RESOLVED that i. the outturn capital expenditure as outlined in Table 1 and detailed in Annex A is noted. ii. the carry forward of £21.713m from the 2021/22 capital programme to 2022/23 including those specific schemes listed in Annexe B is approved. iii. the financing of capital expenditure as shown in Table 3 is noted. iv. the additional High Needs Provision Capital Allocation grant as noted in para 5.11 is approved .
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
1.1At its meeting on 28th February 2021, the Council approved a capital programme for 2021/22-2023/24. This report updates the Executive on the capital outturn expenditure position for 2021/22 and requests approval for the carry forward of the remaining capital programme, the majority of which is committed but not yet spent. The report also sets out how the 2021/22 expenditure is to be financed.
Recommendations
2.1That the Executive:
a) Notes the outturn capital expenditure as outlined in Table 1 and detailed in Annex A b) Approves the carry forward of £21.713m from the 2021/22 capital programme to 2022/23 including those specific schemes listed in Annexe B c) Notes the financing of capital expenditure as shown in Table 3. d) To approve the additional High Needs Provision Capital Allocation grant as noted in para 5.11
Reasons for recommendations
3.1The reasons for the recommendations are set out in section 5 below.
Alternative options considered
4.1Not Applicable
5 SUPPORTING INFORMATION
Outturn Capital Expenditure 5.1 The capital programme budget for 2021/22 consisted of £52.217m on projects and programmes. The projected outturn is £27.221m (52% of approved budget). These figures remain subject to change, pending external audit. However, no significant movement is anticipated.
5.2Table 1 summarises the outturn position for schemes managed by Directorates based on latest information available. Table 1: Capital outturn for each Directorate Budget Expenditure C/Fwd Underspend £’000 £’000 £’000 £’000 Central Departments 26,062 11,956 11,036 -3,070 Delivery 5,213 3,030 2,177 -7 People 20,942 12,236 8,499 -206 TOTAL 52,217 27,221 25,007 -3,283 5.3 According to Financial Regulations, departments are required to manage their budgets to ensure that the overall department capital programme is not exceeded. As can be seen above the overall capital programme is underspent against budget. However, there are a number of individual variances which are required to be drawn to the attention of Members (>£50,000). The most significant areas of underspends are;
A3095 Improvement Scheme (£2.8m) – This scheme needed to proceed in 2021/22 in order to facilitate a wider development. The scheme was to be funded from S106 which at the time of the 2021/22 Budget approval had not been secured. As such Council agreed to pre-fund this from Council resources, however the necessary S106 funding was secured before the end of the financial year and as such the scheme was completed within budget.
College Town Amalgamation (£0.068m) – Project completed within budget.
5.4The total carry forwards requested by service departments amount to £21.713m. Many of the projects are either close to being completed or are contractually committed and underway. A list of those schemes that had requested a budget carry-forward from 2020/21 into 2021/22 and have yet to see any expenditure incurred and for which a further carry forward into 2022/23 has been requested are summarised in Annexe B.
5.5The most significant carry-forwards that have been funded from Council resources (as compared with grant funding which is normally automatically carried forward) are as follows:
Various IT Schemes (£0.5m) – Budgets have been largely pooled into three main areas – Desktop, Infrastructure and Transformation. The impact of COVID has had a significant impact on the way the Council works digitally – with home working becoming a norm over the last 18 months – this has led to a review of IT expenditure priorities and unspent budget will be used to focus on the new priorities.
Town Centre Redevelopment (£6.1m) – The funding set aside for the redevelopment of the Town Centre through various schemes will be drawn down as the programme continues to roll out. Given the difficult economic over the last 2 years the continued redevelopment of the town centre is demand-led and driven by factors largely outside of the Council’s control.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo...
Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.