care, Health and Housing • Heathlands (Underspend £250k) There remain retention payments to be finalised however the overall spend is within budget and the balance of the contingency can be released as an underspend.
Children, Young People and Learning • Warfield West Primary (Underspend £334k) Unused contingency and an element of planned highway works not required. • Ascot Heath Schools Amalgamation (Underspend £253k) Unused contingency and some planned works not required as project proceeded.
Carry Forwards 5.4 The total carry forwards requested by service departments amount to £34.114m. Many of the projects are either close to being completed or are contractually committed and underway. A list of those schemes that had requested a budget carry- forward from 2021/22 into 2022/23 and have yet to see any expenditure incurred and for which a further carry forward into 2023/24 has been requested are summarised in Annexe B (only schemes relating to Central and Delivery Directorate fall into this category in 2022/23).
5.5The most significant carry-forwards that have been funded from Council resources (as compared with grant funding which is automatically carried forward) are as follows:
• Various IT Schemes (£0.4m) – Budgets have been largely pooled into three main areas – Desktop, Infrastructure and Transformation. During the year Unrestricted
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo...
Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.